SiteSorted
Plumbing · United States

JHA for gas line installation

OSHA expects employers to find and control hazards on every job, and many general contractors require a written JHA for gas line installation before you start.

A JHA breaks the job into steps, lists the hazards in each step and the controls that protect the crew, and the crew signs it. The main hazards are electric shock from live wiring, fire from hot works, lifting and carrying heavy loads and gas and fuel lines.

JHA example: gas line installation

This is a complete JHA for gas line installation, with 6 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.

Job Hazard Analysis (JHA)
Gas fitting and appliance connection · Plumbing · Example
Document JHA-001 · Rev 1

Job steps, hazards and controls

#Job stepHazardsRisk beforeControlsRisk after
1Only a licensed gas fitter does this work. Tell occupants and remove ignition sources
  • Gas and fuel lines
  • Working in an occupied home or building
High
  • Isolate and purge the line before work, with the owner's approval. Elimination
  • Lock off and tag the isolation valve. Engineering (guarding)
  • Check for leaks with a gas detector before and during work, and ventilate the area. Engineering
  • Only licensed gas fitters work on gas lines. Administrative
  • Remove ignition sources: no smoking, no hot work and no sparking tools near the line. Administrative
  • Know where the shut-off valve is and what to do if a leak happens. Administrative
  • Wear safety glasses and gloves, and keep a fire extinguisher close by. PPE
  • Plan noisy, dusty or risky work for when the building is empty. Elimination
  • Close off the work area with barriers, plastic sheeting or locked doors, and put up signs. Engineering (guarding)
  • Keep fire exits and paths clear at all times. Administrative
  • Tell occupants before you turn off power, water or gas, and before noisy or dusty work. Administrative
  • Lock away tools, chemicals and materials each day, out of reach of children. Administrative
  • Clean up dust and debris at the end of each day. Administrative
Medium
2Isolate gas at the meter, apply lockout/tagout, and purge the line
  • Gas and fuel lines
  • Stored energy
  • Fire and emergencies
High
  • Gas and fuel lines: see step 1 for the full controls Administrative
  • Release or block all stored energy before work: release the pressure in pipes, tanks and hoses, bleed hydraulics, release springs, lower loads. Elimination
  • Lock out and tag all energy sources with personal locks. Engineering (guarding)
  • Put mechanical blocks or props under raised parts like buckets, tipper bodies and doors. Engineering
  • Test that the system is dead and nothing can move before you start. Administrative
  • Follow the maker's procedure, for example for garage door and roller door springs. Administrative
  • Provide fire extinguishers suited to the site, checked and easy to reach. Engineering
  • Keep exits and escape routes clear and signed. Engineering
  • Have a site emergency plan: alarm, exits, assembly point and emergency contacts. Administrative
  • Keep a stocked first aid kit and at least one trained first aider on site. Administrative
  • Know the site address and how emergency services get in. Call 911. Administrative
Medium
3Run and join new pipe, checking there are no electrical cables in the way
  • Electric shock from live wiring
  • Injury from power tools
  • Tight spaces: attics and crawl spaces
Critical
  • Isolate the power before any work. Do not work live. Elimination
  • Lock out and tag the disconnecting means with your own personal lock and tag so the circuit cannot be energized (29 CFR 1926.417). Engineering (guarding)
  • Test before you touch: prove dead at the point of work with a tested voltage tester. Engineering
  • Only qualified persons work on or near exposed energized parts. Administrative
  • Check for back feeds from solar, batteries and generators that can keep a circuit live after the main switch is off. Administrative
  • Keep all guards fitted and working. Never tie back or remove a guard. Engineering
  • Clamp or secure the work piece. Do not hold it by hand. Engineering
  • Only trained, competent people use power tools, following the maker's instructions. Administrative
  • Check tools before use. Unplug or remove the battery before changing blades or bits. Administrative
  • No loose clothing, jewelry or long hair near spinning parts. Administrative
  • Do as much of the work as you can from outside the tight space. Elimination
  • Turn the power off at the panel before entering where you can, as damaged wiring may be live. Engineering (guarding)
  • Lay crawl boards across the joists so you cannot step through the ceiling. Engineering
  • Set up ventilation and lighting in the space. Engineering
  • Limit time in hot attics and take breaks somewhere cool. Administrative
Medium
4Connect the appliance and seal all joints
  • Gas and fuel lines
  • Lifting and carrying heavy loads
High
  • Gas and fuel lines: see step 1 for the full controls Administrative
  • Plan to avoid carrying: have materials delivered, and old items picked up, as close as possible to where they are used. Elimination
  • Use lighter or smaller loads: order smaller bags and shorter lengths, and drain or break down old items before moving them. Substitution
  • Use trolleys, pallet jacks, hoists, vacuum lifters or plant instead of carrying by hand. Engineering
  • Use a two-person lift for anything heavy, long or awkward. Plan the route first and clear it. Administrative
  • Keep the load close, back straight and no twisting. Turn with your feet. Administrative
  • Rotate tasks and take breaks on long lifting jobs. Administrative
  • Wear gloves for grip and safety boots to protect your feet. PPE
Medium
5Pressure and leak test, then light and commission the appliance
  • Pressure testing
  • Gas and fuel lines
  • Fire from hot works
Critical
  • Test with water instead of air or gas where the system allows it. Never put water in refrigerant pipework, which is tested with dry nitrogen. Substitution
  • Keep people out of the test area with signs and barriers. Engineering (guarding)
  • Use a calibrated gauge and a relief valve set to protect the system. Engineering
  • Test to the pressure the system calls for and hold it for the set time. Never go over. Administrative
  • Release the pressure fully before tightening anything or fixing leaks. Administrative
  • Gas and fuel lines: see step 1 for the full controls Administrative
  • Use cold work methods where you can, such as bolting, press fittings or cutting with a saw instead of a torch. Elimination
  • Move anything that can burn at least 35 feet away, or cover it with fire blankets. Engineering (guarding)
  • Use fire-resistant screens to stop sparks reaching people or gaps in walls and floors. Engineering
  • Get a hot work permit before starting. Administrative
  • Keep a charged fire extinguisher and fire blanket at the work spot. Administrative
Medium
6Issue the compliance certificate and clean up
  • Poor housekeeping and waste
Medium
  • Order materials to size and send packaging back where you can. Elimination
  • Put dumpsters and waste chutes close to the work. Engineering
  • Clean as you go, and do a full clean up at the end of each day. Administrative
  • Keep exits, stairs and walkways clear at all times. Administrative
  • Stack materials neatly on level ground, away from edges. Administrative
  • Wear gloves when handling waste. PPE
Low

PPE

Safety-toe boots (ASTM F2413)Safety glasses (ANSI Z87.1)Work glovesN95 respiratorHearing protection (earmuffs or plugs)Knee padsHard hat (ANSI Z89.1)Face shield (ANSI Z87.1)Welding glovesCoveralls

Plant and equipment

Hand toolsProPress toolElectrical test meterPower drill

Permits and plans

Lockout/tagout (1926.417)Hot work permit (fire watch at least 60 minutes after, NFPA 51B)

Emergency

Call 911. Add the nearest hospital, the assembly point and the first aid / cpr person for your site.

Sign-off

Supervisor and every worker sign to confirm they have read and understood this JHA.

Free JHA template for gas line installation

Word (.docx) and PDF, Letter landscape, no email needed. Fill in your site details, then print or send it.

Make yours in 2 minutes

Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.

Start this JHA

Pre-start checklist for gas line installation

Tick these off before work starts. They come from the hazards, permits and equipment in this job.

The safe sequence of work

  1. Only a licensed gas fitter does this work. Tell occupants and remove ignition sources
  2. Isolate gas at the meter, apply lockout/tagout, and purge the line
  3. Run and join new pipe, checking there are no electrical cables in the way
  4. Connect the appliance and seal all joints
  5. Pressure and leak test, then light and commission the appliance
  6. Issue the compliance certificate and clean up

Hazards to watch on gas line installation

The hazards most specific to this job, and the step where each one comes up.

Step 3Tight spaces: attics and crawl spacesCrawling through attics, crawl spaces or tight ceilings leads to falls through the ceiling, heat stress, shocks and cuts.
Step 5Pressure testingA pipe, fitting or cap fails under test pressure and blows apart, hitting people nearby.
Step 2Fire and emergenciesA fire, injury or other emergency happens and workers cannot get out, raise the alarm or get first aid in time.
Step 2Stored energyEnergy left in springs, hydraulics, compressed gas, raised loads or capacitors releases suddenly and crushes or injures workers.
Step 5Fire from hot worksSparks and heat from welding, grinding or flame torches set fire to timber, insulation, rubbish or fuel nearby.
Step 1, 2, 4, 5Gas and fuel linesDamaging or opening a gas or fuel line causes a leak, fire or explosion.
Almost certainLikelyPossibleUnlikelyRareHow bad it could be: First aid only to FatalityBA
Highest risk on gas line installation: Critical before controls (B), down to Medium after controls (A), on the United States 5 by 5 risk matrix (possible and fatality becomes unlikely and recordable / lost time).

What changes on your site

This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):

  • Will anyone work 6 feet or more above a lower level?
  • Will anyone use a ladder or stepladder?
  • Will anyone work on a roof?
  • Is there a skylight, fiberglass panel or other fragile roofing?
  • Will you use a scaffold or rolling tower?

Why JHAs get rejected

General contractors send documents back for these reasons. This example avoids them, but check yours too.

  • Generic steps such as "work safely" or "use PPE" with no task-specific hazards or controls.
  • No OSHA standards referenced for the hazards that have them, such as fall protection, ladders, scaffolds or silica.
  • No competent person named for fall protection, excavation, scaffolds or silica where those hazards exist.
  • Equipment listed without inspection requirements, and no training listed for the people using it.
  • Respirators listed with no respiratory protection program, medical clearance or fit test.
  • Controls rely only on PPE when engineering controls such as guardrails, wet cutting or extraction are feasible.
  • No crew sign-off, or no date and revision when the job has changed.

Questions

Do I need a JHA for gas line installation?

OSHA expects employers to find and control hazards on every job, and many general contractors require a written JHA for gas line installation before you start.

Who signs the JHA?

The supervisor or competent person who prepared it signs, and every crew member signs to show they were trained on the hazards and controls before the job starts. Many general contractors also sign to accept it.

How long do I keep it?

Keep this JHA on site during the job, and keep it with the training and inspection records for at least 1 year after the job (longer if your state plan or general contractor requires it). OSHA does not set a retention period for JHAs themselves.

What PPE is needed for gas line installation?

Usually Safety-toe boots (ASTM F2413), Safety glasses (ANSI Z87.1), Work gloves, N95 respirator, Hearing protection (earmuffs or plugs), Knee pads, Hard hat (ANSI Z89.1), Face shield (ANSI Z87.1), Welding gloves, Coveralls. The site rules may add more, so check with the general contractor.