JHA for storm drain installation

OSHA expects employers to find and control hazards on every job, and many general contractors require a written JHA for storm drain installation before you start.

A JHA breaks the job into steps, lists the hazards in each step and the controls that protect the crew, and the crew signs it. The main hazards are silica dust from concrete, brick, stone and tiles, hitting underground services, trench or excavation collapse and being hit by heavy equipment.

JHA example: storm drain installation

This is a complete JHA for storm drain installation, with 5 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.

Job Hazard Analysis (JHA)
Install storm drain drainage · Excavation and earthworks · Example
Document JHA-001 · Rev 1

Job steps, hazards and controls

#Job stepHazardsRisk beforeControlsRisk after
1Get 811 locates and mark the pipe run
  • Hitting underground services
Critical
  • Keep machine buckets well clear of marked services and use a spotter. Engineering (guarding)
  • Scan the area with a cable locator before digging and mark services on the ground. Engineering
  • Hand dig or vacuum excavate to expose services before using a machine near them. Engineering
  • Call 811 before you dig and wait until all utilities have marked their lines. Administrative
  • Keep plans or locate tickets on site and check them again if the work area grows. Administrative
  • Support or protect exposed utilities so they cannot sag or break while the excavation is open (29 CFR 1926.651(b)(4)). Administrative
  • If you hit a service, stop, get everyone clear, and call the owner and emergency services. Administrative
  • Wear safety boots, gloves and hi-vis when digging. PPE
Medium
2Cut hard surfaces with water suppression
  • Silica dust from concrete, brick, stone and tiles
  • Saw cuts and kickback
  • Loud noise
Critical
  • Order materials cut to size, or use low-dust methods such as score and snap or a block splitter. Substitution
  • Cut outdoors or in a separate area, with other people well away and upwind. Engineering (guarding)
  • Use wet cutting or on-tool dust collection with a HEPA vacuum, as set out in Table 1 of 29 CFR 1926.1153. Engineering
  • Clean up with a vacuum or wet methods. Never dry sweep or use compressed air. Administrative
  • Have a written exposure control plan and a competent person for silica (29 CFR 1926.1153). Administrative
  • Workers who must wear a respirator 30 or more days a year get a free medical exam every 3 years (29 CFR 1926.1153(h)). Administrative
  • Wear the respirator Table 1 lists for the task: APF 10 (a fit-tested N95 or half mask) for most tasks, APF 25 (such as a loose-fitting PAPR) for tuckpointing with a handheld grinder for more than 4 hours a shift. PPE
  • Keep blade guards fitted and working, and use the riving knife on table saws. Engineering
  • Use push sticks and clamps, and support long pieces so they do not pinch the blade. Engineering
  • Use a sharp, undamaged blade made for the material. Administrative
  • Stand to one side of the blade line, out of the kickback path. Administrative
  • Let the blade stop fully before reaching in or putting the saw down. Administrative
  • Use quieter tools and methods, such as cut-to-size materials, low-noise machines and battery tools. Substitution
  • Keep noisy plant away from work areas, and use screens or distance between the noise and people. Engineering (guarding)
  • Keep tools maintained and use mufflers on compressors and generators. Engineering
  • Limit time on noisy tools and rotate workers. Administrative
  • If you have to shout to be heard at arm's length, wear hearing protection. Administrative
Medium
3Dig the trench and pits, protecting edges
  • Trench or excavation collapse
  • Being hit by heavy equipment
  • Falling through a floor opening or void
Critical
  • Use methods that keep people out of the trench, such as directional boring or working from the surface. Elimination
  • Barricade or cover the excavation so people and equipment cannot fall in. Use guardrails on walkways that cross it (29 CFR 1926.651(l)). Engineering (guarding)
  • Use a protective system (sloping, shoring or a trench box) in any trench 5 feet or deeper, or shallower if the competent person sees signs of a possible cave-in (29 CFR 1926.652). Engineering
  • Protective systems for trenches over 20 feet deep are designed by a registered professional engineer (29 CFR 1926.652(b), (c)). Engineering
  • Keep spoil, materials and equipment at least 2 feet back from the edge. Engineering
  • Provide a ladder, stairway or ramp within 25 feet of workers in trenches 4 feet or deeper. Engineering
  • Competent person inspects the trench daily, after rain and as conditions change, and tests the air before entry in trenches over 4 feet deep where a hazardous atmosphere could exist (29 CFR 1926.651(g), (k)). Administrative
  • Nobody works in a trench where water is collecting unless the competent person has controls in place, such as pumping or special support (29 CFR 1926.651(h)). Administrative
  • Nobody stands under a loaded bucket or near a truck being loaded (29 CFR 1926.651(e)). Administrative
  • Separate people and equipment with barriers, exclusion zones and marked walkways. Engineering (guarding)
  • Use equipment with working backup alarms, cameras and lights. Engineering
  • Have a site traffic plan showing equipment routes, loading areas and pedestrian paths. Administrative
  • Use a spotter when backing up or working near people. Administrative
  • Make eye contact with the operator before going near. Stay out of the swing radius. Administrative
  • Cover every hole with a secured cover marked "HOLE" or "COVER" that can hold twice the weight it may carry. Engineering (guarding)
  • Put guardrails with toe boards around stairwells, elevator shafts, floor holes and open edges. Engineering (guarding)
  • Install stairs early and fit temporary handrails as soon as they go in. Engineering
  • Never remove a cover or guardrail without approval. Put it back straight away. Administrative
  • Inspect covers and barriers daily and after other trades have been through. Administrative
Medium
4Lay pipe to grade and set pits
  • Lifting and carrying heavy loads
  • Hazardous chemicals
High
  • Plan to avoid carrying: have materials delivered, and old items picked up, as close as possible to where they are used. Elimination
  • Use lighter or smaller loads: order smaller bags and shorter lengths, and drain or break down old items before moving them. Substitution
  • Use trolleys, pallet jacks, hoists, vacuum lifters or plant instead of carrying by hand. Engineering
  • Use a two-person lift for anything heavy, long or awkward. Plan the route first and clear it. Administrative
  • Keep the load close, back straight and no twisting. Turn with your feet. Administrative
  • Rotate tasks and take breaks on long lifting jobs. Administrative
  • Wear gloves for grip and safety boots to protect your feet. PPE
  • Choose the least harmful product that does the job, for example water-based instead of solvent-based. Substitution
  • Use chemicals in well-ventilated areas, or use fans and extraction in closed rooms. Engineering
  • Read the Safety Data Sheet (SDS) and labels before use, following OSHA Hazard Communication. Administrative
  • Keep chemicals in labeled containers. Never pour them into drink bottles. Administrative
  • Store chemicals away from heat, food and drink, and keep products that react with each other apart. Administrative
  • Have eye wash and a spill kit nearby, and wash hands before eating. Administrative
  • Wear chemical-resistant gloves and safety glasses or goggles as listed on the SDS. PPE
  • Use a respirator with the right cartridge if the SDS calls for one. PPE
Medium
5Backfill, compact and reinstate surfaces
  • Hand-arm and whole-body vibration
  • Loud noise
  • Poor housekeeping and waste
High
  • Use low-vibration tools and methods, such as a breaker on an excavator instead of a hand jackhammer. Substitution
  • Keep tools sharp and well maintained, and use anti-vibration handles and seats. Engineering
  • Limit trigger time on high-vibration tools and rotate workers. Administrative
  • Keep hands warm and dry, and take regular breaks. Administrative
  • Report tingling, numbness or white fingers early. Administrative
  • Wear earplugs or earmuffs rated for the noise. PPE
  • Loud noise: see step 2 for the full controls Administrative
  • Order materials to size and send packaging back where you can. Elimination
  • Put dumpsters and waste chutes close to the work. Engineering
  • Clean as you go, and do a full clean up at the end of each day. Administrative
  • Keep exits, stairs and walkways clear at all times. Administrative
  • Stack materials neatly on level ground, away from edges. Administrative
Medium

PPE

Safety-toe boots (ASTM F2413)High-visibility safety apparel, ANSI/ISEA 107 Class 2 or 3 (Type R near roadways)Safety glasses (ANSI Z87.1)Work glovesHearing protection (earmuffs or plugs)Half-face respirator (P100 cartridges)N95 respiratorHard hat (ANSI Z89.1)Chemical-resistant glovesSafety goggles (ANSI Z87.1)Coveralls

Plant and equipment

ExcavatorPlate compactorHand toolsConcrete saw (cut-off saw)

Permits and plans

811 locate ticket / excavation permit

Emergency

Call 911. Add the nearest hospital, the assembly point and the first aid / cpr person for your site.

Sign-off

Supervisor and every worker sign to confirm they have read and understood this JHA.

Free JHA template for storm drain installation

Word (.docx) and PDF, Letter landscape, no email needed. Fill in your site details, then print or send it.

Make yours in 2 minutes

Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.

Start this JHA

Pre-start checklist for storm drain installation

Tick these off before work starts. They come from the hazards, permits and equipment in this job.

The safe sequence of work

  1. Get 811 locates and mark the pipe run
  2. Cut hard surfaces with water suppression
  3. Dig the trench and pits, protecting edges
  4. Lay pipe to grade and set pits
  5. Backfill, compact and reinstate surfaces

Hazards to watch on storm drain installation

The hazards most specific to this job, and the step where each one comes up.

Step 3Trench or excavation collapseThe trench walls cave in and bury or crush a worker. Trenches 5 feet or deeper need a protective system, and shallower ones do too if there are signs of a possible cave-in.
Step 5Hand-arm and whole-body vibrationLong periods on jackhammers, grinders, compactors or riding plant cause white finger, numbness and back damage.
Step 1Hitting underground servicesDigging, drilling or driving pegs hits a buried power cable, gas pipe or water main, causing electrocution, explosion or flooding.
Step 3Falling through a floor opening or voidA worker steps into an open hole, stairwell, elevator shaft or floor opening and falls to the level below.
Step 3Being hit by heavy equipmentExcavators, loaders, telehandlers and trucks run over or crush workers, especially when backing up or swinging.
Step 2Saw cuts and kickbackCircular saws, miter saws and table saws cut fingers and hands or throw material back at the user.
Almost certainLikelyPossibleUnlikelyRareHow bad it could be: First aid only to FatalityBA
Highest risk on storm drain installation: Critical before controls (B), down to Medium after controls (A), on the United States 5 by 5 risk matrix (likely and fatality becomes unlikely and serious injury).

What changes on your site

This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):

  • Will anyone work 6 feet or more above a lower level?
  • Will anyone use a ladder or stepladder?
  • Will anyone work on a roof?
  • Is there a skylight, fiberglass panel or other fragile roofing?
  • Will you use a scaffold or rolling tower?

Why JHAs get rejected

General contractors send documents back for these reasons. This example avoids them, but check yours too.

  • Generic steps such as "work safely" or "use PPE" with no task-specific hazards or controls.
  • No OSHA standards referenced for the hazards that have them, such as fall protection, ladders, scaffolds or silica.
  • No competent person named for fall protection, excavation, scaffolds or silica where those hazards exist.
  • Equipment listed without inspection requirements, and no training listed for the people using it.
  • Respirators listed with no respiratory protection program, medical clearance or fit test.
  • Controls rely only on PPE when engineering controls such as guardrails, wet cutting or extraction are feasible.
  • No crew sign-off, or no date and revision when the job has changed.

Questions

Do I need a JHA for storm drain installation?

OSHA expects employers to find and control hazards on every job, and many general contractors require a written JHA for storm drain installation before you start.

Who signs the JHA?

The supervisor or competent person who prepared it signs, and every crew member signs to show they were trained on the hazards and controls before the job starts. Many general contractors also sign to accept it.

How long do I keep it?

Keep this JHA on site during the job, and keep it with the training and inspection records for at least 1 year after the job (longer if your state plan or general contractor requires it). OSHA does not set a retention period for JHAs themselves.

What PPE is needed for storm drain installation?

Usually Safety-toe boots (ASTM F2413), High-visibility safety apparel, ANSI/ISEA 107 Class 2 or 3 (Type R near roadways), Safety glasses (ANSI Z87.1), Work gloves, Hearing protection (earmuffs or plugs), Half-face respirator (P100 cartridges), N95 respirator, Hard hat (ANSI Z89.1), Chemical-resistant gloves, Safety goggles (ANSI Z87.1), Coveralls. The site rules may add more, so check with the general contractor.