SiteSorted
Electrical · Canada

FLHA for electrical equipment inspection

Provincial OHS law requires hazards to be assessed and controlled before work starts. A field level hazard assessment (FLHA) for electrical equipment inspection is done on site at the start of the shift and again whenever conditions change.

It lists the tasks, hazards and controls, and every worker signs on before starting and signs off at the end of the shift. The main hazards are electric shock from live wiring, electric shock from cords and power tools, lifting and carrying heavy loads and working in an occupied home or building.

FLHA example: electrical equipment inspection

This is a complete FLHA for electrical equipment inspection, with 5 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.

Field Level Hazard Assessment (FLHA)
Portable electrical equipment inspection · Electrical · Example
Document FLHA-001 · Rev 1

Job steps, hazards and controls

#Job stepHazardsRisk beforeControlsRisk after
1Agree with the client which items to test and when they can be unplugged
  • Working in an occupied home or building
Medium
  • Plan noisy, dusty or risky work for when the building is empty. Elimination
  • Close off the work area with barriers, plastic sheeting or locked doors, and put up signs. Engineering (guarding)
  • Keep fire exits and paths clear at all times. Administrative
  • Tell occupants before you turn off power, water or gas, and before noisy or dusty work. Administrative
  • Lock away tools, chemicals and materials each day, out of reach of children. Administrative
  • Clean up dust and debris at the end of each day. Administrative
Low
2Visually inspect each lead and tool for damage before testing
  • Electric shock from cords and power tools
  • Cuts from sharp edges
High
  • Use battery-powered tools where you can. Substitution
  • Use GFCI protection on all temporary power and portable tools. Engineering
  • Keep cords off the ground and out of water, using stands or hooks. Engineering
  • Check cords, plugs and tools before every use. Tag out and remove anything damaged. Administrative
  • Do not use tools in rain or wet areas unless they are rated for it. Administrative
  • Wear safety boots and dry gloves. PPE
  • Deburr or cover sharp edges, and fit edge protectors on exposed sheet metal. Engineering
  • Use knives with retractable or self-retracting blades. Engineering
  • Cut away from your body and keep your other hand clear. Administrative
  • Put used blades in a blade bin or sharps container. Administrative
  • Use two people to handle large sheets of metal or glass. Administrative
  • Wear cut-resistant gloves and long sleeves. PPE
Low
3Test each item with the tester, keeping hands clear during the leakage and insulation tests
  • Electric shock from live wiring
Critical
  • Isolate the power before any work. Do not work live. Elimination
  • Lock out and tag the isolation point with your own personal lock and danger tag. Engineering (guarding)
  • Test before you touch: prove dead at the point of work with a tested voltage tester. Engineering
  • Only licensed electricians do electrical work, to the Canadian Electrical Code and provincial rules. Administrative
  • Check for back feeds from solar, batteries and generators that can keep a circuit live after the main switch is off. Administrative
  • If energized work cannot be avoided, use a permit, a safety observer and insulated tools, following CSA Z462. Administrative
  • Wear insulated gloves, arc-rated clothing and a face shield when testing or working near live parts. PPE
Medium
4Tag items that pass, and take failed items out of service with a danger tag
  • Electric shock from cords and power tools
High
  • Electric shock from cords and power tools: see step 2 for the full controls Administrative
Low
5Coil leads, keep walkways clear and record results
  • Slips and trips
  • Lifting and carrying heavy loads
High
  • Plan walkways and keep them clear of materials, hoses and leads. Elimination
  • Run leads and hoses overhead on hooks or stands, or along walls, not across walkways. Engineering
  • Fill or cover holes, and lay boards or mats on muddy access paths. Engineering
  • Clean up offcuts, packaging and spills as you go, not at the end of the day. Administrative
  • Keep work areas, stairs and access paths well lit. Administrative
  • Wear safety boots with good grip, laced up. PPE
  • Plan to avoid carrying: have materials delivered, and old items picked up, as close as possible to where they are used. Elimination
  • Use lighter or smaller loads: order smaller bags and shorter lengths, and drain or break down old items before moving them. Substitution
  • Use trolleys, pallet jacks, hoists, vacuum lifters or equipment instead of carrying by hand. Engineering
  • Use a two-person lift for anything heavy, long or awkward. Plan the route first and clear it. Administrative
  • Keep the load close, back straight and no twisting. Turn with your feet. Administrative
  • Rotate tasks and take breaks on long lifting jobs. Administrative
  • Wear gloves for grip and safety boots to protect your feet. PPE
Medium

PPE

CSA green triangle safety boots (CSA Z195)Safety glasses (CSA Z94.3)N95 respiratorWork glovesCut-resistant glovesRubber insulating glovesArc flash PPE (CSA Z462)

Plant and equipment

Electrical test meter

Permits and plans

Lockout permit

Emergency

Call 911. Add the nearest hospital, the muster point and the first aid attendant for your site.

Sign-off

Supervisor and every worker sign to confirm they have read and understood this FLHA, then sign off at the end of the shift.

Free FLHA template for electrical equipment inspection

Word (.docx) and PDF, Letter landscape, no email needed. Fill in your site details, then print or send it.

Make yours in 2 minutes

Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.

Start this FLHA

Pre-start checklist for electrical equipment inspection

Tick these off before work starts. They come from the hazards, permits and equipment in this job.

The safe sequence of work

  1. Agree with the client which items to test and when they can be unplugged
  2. Visually inspect each lead and tool for damage before testing
  3. Test each item with the tester, keeping hands clear during the leakage and insulation tests
  4. Tag items that pass, and take failed items out of service with a danger tag
  5. Coil leads, keep walkways clear and record results

Hazards to watch on electrical equipment inspection

The hazards most specific to this job, and the step where each one comes up.

Step 2, 4Electric shock from cords and power toolsDamaged cords, plugs or tools, or water near power, give the user an electric shock.
Step 1Working in an occupied home or buildingResidents, staff or children wander into the work area and get hurt, or the work blocks exits or cuts off power or water while people are inside.
Step 5Slips and tripsWorkers slip on wet or muddy ground or trip on leads, offcuts and uneven ground, causing sprains, broken bones or head injuries.
Step 2Cuts from sharp edgesSheet metal, glass, blades, cable tray and offcuts cut hands and arms.
Step 3Electric shock from live wiringContact with energized wires, electrical panels or equipment gives an electric shock or arc flash burn that can kill.
Step 5Lifting and carrying heavy loadsLifting, carrying, pushing or twisting with heavy or awkward loads strains the back, shoulders or knees.
Almost certainLikelyPossibleUnlikelyRareHow bad it could be: First aid only to FatalityBA
Highest risk on electrical equipment inspection: Critical before controls (B), down to Medium after controls (A), on the Canada 5 by 5 risk matrix (possible and fatality becomes unlikely and lost time injury).

What changes on your site

This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):

  • Could anyone fall 3 metres or more, or fall any distance into machinery, water, a hazardous substance or through an opening?
  • Will anyone use a ladder or stepladder?
  • Will anyone work on a roof?
  • Is there a fragile roof, skylight or clear roof sheet?
  • Will you use a scaffold or mobile tower?

Why FLHAs get rejected

Prime contractors and COR auditors send documents back for these reasons. This example avoids them, but check yours too.

  • End of shift boxes already say "None" when the form was signed at the start of the shift.
  • One FLHA reused for days or weeks, or a "review by" date a month away, when the work and conditions change daily.
  • No time of assessment and no record of any revision, which Alberta s.7(3) requires.
  • Workers signed that they "read" it, but nothing shows they took part, which Alberta s.8(1) requires.
  • Work at height with no fall protection plan where the province requires one, or no written rescue procedure for workers using fall arrest.
  • Permits or locates required on site but no permit or ticket numbers recorded.
  • No re-assessment entry after an obvious change such as weather, a new task or a new crew member.

Rules by province for electrical equipment inspection

Province or territoryKey local ruleRegulator
OntarioFall protection (O. Reg. 213/91 s.26) applies at a fall of more than 3 m, more than 1.2 m where the work area is used as a path for a wheelbarrow or similar equipment, and at any height into operating machinery, water or other liquid, a hazardous substance, or through an opening.Ontario Ministry of Labour, Immigration, Training and Skills Development
British ColumbiaFall protection is required where a fall of 3 m or more may occur (s.11.2). A written fall protection plan is required at 7.5 m or more where there are no permanent guardrails (s.11.3).WorkSafeBC
AlbertaA hazard assessment must be done before work begins, and before a new work site is built (OHS Code s.7(1)). The results must be written down with the controls (s.7(2)).Alberta Occupational Health and Safety
QuebecGuardrails (Safety Code s.2.9.1, as amended by Decret 63-2025) are needed where a worker could fall into liquid or a hazardous substance, onto moving parts or dangerous equipment, 1.2 m or more when using a vehicle, 1.5 m or more when handling a load, and more than 3 m in all other cases.CNESST (Commission des normes, de l'equite, de la sante et de la securite du travail)
ManitobaA prime contractor is required whenever more than one employer or self employed person works on the site at the same time (Act s.7).Manitoba Workplace Safety and Health Branch
SaskatchewanAn occupational health committee is required at 10 or more workers of one employer (Act s.3-22).Saskatchewan Ministry of Labour Relations and Workplace Safety, OHS Division
Nova ScotiaWorkers must be trained in fall protection before using it or working in, supervising or planning work in a fall protection area, with a refresher at least every 3 years (WHSR s.21.19).Nova Scotia Department of Labour, Skills and Immigration, Safety Branch (OHS)
New BrunswickFall protection is needed from 3 m above water or the nearest permanent safe level (Reg 91-191 s.49(1)(a)(i)).WorkSafeNB
Newfoundland and LabradorGive written notice to the minister before starting a construction project that will last 30 days or more, with the site, location, type of work and number of workers (Regs s.8).Government Services, Occupational Health and Safety Division
Prince Edward IslandFall protection is needed from 3 m above the nearest safe surface or water (Fall Protection Regulations s.2(1)(a)).Workers Compensation Board of PEI, OHS Division
YukonEvery employer must do hazard assessments with the committee, representative or workers, and redo them after significant changes or incidents (Regs s.1.03.01).Yukon Workers' Safety and Compensation Board
Northwest TerritoriesFall protection is needed from 3 m, or lower if there is a risk of injury (s.119(1)). Guardrails are needed for falls of 1.2 m to 3 m at permanent work sites (s.119(2)).Workers' Safety and Compensation Commission (WSCC)
NunavutNo 911. To reach the RCMP in an emergency, dial your community's first three digits then 1111 (Iqaluit: 979-1111). Put the local fire, ambulance and RCMP numbers on every FLHA.Workers' Safety and Compensation Commission (WSCC)

Questions

Do I need an FLHA for electrical equipment inspection?

Provincial OHS law requires hazards to be assessed and controlled before work starts. A field level hazard assessment (FLHA) for electrical equipment inspection is done on site at the start of the shift and again whenever conditions change.

Who signs the FLHA?

The supervisor and every worker take part in the assessment and sign on before work starts, then sign off at the end of the shift. Review it and re-sign whenever the task or conditions change.

How long do I keep it?

Keep completed hazard assessments for at least 3 years (COR auditors sample the last 12 months). Review this FLHA and re-sign whenever the task, crew or conditions change.

What PPE is needed for electrical equipment inspection?

Usually CSA green triangle safety boots (CSA Z195), Safety glasses (CSA Z94.3), N95 respirator, Work gloves, Cut-resistant gloves, Rubber insulating gloves, Arc flash PPE (CSA Z462). The site rules may add more, so check with the general contractor.

More electrical FLHAs

Toolbox talks for this job

Blank FLHA template: free FLHA templates. Also for other countries: Australia (SWMS) · United Kingdom (RAMS) · United States (JHA)

Sources