Method statement for roof repairs
You must assess the risks of roof repairs and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are falling from a roof edge, falling through a fragile roof or skylight, disturbing asbestos and electric shock from live wiring.
RAMS example: roof repairs
This is a complete RAMS for roof repairs, with 6 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
Risk assessment
| # | Activity | Hazards | Who might be harmed | Risk before | Controls | Risk after |
|---|---|---|---|---|---|---|
| 1 | Check the roof type and condition from the ground, looking for brittle sheets, skylights and asbestos |
| Workers, People below, Occupants, Public | Very high (15) |
| Medium (5) |
| 2 | Set up a secured ladder and edge protection or a harness and anchor |
| Workers, People below | Very high (20) |
| Medium (8) |
| 3 | Go into the roof space to find the leak, watching for live cables and weak ceiling joists |
| Workers, Occupants, Visitors | Very high (15) |
| Medium (8) |
| 4 | Replace cracked tiles, sheets or flashings and seal joints |
| Workers, Occupants, Visitors, Public | Medium (9) |
| Medium (6) |
| 5 | Use heat for flashings only with a hot work permit and a fire extinguisher at hand |
| Workers, Occupants, Public | Very high (15) |
| Medium (5) |
| 6 | Clean up debris, check gutters are clear and remove the ladder |
| Workers, Visitors, Public, People below | High (12) |
| Medium (8) |
Method statement: sequence of work
- Check the roof type and condition from the ground, looking for brittle sheets, skylights and asbestos
- Set up a secured ladder and edge protection or a harness and anchor
- Go into the roof space to find the leak, watching for live cables and weak ceiling joists
- Replace cracked tiles, sheets or flashings and seal joints
- Use heat for flashings only with a hot work permit and a fire extinguisher at hand
- Clean up debris, check gutters are clear and remove the ladder
PPE
Plant and equipment
Permits and plans
Emergency
Call 999. Add the nearest A&E, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this RAMS.
Free RAMS template for roof repairs
Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for roof repairs
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- RAMS read, explained and signed by everyone on the job
- Edge protection or fall protection in place before work at height starts
- Fragile roof areas and skylights covered or barricaded
- Openings, voids and penetrations covered and marked
- Ladder inspected, secured and extending 1 m above the landing
- Asbestos register or survey checked for the work area
- Hot work permit issued, extinguisher at hand, fire watch arranged
- Exclusion zone below the work and public kept out
- Weather checked: water, shade and rest breaks planned
- First aider, first aid kit and emergency number (999) confirmed
- PPE checked and worn: safety boots, full body harness and lanyard, rigger gloves, safety glasses
The safe sequence of work
- Check the roof type and condition from the ground, looking for brittle sheets, skylights and asbestos
- Set up a secured ladder and edge protection or a harness and anchor
- Go into the roof space to find the leak, watching for live cables and weak ceiling joists
- Replace cracked tiles, sheets or flashings and seal joints
- Use heat for flashings only with a hot work permit and a fire extinguisher at hand
- Clean up debris, check gutters are clear and remove the ladder
Hazards to watch on roof repairs
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone work at height, anywhere a fall could hurt them?
- Will anyone work on a roof?
- Will you use a scaffold or mobile tower?
- Will you use a MEWP (scissor lift or cherry picker)?
- Will you sand, scrape, burn off or cut old paint in a building from before 1992?
Why RAMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- The method statement is only a list of headings that repeats the risk table and never says how the work is done.
- The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
- Residual risk is still High after controls with no extra measures or explanation.
- It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
- Work on an older building with no reference to an asbestos survey.
- Plant and access equipment listed with no inspection, thorough examination or competence evidence.
- No briefing record, no revision history, or no named supervisor.
Questions
Do I need RAMS for roof repairs?
You must assess the risks of roof repairs and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
Who signs the RAMS?
The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.
How long do I keep it?
Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.
What PPE is needed for roof repairs?
Usually Safety boots, Full body harness and lanyard, Rigger gloves, Safety glasses, Sun protection (sunscreen and neck cover), Safety helmet, Half-mask respirator (P3 filters), Coveralls, Cut-resistant gloves, Chemical-resistant gloves, Safety goggles, Welding gauntlets, Face shield. The site rules may add more, so check with the principal contractor.