Method statement for non-licensed asbestos removal
You must assess the risks of non-licensed asbestos removal and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are falling from a roof edge, disturbing asbestos, electric shock from live wiring and falling through a fragile roof or skylight.
RAMS example: non-licensed asbestos removal
This is a complete RAMS for non-licensed asbestos removal, with 10 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
Risk assessment
| # | Activity | Hazards | Who might be harmed | Risk before | Controls | Risk after |
|---|---|---|---|---|---|---|
| 1 | Confirm the work is non-licensed. If it is notifiable non-licensed work (NNLW), notify HSE (HSENI in Northern Ireland) before starting and keep health records |
| Workers, Occupants, Public, Children | Very high (15) |
| Medium (5) |
| 2 | Set up the work area with barriers, signs and plastic sheeting, and close nearby windows |
| Workers, Occupants, Public, Children | Very high (15) |
| Medium (5) |
| 3 | Set up a decontamination point and put on disposable coveralls and a fitted respirator |
| Workers, Occupants, Public | Very high (15) |
| Medium (5) |
| 4 | Have a licensed electrician isolate and disconnect power to anything fixed to the sheets, and check where the service line is attached |
| Workers, Occupants | Very high (15) |
| Medium (5) |
| 5 | Use fall protection when removing from roofs, as sheets are fragile |
| Workers, People below | Very high (20) |
| Medium (5) |
| 6 | Wet the sheets and undo fixings by hand, removing sheets whole with no power tools or breaking |
| Workers, Occupants, Public | Very high (15) |
| Medium (8) |
| 7 | Lower sheets carefully; never drop or slide them |
| Workers, Occupants, Public, People below | Very high (15) |
| Medium (8) |
| 8 | Wrap sheets in heavy plastic, label as asbestos waste and take to an approved disposal site |
| Workers, Occupants, Public, Visitors | Very high (15) |
| Medium (5) |
| 9 | Clean up with an H-class vacuum and wet wipes, then decontaminate |
| Workers, Occupants, Public | Very high (15) |
| Medium (5) |
| 10 | Do a thorough visual check that no debris is left, and record it before others enter |
| Workers, Occupants, Public | Very high (15) |
| Medium (5) |
Method statement: sequence of work
- Confirm the work is non-licensed. If it is notifiable non-licensed work (NNLW), notify HSE (HSENI in Northern Ireland) before starting and keep health records
- Set up the work area with barriers, signs and plastic sheeting, and close nearby windows
- Set up a decontamination point and put on disposable coveralls and a fitted respirator
- Have a licensed electrician isolate and disconnect power to anything fixed to the sheets, and check where the service line is attached
- Use fall protection when removing from roofs, as sheets are fragile
- Wet the sheets and undo fixings by hand, removing sheets whole with no power tools or breaking
- Lower sheets carefully; never drop or slide them
- Wrap sheets in heavy plastic, label as asbestos waste and take to an approved disposal site
- Clean up with an H-class vacuum and wet wipes, then decontaminate
- Do a thorough visual check that no debris is left, and record it before others enter
PPE
Plant and equipment
Permits and plans
Emergency
Call 999. Add the nearest A&E, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this RAMS.
Free RAMS template for non-licensed asbestos removal
Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for non-licensed asbestos removal
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- RAMS read, explained and signed by everyone on the job
- Edge protection or fall protection in place before work at height starts
- Fragile roof areas and skylights covered or barricaded
- Asbestos register or survey checked for the work area
- Exclusion zone below the work and public kept out
- Weather checked: water, shade and rest breaks planned
- First aider, first aid kit and emergency number (999) confirmed
- PPE checked and worn: half-mask respirator (P3 filters), coveralls, chemical-resistant gloves, safety boots
The safe sequence of work
- Confirm the work is non-licensed. If it is notifiable non-licensed work (NNLW), notify HSE (HSENI in Northern Ireland) before starting and keep health records
- Set up the work area with barriers, signs and plastic sheeting, and close nearby windows
- Set up a decontamination point and put on disposable coveralls and a fitted respirator
- Have a licensed electrician isolate and disconnect power to anything fixed to the sheets, and check where the service line is attached
- Use fall protection when removing from roofs, as sheets are fragile
- Wet the sheets and undo fixings by hand, removing sheets whole with no power tools or breaking
- Lower sheets carefully; never drop or slide them
- Wrap sheets in heavy plastic, label as asbestos waste and take to an approved disposal site
- Clean up with an H-class vacuum and wet wipes, then decontaminate
- Do a thorough visual check that no debris is left, and record it before others enter
Hazards to watch on non-licensed asbestos removal
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone work at height, anywhere a fall could hurt them?
- Will anyone use a ladder or stepladder?
- Will anyone work on a roof?
- Will you use a scaffold or mobile tower?
- Will you use a MEWP (scissor lift or cherry picker)?
Why RAMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- The method statement is only a list of headings that repeats the risk table and never says how the work is done.
- The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
- Residual risk is still High after controls with no extra measures or explanation.
- It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
- Work on an older building with no reference to an asbestos survey.
- Plant and access equipment listed with no inspection, thorough examination or competence evidence.
- No briefing record, no revision history, or no named supervisor.
Questions
Do I need RAMS for non-licensed asbestos removal?
You must assess the risks of non-licensed asbestos removal and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
Who signs the RAMS?
The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.
How long do I keep it?
Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.
What PPE is needed for non-licensed asbestos removal?
Usually Half-mask respirator (P3 filters), Coveralls, Chemical-resistant gloves, Safety boots, Safety glasses, Rigger gloves, Hi-vis vest, Full body harness and lanyard, Safety helmet, Sun protection (sunscreen and neck cover). The site rules may add more, so check with the principal contractor.