Method statement for house rewiring

You must assess the risks of house rewiring and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.

RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are silica dust from concrete, brick, stone and tiles, disturbing asbestos, electric shock from live wiring and falling through a floor opening or void.

RAMS example: house rewiring

This is a complete RAMS for house rewiring, with 9 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.

Risk Assessment and Method Statement (RAMS)
Rewire a house · Electrical · Example
Document RAMS-001 · Rev 1

Risk assessment

#ActivityHazardsWho might be harmedRisk beforeControlsRisk after
1Agree a room by room plan with the occupants and protect floors and furniture
  • Working in an occupied home or building
  • Slips and trips
Residents, Children, Staff, Workers, Visitors, PublicMedium (9)
  • Plan noisy, dusty or risky work for when the building is empty. Eliminate
  • Close off the work area with barriers, plastic sheeting or locked doors, and put up signs. Isolate
  • Keep fire exits and paths clear at all times. Control (procedures)
  • Tell occupants before you turn off power, water or gas, and before noisy or dusty work. Control (procedures)
  • Lock away tools, chemicals and materials each day, out of reach of children. Control (procedures)
  • Clean up dust and debris at the end of each day. Control (procedures)
  • Plan walkways and keep them clear of materials, hoses and leads. Eliminate
  • Run leads and hoses overhead on hooks or stands, or along walls, not across walkways. Control (engineering)
  • Slips and trips: see step 7 for the full controls Control (procedures)
Low (4)
2Check the asbestos survey and look for old lead paint before cutting into walls and ceilings
  • Disturbing asbestos
  • Lead paint dust and fumes
Workers, Occupants, Public, Residents, ChildrenVery high (15)
  • Before work on any building built before 2000, check the refurbishment and demolition asbestos survey for the work area (HSE HSG264). If there is none, presume asbestos is present or have it sampled before you start. Eliminate
  • Seal off the work area and keep everyone else out. Isolate
  • If asbestos must be disturbed, keep it wet, use hand tools not power tools, and clean up with an H-class vacuum. Control (engineering)
  • Most asbestos insulation, coatings and insulating board need a licensed contractor. Notifiable non-licensed work is notified to HSE before it starts. Other work needs trained workers and controls. Control (procedures)
  • Stop work straight away if you find suspect asbestos. Do not touch it and tell your supervisor. Control (procedures)
  • Wear a fit-tested FFP3 mask (or better) and disposable type 5 coveralls. PPE
  • Test old paint for lead before you sand, scrape, cut or heat it. Eliminate
  • Use wet scraping, chemical strippers or shrouded tools with extraction instead of dry sanding. Never burn off lead paint with an open flame. Reduce / substitute
  • Seal off the work area with plastic sheeting and keep residents, children and pets out. Isolate
  • Clean up with an H-class vacuum and wet wipes. Never dry sweep. Control (engineering)
  • Wash hands and face before eating, drinking or smoking. Change out of dusty clothes before going home. Control (procedures)
  • Wear an FFP3 mask, disposable coveralls and gloves. PPE
Medium (5)
3Isolate the circuits being worked on, lock off and label and test to prove dead; run any temporary supply through RCD protection
  • Electric shock from live wiring
  • Stored energy
  • Electric shock from leads and power tools
Workers, OccupantsVery high (15)
  • Isolate the power before any work. Do not work live. Eliminate
  • Lock out and tag the isolation point with your own personal lock and danger tag. Isolate
  • Prove dead at the point of work with an approved voltage indicator (GS38), and prove the tester before and after. Control (engineering)
  • Only competent, qualified electricians do electrical work, following a safe isolation procedure. Control (procedures)
  • Check for back feeds from solar, batteries and generators that can keep a circuit live after the main switch is off. Control (procedures)
  • Release or block all stored energy before work: release the pressure in pipes, tanks and hoses, bleed hydraulics, release springs, lower loads. Eliminate
  • Lock out and tag all energy sources with personal locks. Isolate
  • Put mechanical blocks or props under raised parts like buckets, tipper bodies and doors. Control (engineering)
  • Test that the system is dead and nothing can move before you start. Control (procedures)
  • Follow the maker's procedure, for example for garage door and roller door springs. Control (procedures)
  • Use battery-powered tools where you can. Reduce / substitute
  • Use 110V tools through a centre-tapped transformer, or battery tools. Use an RCD on any 230V supply. Control (engineering)
  • Keep leads off the ground and out of water, using lead stands or hooks. Control (engineering)
  • Check leads, plugs and tools before every use. Tag out and remove anything damaged. Control (procedures)
  • Keep tools and leads inspected and PAT tested on a regular schedule. Control (procedures)
  • Do not use tools in rain or wet areas unless they are rated for it. Control (procedures)
Medium (5)
4Work in the ceiling space only on joists, with lighting and short breaks in hot weather
  • Falling through a floor opening or void
  • Heat stress
  • Poor lighting and night work
  • Bites and stings
Workers, Visitors, PublicVery high (15)
  • Cover every hole and penetration with a fixed, secured cover marked "HOLE" or "DANGER". Isolate
  • Put guardrails with toe boards around stairwells, lift shafts, voids and open edges. Isolate
  • Install stairs early and fit temporary handrails as soon as they go in. Control (engineering)
  • Never remove a cover or guardrail without approval. Put it back straight away. Control (procedures)
  • Schedule heavy work for the cooler part of the day. Eliminate
  • Provide shade over work and rest areas, and fans or cooling in roof spaces. Control (engineering)
  • Supply cool drinking water close by and drink a cup every 15 to 20 minutes. Control (procedures)
  • Take regular rest breaks in the shade, more often as it gets hotter. Control (procedures)
  • Plan work for daylight hours where you can. Eliminate
  • Set up enough temporary lighting for the task, walkways, stairs and access points. Control (engineering)
  • Aim lights so they do not dazzle plant operators or drivers. Control (engineering)
  • Check lighting before work starts and carry a torch or head lamp. Control (procedures)
  • Check work areas before starting, and get pest control to remove nests. Eliminate
  • Look before you reach into dark spaces. Control (procedures)
  • Ask owners to keep pets away from the work area. Control (procedures)
  • Know who has allergies and keep their medication, such as an adrenaline auto-injector, close by. Control (procedures)
Medium (8)
5Scan for pipes, then chase walls and drill holes using dust extraction
  • Silica dust from concrete, brick, stone and tiles
  • General dust
  • Injury from power tools
  • Gas and fuel lines
Workers, People nearby, Occupants, PublicVery high (20)
  • Order materials cut to size, or use low-dust methods such as score and snap or a block splitter. Reduce / substitute
  • Cut outdoors or in a separate area, with other people well away and upwind. Isolate
  • Use water on the blade or on-tool dust extraction connected to an H-class vacuum. Control (engineering)
  • Clean up with a vacuum or wet methods. Never dry sweep or use compressed air. Control (procedures)
  • Do a COSHH assessment and keep exposure below the workplace exposure limit (0.1 mg/m3 respirable crystalline silica, 8 hours). Control (procedures)
  • Workers regularly exposed to silica dust get health surveillance (COSHH reg 11, HSE G404). Control (procedures)
  • Wear a fit-tested FFP3 mask. PPE
  • Use low-dust products, such as dust-reduced or pre-mixed compounds. Reduce / substitute
  • Seal off the work area with plastic sheeting in occupied buildings. Isolate
  • Use tools with dust extraction and a vacuum for clean up. Control (engineering)
  • Lightly mist the area with water to keep dust down, away from anything electrical. Control (engineering)
  • Keep all guards fitted and working. Never tie back or remove a guard. Control (engineering)
  • Clamp or secure the work piece. Do not hold it by hand. Control (engineering)
  • Only trained, competent people use power tools, following the maker's instructions. Control (procedures)
  • Check tools before use. Unplug or remove the battery before changing blades or bits. Control (procedures)
  • Isolate and purge the line before work, with the owner's approval. Eliminate
  • Lock off and tag the isolation valve. Isolate
  • Check for leaks with a gas detector before and during work, and ventilate the area. Control (engineering)
  • Only Gas Safe registered engineers work on gas fittings. Control (procedures)
Medium (6)
6Strip out old wiring, treating every cable as live until it is proven dead
  • Electric shock from live wiring
  • Cuts from sharp edges
Workers, OccupantsVery high (15)
  • If live work cannot be avoided, use a permit, a safety observer and insulated tools. Control (procedures)
  • Wear insulated gloves, arc-rated clothing and a face shield when testing or working near live parts. PPE
  • Electric shock from live wiring: see step 3 for the full controls Control (procedures)
  • Deburr or cover sharp edges, and fit edge protectors on exposed sheet metal. Control (engineering)
  • Use knives with retractable or self-retracting blades. Control (engineering)
  • Cut away from your body and keep your other hand clear. Control (procedures)
  • Put used blades in a blade bin or sharps container. Control (procedures)
  • Use two people to handle large sheets of metal or glass. Control (procedures)
  • Wear cut-resistant gloves and long sleeves. PPE
Medium (5)
7Pull in new cables, keeping walkways and stairs clear
  • Slips and trips
  • Lifting and carrying heavy loads
Workers, Visitors, PublicHigh (12)
  • Plan walkways and keep them clear of materials, hoses and leads. Eliminate
  • Run leads and hoses overhead on hooks or stands, or along walls, not across walkways. Control (engineering)
  • Fill or cover holes, and lay boards or mats on muddy access paths. Control (engineering)
  • Clean up offcuts, packaging and spills as you go, not at the end of the day. Control (procedures)
  • Keep work areas, stairs and access paths well lit. Control (procedures)
  • Wear safety boots with good grip, laced up. PPE
  • Plan to avoid carrying: have materials delivered, and old items picked up, as close as possible to where they are used. Eliminate
  • Use lighter or smaller loads: order smaller bags and shorter lengths, and drain or break down old items before moving them. Reduce / substitute
  • Use trolleys, pallet jacks, hoists, vacuum lifters or plant instead of carrying by hand. Control (engineering)
  • Use a two-person lift for anything heavy, long or awkward. Plan the route first and clear it. Control (procedures)
  • Keep the load close, back straight and no twisting. Turn with your feet. Control (procedures)
  • Rotate tasks and take breaks on long lifting jobs. Control (procedures)
  • Wear gloves for grip and safety boots to protect your feet. PPE
Medium (6)
8Fit off sockets, switches and lights from a stable step or platform
  • Electric shock from leads and power tools
  • Falling from a ladder
  • Repetitive work and awkward postures
WorkersHigh (12)
  • Wear safety boots and dry gloves. PPE
  • Electric shock from leads and power tools: see step 3 for the full controls Control (procedures)
  • Use a podium step, mobile tower or MEWP for longer jobs instead of a straight ladder. Reduce / substitute
  • Use EN 131 professional ladders in good condition. Remove any damaged ladder from site. Control (engineering)
  • Set extension ladders at a 4 to 1 angle on firm, level ground, tied or footed, and reaching 1 metre above the landing. Control (engineering)
  • Use ladders only for short, light work (about 30 minutes in one spot). Do not carry heavy or awkward loads up a ladder. Control (procedures)
  • Keep three points of contact and your belt buckle between the stiles. Do not overreach. Control (procedures)
  • Use tools that cut the effort: powered screwdrivers, long-handled tools and extension poles for overhead work. Reduce / substitute
  • Set work up at waist height on benches or trestles where you can. Control (engineering)
  • Use light tools with good grips, and keep blades and bits sharp. Control (engineering)
  • Rotate tasks and take short breaks every hour on repetitive work. Control (procedures)
  • Warm up before heavy physical work and report aches and pains early. Control (procedures)
Medium (8)
9Test every circuit, re-energise, make good and hand over the certificate
  • Electric shock from live wiring
  • Poor housekeeping and waste
Workers, Occupants, VisitorsVery high (15)
  • Electric shock from live wiring: see step 3 for the full controls Control (procedures)
  • Order materials to size and send packaging back where you can. Eliminate
  • Put skips and waste chutes close to the work. Control (engineering)
  • Clean as you go, and do a full clean up at the end of each day. Control (procedures)
  • Keep exits, stairs and walkways clear at all times. Control (procedures)
  • Stack materials neatly on level ground, away from edges. Control (procedures)
  • Use a registered waste carrier and keep waste transfer notes for at least 2 years. Keep hazardous waste such as asbestos separate, with consignment notes (special waste in Scotland). Control (procedures)
  • Wear gloves when handling waste. PPE
Medium (5)

Method statement: sequence of work

  1. Agree a room by room plan with the occupants and protect floors and furniture
  2. Check the asbestos survey and look for old lead paint before cutting into walls and ceilings
  3. Isolate the circuits being worked on, lock off and label and test to prove dead; run any temporary supply through RCD protection
  4. Work in the ceiling space only on joists, with lighting and short breaks in hot weather
  5. Scan for pipes, then chase walls and drill holes using dust extraction
  6. Strip out old wiring, treating every cable as live until it is proven dead
  7. Pull in new cables, keeping walkways and stairs clear
  8. Fit off sockets, switches and lights from a stable step or platform
  9. Test every circuit, re-energise, make good and hand over the certificate

PPE

Safety bootsSafety glassesFFP3 dust maskRigger glovesKnee padsHalf-mask respirator (P3 filters)CoverallsInsulated electrical glovesArc-rated clothing and face shieldSun protection (sunscreen and neck cover)Hi-vis vestEar defendersCut-resistant glovesSafety helmet

Plant and equipment

Electrical test equipment (multifunction tester)Power drillHand toolsStepladderSDS drill

Permits and plans

Permit to work (electrical isolation)

Emergency

Call 999. Add the nearest A&E, the assembly point and the first aider for your site.

Sign-off

Supervisor and every worker sign to confirm they have read and understood this RAMS.

Free RAMS template for house rewiring

Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.

Make yours in 2 minutes

Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.

Start this RAMS

Pre-start checklist for house rewiring

Tick these off before work starts. They come from the hazards, permits and equipment in this job.

The safe sequence of work

  1. Agree a room by room plan with the occupants and protect floors and furniture
  2. Check the asbestos survey and look for old lead paint before cutting into walls and ceilings
  3. Isolate the circuits being worked on, lock off and label and test to prove dead; run any temporary supply through RCD protection
  4. Work in the ceiling space only on joists, with lighting and short breaks in hot weather
  5. Scan for pipes, then chase walls and drill holes using dust extraction
  6. Strip out old wiring, treating every cable as live until it is proven dead
  7. Pull in new cables, keeping walkways and stairs clear
  8. Fit off sockets, switches and lights from a stable step or platform
  9. Test every circuit, re-energise, make good and hand over the certificate

Hazards to watch on house rewiring

The hazards most specific to this job, and the step where each one comes up.

Step 4Poor lighting and night workDim or dark work areas hide trip hazards, edges and moving plant, and make workers hard to see.
Step 4Bites and stingsSpiders, wasps, bees, ticks and dogs bite or sting workers in roof spaces, under floors and in gardens.
Step 2Lead paint dust and fumesLead paint was common before the 1970s and was used in some buildings until 1992. Sanding, scraping or heating it releases dust or fumes that poison workers and families, especially children.
Step 3, 8Electric shock from leads and power toolsDamaged leads, plugs or tools, or water near power, give the user an electric shock.
Step 3Stored energyEnergy left in springs, hydraulics, compressed gas, raised loads or capacitors releases suddenly and crushes or injures workers.
Step 5Gas and fuel linesDamaging or opening a gas or fuel line causes a leak, fire or explosion.
Very likelyLikelyPossibleUnlikelyVery unlikelyHow bad it could be: Negligible to FatalBA
Highest risk on house rewiring: Very high before controls (B), down to Medium after controls (A), on the United Kingdom 5 by 5 risk matrix (likely and fatal becomes unlikely and major injury).

What changes on your site

This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):

  • Will anyone work at height, anywhere a fall could hurt them?
  • Will anyone work on a roof?
  • Is there a fragile roof, skylight or clear roof sheet?
  • Will you use a scaffold or mobile tower?
  • Will you use a MEWP (scissor lift or cherry picker)?

Why RAMS get rejected

Principal contractors send documents back for these reasons. This example avoids them, but check yours too.

  • The method statement is only a list of headings that repeats the risk table and never says how the work is done.
  • The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
  • Residual risk is still High after controls with no extra measures or explanation.
  • It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
  • Work on an older building with no reference to an asbestos survey.
  • Plant and access equipment listed with no inspection, thorough examination or competence evidence.
  • No briefing record, no revision history, or no named supervisor.

Questions

Do I need RAMS for house rewiring?

You must assess the risks of house rewiring and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.

Who signs the RAMS?

The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.

How long do I keep it?

Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.

What PPE is needed for house rewiring?

Usually Safety boots, Safety glasses, FFP3 dust mask, Rigger gloves, Knee pads, Half-mask respirator (P3 filters), Coveralls, Insulated electrical gloves, Arc-rated clothing and face shield, Sun protection (sunscreen and neck cover), Hi-vis vest, Ear defenders, Cut-resistant gloves, Safety helmet. The site rules may add more, so check with the principal contractor.