Method statement for small building demolition

You must assess the risks of small building demolition and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.

RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are falling from height, silica dust from concrete, brick, stone and tiles, disturbing asbestos and electric shock from live wiring.

RAMS example: small building demolition

This is a complete RAMS for small building demolition, with 6 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.

Risk Assessment and Method Statement (RAMS)
Demolish a small building · Demolition · Example
Document RAMS-001 · Rev 1

Risk assessment

#ActivityHazardsWho might be harmedRisk beforeControlsRisk after
1Check the asbestos survey, get asbestos removed, and get services disconnected
  • Disturbing asbestos
  • Electric shock from live wiring
  • Gas and fuel lines
  • Hitting underground services
Workers, Occupants, PublicVery high (15)
  • Before work on any building built before 2000, check the refurbishment and demolition asbestos survey for the work area (HSE HSG264). If there is none, presume asbestos is present or have it sampled before you start. Eliminate
  • Seal off the work area and keep everyone else out. Isolate
  • If asbestos must be disturbed, keep it wet, use hand tools not power tools, and clean up with an H-class vacuum. Control (engineering)
  • Most asbestos insulation, coatings and insulating board need a licensed contractor. Notifiable non-licensed work is notified to HSE before it starts. Other work needs trained workers and controls. Control (procedures)
  • Stop work straight away if you find suspect asbestos. Do not touch it and tell your supervisor. Control (procedures)
  • Isolate the power before any work. Do not work live. Eliminate
  • Lock out and tag the isolation point with your own personal lock and danger tag. Isolate
  • Prove dead at the point of work with an approved voltage indicator (GS38), and prove the tester before and after. Control (engineering)
  • Only competent, qualified electricians do electrical work, following a safe isolation procedure. Control (procedures)
  • Isolate and purge the line before work, with the owner's approval. Eliminate
  • Lock off and tag the isolation valve. Isolate
  • Check for leaks with a gas detector before and during work, and ventilate the area. Control (engineering)
  • Only Gas Safe registered engineers work on gas fittings. Control (procedures)
  • Keep machine buckets well clear of marked services and use a spotter. Isolate
  • Do a CAT and Genny scan before digging and mark services on the ground. Control (engineering)
  • Hand dig trial holes to find services before machine digging (safe digging practice). Control (engineering)
  • Get utility plans before digging and check them against what you see on site. Control (procedures)
Medium (5)
2Fence the site and set up traffic and public control
  • Public entering the work area
  • Road traffic
Public, Children, Workers, Road usersVery high (15)
  • Fence off the site with secure temporary fencing and lock the gates when you leave. Isolate
  • Give pedestrians a safe, marked path around the work, with ramps for prams and wheelchairs. Isolate
  • Use hoarding, covered walkways or catch fans where work is above public areas. Control (engineering)
  • Put signs at each entry: site name, contact number and "No unauthorised entry". Control (procedures)
  • Make the site safe at the end of each day: cover holes, lower plant, remove ladders and lock tools away. Control (procedures)
  • Use a spotter when moving plant or materials across public paths. Control (procedures)
  • Do the work at low-traffic times, or close the road or lane with approval. Eliminate
  • Put solid barriers between the work and traffic where speeds are high, not just cones. Isolate
  • Use a truck-mounted attenuator or buffer vehicle on high speed roads. Control (engineering)
  • Set up signs and cones to Chapter 8 (Traffic Signs Manual) by trained operatives. Control (procedures)
  • Get a street works permit or licence from the highway authority before you start. Control (procedures)
  • Park work vehicles to shield the work zone, with beacons on. Control (procedures)
  • Wear Class 2 or 3 hi-vis clothing (EN ISO 20471). PPE
Medium (5)
3Strip out by hand before machine demolition
  • Lifting and carrying heavy loads
  • Cuts from sharp edges
  • Falling from height
Workers, People belowVery high (20)
  • Plan to avoid carrying: have materials delivered, and old items picked up, as close as possible to where they are used. Eliminate
  • Use lighter or smaller loads: order smaller bags and shorter lengths, and drain or break down old items before moving them. Reduce / substitute
  • Use trolleys, pallet jacks, hoists, vacuum lifters or plant instead of carrying by hand. Control (engineering)
  • Use a two-person lift for anything heavy, long or awkward. Plan the route first and clear it. Control (procedures)
  • Keep the load close, back straight and no twisting. Turn with your feet. Control (procedures)
  • Deburr or cover sharp edges, and fit edge protectors on exposed sheet metal. Control (engineering)
  • Use knives with retractable or self-retracting blades. Control (engineering)
  • Cut away from your body and keep your other hand clear. Control (procedures)
  • Put used blades in a blade bin or sharps container. Control (procedures)
  • Use two people to handle large sheets of metal or glass. Control (procedures)
  • Do the work from the ground where you can, for example pre-assemble on the ground or use extension poles. Eliminate
  • Install guardrails or edge protection on all open edges before work starts. Isolate
  • Use a scaffold, mobile tower or MEWP instead of working off a ladder. Control (engineering)
  • Where edge protection is not practical, use a fall restraint or fall arrest system on a rated anchor point. Control (engineering)
  • Have a rescue plan so a worker hanging in a harness can be brought down within minutes. Control (procedures)
Medium (6)
4Demolish with the excavator, keeping everyone outside the exclusion zone
  • Being hit by mobile plant
  • Structural collapse during alterations
  • Demolition and falling debris
Workers, Visitors, Public, Occupants, NeighboursVery high (15)
  • Separate people and plant with barriers, exclusion zones and marked walkways. Isolate
  • Use plant with working reversing alarms, cameras and lights. Control (engineering)
  • Have a traffic management plan showing plant routes, loading areas and pedestrian paths. Control (procedures)
  • Use a spotter when reversing or working near people. Control (procedures)
  • Make eye contact with the operator before going near. Stay out of the swing radius. Control (procedures)
  • Get an engineer to check before removing any wall, beam, post or bracing that may be load-bearing. Eliminate
  • Keep everyone clear of the area under and next to the work. Isolate
  • Install temporary props, needles or shoring as designed before removing any support. Control (engineering)
  • Follow the engineer's sequence. Do not change it without approval. Control (procedures)
  • Check props daily. Do not remove them until the permanent support is in and approved. Control (procedures)
  • Check for asbestos, lead, live services and structural risks before demolition starts. Eliminate
  • Disconnect and cap power, gas and water before demolition. Isolate
  • Set an exclusion zone bigger than the distance the structure could fall. Isolate
  • Use a machine with a guarded cab instead of hand demolition where practical. Control (engineering)
  • Use chutes or bins to get debris down. Never drop it from height. Control (engineering)
  • Record the demolition, dismantling or strip-out arrangements in writing before work starts (CDM 2015 reg 20(2)). Control (procedures)
Medium (5)
5Keep dust down with water
  • General dust
  • Silica dust from concrete, brick, stone and tiles
  • Loud noise
Workers, Occupants, People nearbyVery high (20)
  • Use low-dust products, such as dust-reduced or pre-mixed compounds. Reduce / substitute
  • Seal off the work area with plastic sheeting in occupied buildings. Isolate
  • Use tools with dust extraction and a vacuum for clean up. Control (engineering)
  • Lightly mist the area with water to keep dust down, away from anything electrical. Control (engineering)
  • Never dry sweep or blow dust off with compressed air. Control (procedures)
  • Order materials cut to size, or use low-dust methods such as score and snap or a block splitter. Reduce / substitute
  • Cut outdoors or in a separate area, with other people well away and upwind. Isolate
  • Use water on the blade or on-tool dust extraction connected to an H-class vacuum. Control (engineering)
  • Clean up with a vacuum or wet methods. Never dry sweep or use compressed air. Control (procedures)
  • Do a COSHH assessment and keep exposure below the workplace exposure limit (0.1 mg/m3 respirable crystalline silica, 8 hours). Control (procedures)
  • Workers regularly exposed to silica dust get health surveillance (COSHH reg 11, HSE G404). Control (procedures)
  • Wear a fit-tested FFP3 mask. PPE
  • Use quieter tools and methods, such as cut-to-size materials, low-noise machines and battery tools. Reduce / substitute
  • Keep noisy plant away from work areas, and use screens or distance between the noise and people. Isolate
  • Keep tools maintained and use mufflers on compressors and generators. Control (engineering)
  • Limit time on noisy tools and rotate workers. Control (procedures)
  • If you have to shout to be heard by someone 2 metres away, the noise is probably 85 dB(A) or more: wear hearing protection. Control (procedures)
  • Assess noise. At 85 dB(A) or more, hearing protection is required and the zone must be marked. Control (procedures)
Medium (6)
6Sort and load waste into trucks, then level the site
  • Being hit by mobile plant
  • Road traffic
  • Poor housekeeping and waste
Workers, Visitors, Public, Road usersVery high (15)
  • Operators hold a CPCS, NPORS or equal card for the plant they use. Control (procedures)
  • Do a pre-start check on each machine every day and record it. Control (procedures)
  • Wear hi-vis clothing and a hard hat. PPE
  • Being hit by mobile plant: see step 4 for the full controls Control (procedures)
  • Road traffic: see step 2 for the full controls Control (procedures)
  • Order materials to size and send packaging back where you can. Eliminate
  • Put skips and waste chutes close to the work. Control (engineering)
  • Clean as you go, and do a full clean up at the end of each day. Control (procedures)
  • Keep exits, stairs and walkways clear at all times. Control (procedures)
  • Stack materials neatly on level ground, away from edges. Control (procedures)
  • Use a registered waste carrier and keep waste transfer notes for at least 2 years. Keep hazardous waste such as asbestos separate, with consignment notes (special waste in Scotland). Control (procedures)
Medium (5)

Method statement: sequence of work

  1. Check the asbestos survey, get asbestos removed, and get services disconnected
  2. Fence the site and set up traffic and public control
  3. Strip out by hand before machine demolition
  4. Demolish with the excavator, keeping everyone outside the exclusion zone
  5. Keep dust down with water
  6. Sort and load waste into trucks, then level the site

PPE

Safety bootsSafety helmetHi-vis vestSafety glassesFFP3 dust maskEar defendersCut-resistant glovesHalf-mask respirator (P3 filters)CoverallsRigger gloves

Plant and equipment

Excavator (360): CPCS or NPORS excavator cardSkid steer loader: CPCS or NPORS skid steer cardSite dumper: CPCS or NPORS forward tipping dumper cardHand toolsTrailer

Emergency

Call 999. Add the nearest A&E, the assembly point and the first aider for your site.

Sign-off

Supervisor and every worker sign to confirm they have read and understood this RAMS.

Free RAMS template for small building demolition

Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.

Make yours in 2 minutes

Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.

Start this RAMS

Pre-start checklist for small building demolition

Tick these off before work starts. They come from the hazards, permits and equipment in this job.

The safe sequence of work

  1. Check the asbestos survey, get asbestos removed, and get services disconnected
  2. Fence the site and set up traffic and public control
  3. Strip out by hand before machine demolition
  4. Demolish with the excavator, keeping everyone outside the exclusion zone
  5. Keep dust down with water
  6. Sort and load waste into trucks, then level the site

Hazards to watch on small building demolition

The hazards most specific to this job, and the step where each one comes up.

Step 4Demolition and falling debrisPart of a structure collapses early, or debris falls and hits workers or the public during demolition or strip out.
Step 2, 6Road trafficPassing cars and trucks hit workers or plant working on or next to a road.
Step 1Gas and fuel linesDamaging or opening a gas or fuel line causes a leak, fire or explosion.
Step 4Structural collapse during alterationsRemoving a wall, beam, post or bracing makes part of the building fall on workers.
Step 1Hitting underground servicesDigging, drilling or driving pegs hits a buried power cable, gas pipe or water main, causing electrocution, explosion or flooding.
Step 1Disturbing asbestosBuildings built before 2000 may contain asbestos. Drilling, cutting or breaking it releases fibres that cause cancer years later.
Very likelyLikelyPossibleUnlikelyVery unlikelyHow bad it could be: Negligible to FatalBA
Highest risk on small building demolition: Very high before controls (B), down to Medium after controls (A), on the United Kingdom 5 by 5 risk matrix (likely and fatal becomes unlikely and lost time injury).

What changes on your site

This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):

  • Will anyone work at height, anywhere a fall could hurt them?
  • Will anyone use a ladder or stepladder?
  • Will anyone work on a roof?
  • Is there a fragile roof, skylight or clear roof sheet?
  • Will you use a scaffold or mobile tower?

Licences and legal requirements in United Kingdom

Equipment on this job that needs a licence, ticket or training:

  • Excavator (360): CPCS or NPORS excavator card
  • Skid steer loader: CPCS or NPORS skid steer card
  • Site dumper: CPCS or NPORS forward tipping dumper card

Employers must assess the risks of their work and record the significant findings (required where you employ 5 or more people). On CDM projects, contractors give their RAMS to the principal contractor before starting, and brief the workers on it.

Rules that apply: Control of Asbestos Regulations 2012; Electricity at Work Regulations 1989; Gas Safety (Installation and Use) Regulations 1998; HSE HSG47 Avoiding danger from underground services; CDM Regulations 2015; Safety at Street Works and Road Works Code of Practice (Red Book); Manual Handling Operations Regulations 1992; Work at Height Regulations 2005; CDM Regulations 2015 and PUWER 1998; CDM Regulations 2015, regulation 19 (stability of structures); CDM Regulations 2015, regulation 20 (demolition); COSHH Regulations 2002; Control of Noise at Work Regulations 2005.

Why RAMS get rejected

Principal contractors send documents back for these reasons. This example avoids them, but check yours too.

  • The method statement is only a list of headings that repeats the risk table and never says how the work is done.
  • The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
  • Residual risk is still High after controls with no extra measures or explanation.
  • It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
  • Work on an older building with no reference to an asbestos survey.
  • Plant and access equipment listed with no inspection, thorough examination or competence evidence.
  • No briefing record, no revision history, or no named supervisor.

Questions

Do I need RAMS for small building demolition?

You must assess the risks of small building demolition and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.

Who signs the RAMS?

The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.

How long do I keep it?

Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.

What PPE is needed for small building demolition?

Usually Safety boots, Safety helmet, Hi-vis vest, Safety glasses, FFP3 dust mask, Ear defenders, Cut-resistant gloves, Half-mask respirator (P3 filters), Coveralls, Rigger gloves. The site rules may add more, so check with the principal contractor.