Method statement for irrigation installation

You must assess the risks of irrigation installation and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.

RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are hitting underground services, being hit by mobile plant, electric shock from live wiring and lifting and carrying heavy loads.

RAMS example: irrigation installation

This is a complete RAMS for irrigation installation, with 5 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.

Risk Assessment and Method Statement (RAMS)
Irrigation installation · Landscaping · Example
Document RAMS-001 · Rev 1

Risk assessment

#ActivityHazardsWho might be harmedRisk beforeControlsRisk after
1Get utility plans and mark trench lines
  • Hitting underground services
Workers, PublicVery high (15)
  • Keep machine buckets well clear of marked services and use a spotter. Isolate
  • Do a CAT and Genny scan before digging and mark services on the ground. Control (engineering)
  • Hand dig trial holes to find services before machine digging (safe digging practice). Control (engineering)
  • Get utility plans before digging and check them against what you see on site. Control (procedures)
  • Keep plans or locate tickets on site and check them again if the work area grows. Control (procedures)
  • If you hit a service, stop, get everyone clear, and call the owner and emergency services. Control (procedures)
  • Wear safety boots, gloves and hi-vis when digging. PPE
Medium (5)
2Dig shallow trenches by hand or with a trencher
  • Lifting and carrying heavy loads
  • Being hit by mobile plant
Workers, Visitors, PublicVery high (15)
  • Plan to avoid carrying: have materials delivered, and old items picked up, as close as possible to where they are used. Eliminate
  • Use lighter or smaller loads: order smaller bags and shorter lengths, and drain or break down old items before moving them. Reduce / substitute
  • Use trolleys, pallet jacks, hoists, vacuum lifters or plant instead of carrying by hand. Control (engineering)
  • Use a two-person lift for anything heavy, long or awkward. Plan the route first and clear it. Control (procedures)
  • Keep the load close, back straight and no twisting. Turn with your feet. Control (procedures)
  • Rotate tasks and take breaks on long lifting jobs. Control (procedures)
  • Wear gloves for grip and safety boots to protect your feet. PPE
  • Separate people and plant with barriers, exclusion zones and marked walkways. Isolate
  • Use plant with working reversing alarms, cameras and lights. Control (engineering)
  • Have a traffic management plan showing plant routes, loading areas and pedestrian paths. Control (procedures)
  • Use a spotter when reversing or working near people. Control (procedures)
  • Make eye contact with the operator before going near. Stay out of the swing radius. Control (procedures)
  • Operators hold a CPCS, NPORS or equal card for the plant they use. Control (procedures)
  • Do a pre-start check on each machine every day and record it. Control (procedures)
  • Wear hi-vis clothing and a hard hat. PPE
Medium (6)
3Lay pipe and glue joints with ventilation
  • Hazardous chemicals
Workers, OccupantsMedium (9)
  • Choose the least harmful product that does the job, for example water-based instead of solvent-based. Reduce / substitute
  • Use chemicals in well-ventilated areas, or use fans and extraction in closed rooms. Control (engineering)
  • Do a COSHH assessment and read the Safety Data Sheet (SDS) before use. Control (procedures)
  • Keep chemicals in labelled containers. Never decant into drink bottles. Control (procedures)
  • Store chemicals away from heat, food and drink, and keep products that react with each other apart. Control (procedures)
  • Have eye wash and a spill kit nearby, and wash hands before eating. Control (procedures)
  • Wear chemical-resistant gloves and safety glasses or goggles as listed on the SDS. PPE
  • Use a respirator with the right cartridge if the SDS calls for one. PPE
Medium (6)
4Connect the controller, getting a qualified electrician for any new power
  • Electric shock from live wiring
Workers, OccupantsVery high (15)
  • Isolate the power before any work. Do not work live. Eliminate
  • Lock out and tag the isolation point with your own personal lock and danger tag. Isolate
  • Prove dead at the point of work with an approved voltage indicator (GS38), and prove the tester before and after. Control (engineering)
  • Only competent, qualified electricians do electrical work, following a safe isolation procedure. Control (procedures)
  • Check for back feeds from solar, batteries and generators that can keep a circuit live after the main switch is off. Control (procedures)
  • If live work cannot be avoided, use a permit, a safety observer and insulated tools. Control (procedures)
  • Wear insulated gloves, arc-rated clothing and a face shield when testing or working near live parts. PPE
Medium (5)
5Test, backfill and clean up
  • Pressure testing
  • Poor housekeeping and waste
Workers, Occupants, VisitorsMedium (8)
  • Test with water instead of air or gas where the system allows it. Never put water in refrigerant pipework, which is tested with dry nitrogen. Reduce / substitute
  • Keep people out of the test area with signs and barriers. Isolate
  • Use a calibrated gauge and a relief valve set to protect the system. Control (engineering)
  • Test to the pressure the system calls for and hold it for the set time. Never go over. Control (procedures)
  • Release the pressure fully before tightening anything or fixing leaks. Control (procedures)
  • Wear safety glasses or a face shield. PPE
  • Order materials to size and send packaging back where you can. Eliminate
  • Put skips and waste chutes close to the work. Control (engineering)
  • Clean as you go, and do a full clean up at the end of each day. Control (procedures)
  • Keep exits, stairs and walkways clear at all times. Control (procedures)
  • Stack materials neatly on level ground, away from edges. Control (procedures)
  • Use a registered waste carrier and keep waste transfer notes for at least 2 years. Keep hazardous waste such as asbestos separate, with consignment notes (special waste in Scotland). Control (procedures)
  • Wear gloves when handling waste. PPE
Low (4)

Method statement: sequence of work

  1. Get utility plans and mark trench lines
  2. Dig shallow trenches by hand or with a trencher
  3. Lay pipe and glue joints with ventilation
  4. Connect the controller, getting a qualified electrician for any new power
  5. Test, backfill and clean up

PPE

Safety bootsRigger glovesSun protection (sunscreen and neck cover)Hi-vis vestSafety helmetChemical-resistant glovesSafety gogglesHalf-mask respirator (P3 filters)CoverallsSafety glassesFace shield

Plant and equipment

Hand toolsExcavator (360): CPCS or NPORS excavator cardPower drill

Emergency

Call 999. Add the nearest A&E, the assembly point and the first aider for your site.

Sign-off

Supervisor and every worker sign to confirm they have read and understood this RAMS.

Free RAMS template for irrigation installation

Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.

Make yours in 2 minutes

Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.

Start this RAMS

Pre-start checklist for irrigation installation

Tick these off before work starts. They come from the hazards, permits and equipment in this job.

The safe sequence of work

  1. Get utility plans and mark trench lines
  2. Dig shallow trenches by hand or with a trencher
  3. Lay pipe and glue joints with ventilation
  4. Connect the controller, getting a qualified electrician for any new power
  5. Test, backfill and clean up

Hazards to watch on irrigation installation

The hazards most specific to this job, and the step where each one comes up.

Step 5Pressure testingA pipe, fitting or cap fails under test pressure and blows apart, hitting people nearby.
Step 1Hitting underground servicesDigging, drilling or driving pegs hits a buried power cable, gas pipe or water main, causing electrocution, explosion or flooding.
Step 2Being hit by mobile plantExcavators, loaders, telehandlers and trucks run over or crush workers, especially when reversing or slewing.
Step 3Hazardous chemicalsGlues, sealants, solvents, acids, cleaners and cement burn skin and eyes or cause breathing problems and poisoning.
Step 4Electric shock from live wiringContact with live wires, distribution boards or equipment gives an electric shock or arc flash burn that can kill.
Step 2Lifting and carrying heavy loadsLifting, carrying, pushing or twisting with heavy or awkward loads strains the back, shoulders or knees.
Very likelyLikelyPossibleUnlikelyVery unlikelyHow bad it could be: Negligible to FatalBA
Highest risk on irrigation installation: Very high before controls (B), down to Medium after controls (A), on the United Kingdom 5 by 5 risk matrix (possible and fatal becomes unlikely and lost time injury).

What changes on your site

This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):

  • Will anyone work at height, anywhere a fall could hurt them?
  • Will anyone use a ladder or stepladder?
  • Will anyone work on a roof?
  • Is there a fragile roof, skylight or clear roof sheet?
  • Will you use a scaffold or mobile tower?

Licences and legal requirements in United Kingdom

Equipment on this job that needs a licence, ticket or training:

  • Excavator (360): CPCS or NPORS excavator card

Employers must assess the risks of their work and record the significant findings (required where you employ 5 or more people). On CDM projects, contractors give their RAMS to the principal contractor before starting, and brief the workers on it.

Rules that apply: HSE HSG47 Avoiding danger from underground services; Manual Handling Operations Regulations 1992; CDM Regulations 2015 and PUWER 1998; COSHH Regulations 2002; Electricity at Work Regulations 1989; Pressure Systems Safety Regulations 2000.

Why RAMS get rejected

Principal contractors send documents back for these reasons. This example avoids them, but check yours too.

  • The method statement is only a list of headings that repeats the risk table and never says how the work is done.
  • The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
  • Residual risk is still High after controls with no extra measures or explanation.
  • It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
  • Work on an older building with no reference to an asbestos survey.
  • Plant and access equipment listed with no inspection, thorough examination or competence evidence.
  • No briefing record, no revision history, or no named supervisor.

Questions

Do I need RAMS for irrigation installation?

You must assess the risks of irrigation installation and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.

Who signs the RAMS?

The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.

How long do I keep it?

Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.

What PPE is needed for irrigation installation?

Usually Safety boots, Rigger gloves, Sun protection (sunscreen and neck cover), Hi-vis vest, Safety helmet, Chemical-resistant gloves, Safety goggles, Half-mask respirator (P3 filters), Coveralls, Safety glasses, Face shield. The site rules may add more, so check with the principal contractor.