JHA for scaffold alteration
OSHA expects employers to find and control hazards on every job, and many general contractors require a written JHA for scaffold alteration before you start.
A JHA breaks the job into steps, lists the hazards in each step and the controls that protect the crew, and the crew signs it. The main hazards are falling from height, scaffold collapse or fall from scaffold, falling tools and materials and public entering the work area.
JHA example: scaffold alteration
This is a complete JHA for scaffold alteration, with 5 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
Job steps, hazards and controls
| # | Job step | Hazards | Risk before | Controls | Risk after |
|---|---|---|---|---|---|
| 1 | Only licensed or carded scaffolders alter scaffold; tag it out first |
| Critical |
| Medium |
| 2 | Clear other workers from the area |
| High |
| Medium |
| 3 | Make the change, keeping ties and bracing in place |
| Critical |
| Medium |
| 4 | Reinstate guardrails and toe boards |
| Critical |
| Medium |
| 5 | Re-inspect and re-tag |
| Critical |
| Medium |
PPE
Plant and equipment
Permits and plans
Emergency
Call 911. Add the nearest hospital, the assembly point and the first aid / cpr person for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this JHA.
Free JHA template for scaffold alteration
Word (.docx) and PDF, Letter landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for scaffold alteration
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- JHA read, explained and signed by everyone on the job
- Guardrails, nets or fall arrest in place before anyone works at 6 ft or more
- Scaffold inspected by a competent person this shift
- Exclusion zone below the work and public kept out
- First aid / CPR person, first aid kit and emergency number (911) confirmed
- PPE checked and worn: safety-toe boots (ASTM F2413), hard hat (ANSI Z89.1), personal fall arrest system (harness), work gloves
The safe sequence of work
- Only licensed or carded scaffolders alter scaffold; tag it out first
- Clear other workers from the area
- Make the change, keeping ties and bracing in place
- Reinstate guardrails and toe boards
- Re-inspect and re-tag
Hazards to watch on scaffold alteration
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone use a ladder or stepladder?
- Will anyone work on a roof?
- Is there a skylight, fiberglass panel or other fragile roofing?
- Will you use an aerial lift (scissor lift or boom lift)?
- Was the building built before 1981?
Licences and legal requirements in United States
Equipment on this job that needs a licence, ticket or training:
- Supported scaffold: Erected under a competent person (29 CFR 1926.451)
OSHA requires employers to find and fix hazards and to train workers on them. A JHA breaks the job into steps, lists the hazards in each step and the controls that protect the crew. General contractors often require one before you start.
Rules that apply: 29 CFR 1926 Subpart L; 29 CFR 1926.501(c); 29 CFR 1926 Subpart M.
Why JHAs get rejected
General contractors send documents back for these reasons. This example avoids them, but check yours too.
- Generic steps such as "work safely" or "use PPE" with no task-specific hazards or controls.
- No OSHA standards referenced for the hazards that have them, such as fall protection, ladders, scaffolds or silica.
- No competent person named for fall protection, excavation, scaffolds or silica where those hazards exist.
- Equipment listed without inspection requirements, and no training listed for the people using it.
- Respirators listed with no respiratory protection program, medical clearance or fit test.
- Controls rely only on PPE when engineering controls such as guardrails, wet cutting or extraction are feasible.
- No crew sign-off, or no date and revision when the job has changed.
Questions
Do I need a JHA for scaffold alteration?
OSHA expects employers to find and control hazards on every job, and many general contractors require a written JHA for scaffold alteration before you start.
Who signs the JHA?
The supervisor or competent person who prepared it signs, and every crew member signs to show they were trained on the hazards and controls before the job starts. Many general contractors also sign to accept it.
How long do I keep it?
Keep this JHA on site during the job, and keep it with the training and inspection records for at least 1 year after the job (longer if your state plan or general contractor requires it). OSHA does not set a retention period for JHAs themselves.
What PPE is needed for scaffold alteration?
Usually Safety-toe boots (ASTM F2413), Hard hat (ANSI Z89.1), Personal fall arrest system (harness), Work gloves, High-visibility safety apparel, ANSI/ISEA 107 Class 2 or 3 (Type R near roadways), Safety glasses (ANSI Z87.1). The site rules may add more, so check with the general contractor.
More scaffolding JHAs
Related jobs in other trades
Toolbox talks for this job
Blank JHA template: free JHA templates. Also for other countries: Australia (SWMS) · United Kingdom (RAMS) · Canada (FLHA)