Method statement for EV charger installation
You must assess the risks of EV charger installation and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are silica dust from concrete, brick, stone and tiles, hitting underground services, electric shock from live wiring and road traffic.
RAMS example: EV charger installation
This is a complete RAMS for EV charger installation, with 6 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
Risk assessment
| # | Activity | Hazards | Who might be harmed | Risk before | Controls | Risk after |
|---|---|---|---|---|---|---|
| 1 | Check the supply capacity and plan the cable route away from gas and water lines |
| Workers, Occupants, Public | Very high (15) |
| Medium (5) |
| 2 | Isolate at the consumer unit, lock off and label and test to prove dead |
| Workers, Occupants | Very high (15) |
| Medium (5) |
| 3 | Drill through brick or concrete with dust extraction |
| Workers, People nearby | Very high (20) |
| Medium (6) |
| 4 | Run the cable and mount the charger, keeping cables out of walkways |
| Workers, Visitors, Public, Road users | Very high (15) |
| Medium (6) |
| 5 | Terminate at the consumer unit and charger, fitting the right RCD protection |
| Workers, Occupants | Very high (15) |
| Medium (5) |
| 6 | Test, commission the charger with the client and clean up |
| Workers, Occupants, Visitors | Very high (15) |
| Medium (5) |
Method statement: sequence of work
- Check the supply capacity and plan the cable route away from gas and water lines
- Isolate at the consumer unit, lock off and label and test to prove dead
- Drill through brick or concrete with dust extraction
- Run the cable and mount the charger, keeping cables out of walkways
- Terminate at the consumer unit and charger, fitting the right RCD protection
- Test, commission the charger with the client and clean up
PPE
Plant and equipment
Permits and plans
Emergency
Call 999. Add the nearest A&E, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this RAMS.
Free RAMS template for EV charger installation
Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for EV charger installation
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- RAMS read, explained and signed by everyone on the job
- Isolation, lockout and test for dead done before work starts
- Utility plans checked and area scanned with CAT and Genny
- Water suppression or on-tool extraction fitted; respirators fit tested
- Exclusion zone and spotter set up for plant and traffic
- First aider, first aid kit and emergency number (999) confirmed
- PPE checked and worn: safety boots, safety glasses, rigger gloves, FFP3 dust mask
The safe sequence of work
- Check the supply capacity and plan the cable route away from gas and water lines
- Isolate at the consumer unit, lock off and label and test to prove dead
- Drill through brick or concrete with dust extraction
- Run the cable and mount the charger, keeping cables out of walkways
- Terminate at the consumer unit and charger, fitting the right RCD protection
- Test, commission the charger with the client and clean up
Hazards to watch on EV charger installation
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone work at height, anywhere a fall could hurt them?
- Will anyone use a ladder or stepladder?
- Will anyone work on a roof?
- Is there a fragile roof, skylight or clear roof sheet?
- Will you use a scaffold or mobile tower?
Why RAMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- The method statement is only a list of headings that repeats the risk table and never says how the work is done.
- The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
- Residual risk is still High after controls with no extra measures or explanation.
- It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
- Work on an older building with no reference to an asbestos survey.
- Plant and access equipment listed with no inspection, thorough examination or competence evidence.
- No briefing record, no revision history, or no named supervisor.
Questions
Do I need RAMS for EV charger installation?
You must assess the risks of EV charger installation and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
Who signs the RAMS?
The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.
How long do I keep it?
Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.
What PPE is needed for EV charger installation?
Usually Safety boots, Safety glasses, Rigger gloves, FFP3 dust mask, Ear defenders, Insulated electrical gloves, Arc-rated clothing and face shield, Half-mask respirator (P3 filters). The site rules may add more, so check with the principal contractor.