Method statement for surface water drainage installation

You must assess the risks of surface water drainage installation and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.

RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are silica dust from concrete, brick, stone and tiles, hitting underground services, trench or excavation collapse and being hit by mobile plant.

RAMS example: surface water drainage installation

This is a complete RAMS for surface water drainage installation, with 5 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.

Risk Assessment and Method Statement (RAMS)
Install surface water drainage · Excavation and earthworks · Example
Document RAMS-001 · Rev 1

Risk assessment

#ActivityHazardsWho might be harmedRisk beforeControlsRisk after
1Get utility plans and mark the pipe run
  • Hitting underground services
Workers, PublicVery high (15)
  • Keep machine buckets well clear of marked services and use a spotter. Isolate
  • Do a CAT and Genny scan before digging and mark services on the ground. Control (engineering)
  • Hand dig trial holes to find services before machine digging (safe digging practice). Control (engineering)
  • Get utility plans before digging and check them against what you see on site. Control (procedures)
  • Keep plans or locate tickets on site and check them again if the work area grows. Control (procedures)
  • If you hit a service, stop, get everyone clear, and call the owner and emergency services. Control (procedures)
  • Wear safety boots, gloves and hi-vis when digging. PPE
Medium (5)
2Cut hard surfaces with water suppression
  • Silica dust from concrete, brick, stone and tiles
  • Saw cuts and kickback
  • Loud noise
Workers, People nearbyVery high (20)
  • Order materials cut to size, or use low-dust methods such as score and snap or a block splitter. Reduce / substitute
  • Cut outdoors or in a separate area, with other people well away and upwind. Isolate
  • Use water on the blade or on-tool dust extraction connected to an H-class vacuum. Control (engineering)
  • Clean up with a vacuum or wet methods. Never dry sweep or use compressed air. Control (procedures)
  • Do a COSHH assessment and keep exposure below the workplace exposure limit (0.1 mg/m3 respirable crystalline silica, 8 hours). Control (procedures)
  • Workers regularly exposed to silica dust get health surveillance (COSHH reg 11, HSE G404). Control (procedures)
  • Wear a fit-tested FFP3 mask. PPE
  • Keep blade guards fitted and working, and use the riving knife on table saws. Control (engineering)
  • Use push sticks and clamps, and support long pieces so they do not pinch the blade. Control (engineering)
  • Use a sharp, undamaged blade made for the material. Control (procedures)
  • Stand to one side of the blade line, out of the kickback path. Control (procedures)
  • Let the blade stop fully before reaching in or putting the saw down. Control (procedures)
  • Use quieter tools and methods, such as cut-to-size materials, low-noise machines and battery tools. Reduce / substitute
  • Keep noisy plant away from work areas, and use screens or distance between the noise and people. Isolate
  • Keep tools maintained and use mufflers on compressors and generators. Control (engineering)
  • Limit time on noisy tools and rotate workers. Control (procedures)
  • If you have to shout to be heard by someone 2 metres away, the noise is probably 85 dB(A) or more: wear hearing protection. Control (procedures)
  • Assess noise. At 85 dB(A) or more, hearing protection is required and the zone must be marked. Control (procedures)
Medium (8)
3Dig the trench and pits, protecting edges
  • Trench or excavation collapse
  • Being hit by mobile plant
  • Falling through a floor opening or void
Workers, Visitors, PublicVery high (15)
  • Use methods that keep people out of the trench, such as directional boring or working from the surface. Eliminate
  • Barricade or cover the excavation so people and plant cannot fall in. Isolate
  • Support or batter back the sides of any excavation where collapse could happen. Use trench boxes or sheet piling for deeper trenches. Control (engineering)
  • Keep spoil, materials and plant at least 1 metre back from the edge. Control (engineering)
  • Provide a safe way in and out, such as a ladder near where people work. Control (engineering)
  • Inspect the excavation at the start of each shift and after rain or anything that could weaken it. Record it. Control (procedures)
  • Separate people and plant with barriers, exclusion zones and marked walkways. Isolate
  • Use plant with working reversing alarms, cameras and lights. Control (engineering)
  • Have a traffic management plan showing plant routes, loading areas and pedestrian paths. Control (procedures)
  • Use a spotter when reversing or working near people. Control (procedures)
  • Make eye contact with the operator before going near. Stay out of the swing radius. Control (procedures)
  • Cover every hole and penetration with a fixed, secured cover marked "HOLE" or "DANGER". Isolate
  • Put guardrails with toe boards around stairwells, lift shafts, voids and open edges. Isolate
  • Install stairs early and fit temporary handrails as soon as they go in. Control (engineering)
  • Never remove a cover or guardrail without approval. Put it back straight away. Control (procedures)
  • Inspect covers and barriers daily and after other trades have been through. Control (procedures)
Medium (5)
4Lay pipe to grade and set pits
  • Lifting and carrying heavy loads
  • Hazardous chemicals
Workers, OccupantsHigh (12)
  • Plan to avoid carrying: have materials delivered, and old items picked up, as close as possible to where they are used. Eliminate
  • Use lighter or smaller loads: order smaller bags and shorter lengths, and drain or break down old items before moving them. Reduce / substitute
  • Use trolleys, pallet jacks, hoists, vacuum lifters or plant instead of carrying by hand. Control (engineering)
  • Use a two-person lift for anything heavy, long or awkward. Plan the route first and clear it. Control (procedures)
  • Keep the load close, back straight and no twisting. Turn with your feet. Control (procedures)
  • Rotate tasks and take breaks on long lifting jobs. Control (procedures)
  • Wear gloves for grip and safety boots to protect your feet. PPE
  • Choose the least harmful product that does the job, for example water-based instead of solvent-based. Reduce / substitute
  • Use chemicals in well-ventilated areas, or use fans and extraction in closed rooms. Control (engineering)
  • Do a COSHH assessment and read the Safety Data Sheet (SDS) before use. Control (procedures)
  • Keep chemicals in labelled containers. Never decant into drink bottles. Control (procedures)
  • Store chemicals away from heat, food and drink, and keep products that react with each other apart. Control (procedures)
  • Have eye wash and a spill kit nearby, and wash hands before eating. Control (procedures)
  • Wear chemical-resistant gloves and safety glasses or goggles as listed on the SDS. PPE
  • Use a respirator with the right cartridge if the SDS calls for one. PPE
Medium (6)
5Backfill, compact and reinstate surfaces
  • Hand-arm and whole-body vibration
  • Loud noise
  • Poor housekeeping and waste
Workers, People nearby, VisitorsHigh (12)
  • Use low-vibration tools and methods, such as a breaker on an excavator instead of a hand jackhammer. Reduce / substitute
  • Keep tools sharp and well maintained, and use anti-vibration handles and seats. Control (engineering)
  • Limit trigger time using the HSE vibration calculator to stay below the exposure action value, and rotate workers. Control (procedures)
  • Keep hands warm and dry, and take regular breaks. Control (procedures)
  • Report tingling, numbness or white fingers early. Control (procedures)
  • Wear earplugs or earmuffs rated for the noise. PPE
  • Loud noise: see step 2 for the full controls Control (procedures)
  • Order materials to size and send packaging back where you can. Eliminate
  • Put skips and waste chutes close to the work. Control (engineering)
  • Clean as you go, and do a full clean up at the end of each day. Control (procedures)
  • Keep exits, stairs and walkways clear at all times. Control (procedures)
  • Stack materials neatly on level ground, away from edges. Control (procedures)
  • Use a registered waste carrier and keep waste transfer notes for at least 2 years. Keep hazardous waste such as asbestos separate, with consignment notes (special waste in Scotland). Control (procedures)
Medium (6)

Method statement: sequence of work

  1. Get utility plans and mark the pipe run
  2. Cut hard surfaces with water suppression
  3. Dig the trench and pits, protecting edges
  4. Lay pipe to grade and set pits
  5. Backfill, compact and reinstate surfaces

PPE

Safety bootsHi-vis vestSafety glassesRigger glovesEar defendersHalf-mask respirator (P3 filters)FFP3 dust maskSafety helmetChemical-resistant glovesSafety gogglesCoveralls

Plant and equipment

Excavator (360): CPCS or NPORS excavator cardWacker plateHand toolsCut-off saw (Stihl saw)

Permits and plans

Permit to dig

Emergency

Call 999. Add the nearest A&E, the assembly point and the first aider for your site.

Sign-off

Supervisor and every worker sign to confirm they have read and understood this RAMS.

Free RAMS template for surface water drainage installation

Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.

Make yours in 2 minutes

Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.

Start this RAMS

Pre-start checklist for surface water drainage installation

Tick these off before work starts. They come from the hazards, permits and equipment in this job.

The safe sequence of work

  1. Get utility plans and mark the pipe run
  2. Cut hard surfaces with water suppression
  3. Dig the trench and pits, protecting edges
  4. Lay pipe to grade and set pits
  5. Backfill, compact and reinstate surfaces

Hazards to watch on surface water drainage installation

The hazards most specific to this job, and the step where each one comes up.

Step 3Trench or excavation collapseThe trench walls cave in and bury or crush a worker. Any excavation can collapse, however shallow. Sides must be supported or battered back wherever a collapse could hurt someone.
Step 5Hand-arm and whole-body vibrationLong periods on jackhammers, grinders, compactors or riding plant cause white finger, numbness and back damage.
Step 1Hitting underground servicesDigging, drilling or driving pegs hits a buried power cable, gas pipe or water main, causing electrocution, explosion or flooding.
Step 3Falling through a floor opening or voidA worker steps into an open hole, stairwell, lift shaft or penetration and falls to the level below.
Step 3Being hit by mobile plantExcavators, loaders, telehandlers and trucks run over or crush workers, especially when reversing or slewing.
Step 2Saw cuts and kickbackCircular saws, drop saws and table saws cut fingers and hands or throw material back at the user.
Very likelyLikelyPossibleUnlikelyVery unlikelyHow bad it could be: Negligible to FatalBA
Highest risk on surface water drainage installation: Very high before controls (B), down to Medium after controls (A), on the United Kingdom 5 by 5 risk matrix (likely and fatal becomes unlikely and major injury).

What changes on your site

This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):

  • Will anyone work at height, anywhere a fall could hurt them?
  • Will anyone use a ladder or stepladder?
  • Will anyone work on a roof?
  • Is there a fragile roof, skylight or clear roof sheet?
  • Will you use a scaffold or mobile tower?

Licences and legal requirements in United Kingdom

Equipment on this job that needs a licence, ticket or training:

  • Excavator (360): CPCS or NPORS excavator card

Employers must assess the risks of their work and record the significant findings (required where you employ 5 or more people). On CDM projects, contractors give their RAMS to the principal contractor before starting, and brief the workers on it.

Rules that apply: HSE HSG47 Avoiding danger from underground services; COSHH Regulations 2002; Provision and Use of Work Equipment Regulations 1998 (PUWER); Control of Noise at Work Regulations 2005; CDM Regulations 2015, regulation 22 (excavations); CDM Regulations 2015 and PUWER 1998; Work at Height Regulations 2005; Manual Handling Operations Regulations 1992; Control of Vibration at Work Regulations 2005.

Why RAMS get rejected

Principal contractors send documents back for these reasons. This example avoids them, but check yours too.

  • The method statement is only a list of headings that repeats the risk table and never says how the work is done.
  • The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
  • Residual risk is still High after controls with no extra measures or explanation.
  • It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
  • Work on an older building with no reference to an asbestos survey.
  • Plant and access equipment listed with no inspection, thorough examination or competence evidence.
  • No briefing record, no revision history, or no named supervisor.

Questions

Do I need RAMS for surface water drainage installation?

You must assess the risks of surface water drainage installation and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.

Who signs the RAMS?

The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.

How long do I keep it?

Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.

What PPE is needed for surface water drainage installation?

Usually Safety boots, Hi-vis vest, Safety glasses, Rigger gloves, Ear defenders, Half-mask respirator (P3 filters), FFP3 dust mask, Safety helmet, Chemical-resistant gloves, Safety goggles, Coveralls. The site rules may add more, so check with the principal contractor.