Method statement for plasterboard repair

You must assess the risks of plasterboard repair and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.

RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are disturbing asbestos, electric shock from live wiring, falling from a ladder and cuts from sharp edges.

RAMS example: plasterboard repair

This is a complete RAMS for plasterboard repair, with 5 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.

Risk Assessment and Method Statement (RAMS)
Plasterboard patching and repairs · Plastering and dry lining · Example
Document RAMS-001 · Rev 1

Risk assessment

#ActivityHazardsWho might be harmedRisk beforeControlsRisk after
1Check for asbestos in older linings before cutting
  • Disturbing asbestos
Workers, Occupants, PublicVery high (15)
  • Before work on any building built before 2000, check the refurbishment and demolition asbestos survey for the work area (HSE HSG264). If there is none, presume asbestos is present or have it sampled before you start. Eliminate
  • Seal off the work area and keep everyone else out. Isolate
  • If asbestos must be disturbed, keep it wet, use hand tools not power tools, and clean up with an H-class vacuum. Control (engineering)
  • Most asbestos insulation, coatings and insulating board need a licensed contractor. Notifiable non-licensed work is notified to HSE before it starts. Other work needs trained workers and controls. Control (procedures)
  • Stop work straight away if you find suspect asbestos. Do not touch it and tell your supervisor. Control (procedures)
  • Wear a fit-tested FFP3 mask (or better) and disposable type 5 coveralls. PPE
Medium (5)
2Check for cables and pipes behind the wall
  • Electric shock from live wiring
Workers, OccupantsVery high (15)
  • Isolate the power before any work. Do not work live. Eliminate
  • Lock out and tag the isolation point with your own personal lock and danger tag. Isolate
  • Prove dead at the point of work with an approved voltage indicator (GS38), and prove the tester before and after. Control (engineering)
  • Only competent, qualified electricians do electrical work, following a safe isolation procedure. Control (procedures)
  • Check for back feeds from solar, batteries and generators that can keep a circuit live after the main switch is off. Control (procedures)
  • If live work cannot be avoided, use a permit, a safety observer and insulated tools. Control (procedures)
  • Wear insulated gloves, arc-rated clothing and a face shield when testing or working near live parts. PPE
Medium (5)
3Cut out damage and fit a patch
  • Cuts from sharp edges
  • General dust
Workers, OccupantsMedium (8)
  • Deburr or cover sharp edges, and fit edge protectors on exposed sheet metal. Control (engineering)
  • Use knives with retractable or self-retracting blades. Control (engineering)
  • Cut away from your body and keep your other hand clear. Control (procedures)
  • Put used blades in a blade bin or sharps container. Control (procedures)
  • Use two people to handle large sheets of metal or glass. Control (procedures)
  • Wear cut-resistant gloves and long sleeves. PPE
  • Use low-dust products, such as dust-reduced or pre-mixed compounds. Reduce / substitute
  • Seal off the work area with plastic sheeting in occupied buildings. Isolate
  • Use tools with dust extraction and a vacuum for clean up. Control (engineering)
  • Lightly mist the area with water to keep dust down, away from anything electrical. Control (engineering)
  • Never dry sweep or blow dust off with compressed air. Control (procedures)
  • Wear a dust mask and safety glasses. PPE
Low (4)
4Set, sand and finish
  • General dust
  • Falling from a ladder
Workers, OccupantsHigh (12)
  • General dust: see step 3 for the full controls Control (procedures)
  • Use a podium step, mobile tower or MEWP for longer jobs instead of a straight ladder. Reduce / substitute
  • Use EN 131 professional ladders in good condition. Remove any damaged ladder from site. Control (engineering)
  • Set extension ladders at a 4 to 1 angle on firm, level ground, tied or footed, and reaching 1 metre above the landing. Control (engineering)
  • Use ladders only for short, light work (about 30 minutes in one spot). Do not carry heavy or awkward loads up a ladder. Control (procedures)
  • Keep three points of contact and your belt buckle between the stiles. Do not overreach. Control (procedures)
  • Do not work off the top three rungs of a leaning ladder. On a stepladder, do not stand on the top two steps (top three on swing-back or double-sided steps) unless there is a suitable handhold. Control (procedures)
  • Check the ladder before each use: feet, rungs, stiles and locks. Control (procedures)
  • Wear non-slip safety boots with clean soles. PPE
Medium (8)
5Clean up
  • Poor housekeeping and waste
Workers, VisitorsMedium (8)
  • Order materials to size and send packaging back where you can. Eliminate
  • Put skips and waste chutes close to the work. Control (engineering)
  • Clean as you go, and do a full clean up at the end of each day. Control (procedures)
  • Keep exits, stairs and walkways clear at all times. Control (procedures)
  • Stack materials neatly on level ground, away from edges. Control (procedures)
  • Use a registered waste carrier and keep waste transfer notes for at least 2 years. Keep hazardous waste such as asbestos separate, with consignment notes (special waste in Scotland). Control (procedures)
  • Wear gloves when handling waste. PPE
Low (4)

Method statement: sequence of work

  1. Check for asbestos in older linings before cutting
  2. Check for cables and pipes behind the wall
  3. Cut out damage and fit a patch
  4. Set, sand and finish
  5. Clean up

PPE

FFP3 dust maskSafety glassesSafety bootsHalf-mask respirator (P3 filters)CoverallsRigger glovesCut-resistant glovesSafety helmet

Plant and equipment

Hand toolsPower sanderStepladder

Emergency

Call 999. Add the nearest A&E, the assembly point and the first aider for your site.

Sign-off

Supervisor and every worker sign to confirm they have read and understood this RAMS.

Free RAMS template for plasterboard repair

Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.

Make yours in 2 minutes

Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.

Start this RAMS

Pre-start checklist for plasterboard repair

Tick these off before work starts. They come from the hazards, permits and equipment in this job.

The safe sequence of work

  1. Check for asbestos in older linings before cutting
  2. Check for cables and pipes behind the wall
  3. Cut out damage and fit a patch
  4. Set, sand and finish
  5. Clean up

Hazards to watch on plasterboard repair

The hazards most specific to this job, and the step where each one comes up.

Step 1Disturbing asbestosBuildings built before 2000 may contain asbestos. Drilling, cutting or breaking it releases fibres that cause cancer years later.
Step 3, 4General dustDust from plasterboard, filler, cement and clean up irritates eyes and lungs and makes it hard to see.
Step 4Falling from a ladderThe ladder slips or tips, or the worker overreaches, and they fall onto a hard surface.
Step 3Cuts from sharp edgesSheet metal, glass, blades, cable tray and offcuts cut hands and arms.
Step 2Electric shock from live wiringContact with live wires, distribution boards or equipment gives an electric shock or arc flash burn that can kill.
Step 5Poor housekeeping and wasteRubbish, offcuts and materials left lying around cause trips, cuts and fires, and block exits.
Very likelyLikelyPossibleUnlikelyVery unlikelyHow bad it could be: Negligible to FatalBA
Highest risk on plasterboard repair: Very high before controls (B), down to Medium after controls (A), on the United Kingdom 5 by 5 risk matrix (possible and fatal becomes unlikely and major injury).

What changes on your site

This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):

  • Will anyone work at height, anywhere a fall could hurt them?
  • Will anyone work on a roof?
  • Is there a fragile roof, skylight or clear roof sheet?
  • Will you use a scaffold or mobile tower?
  • Will you use a MEWP (scissor lift or cherry picker)?

Why RAMS get rejected

Principal contractors send documents back for these reasons. This example avoids them, but check yours too.

  • The method statement is only a list of headings that repeats the risk table and never says how the work is done.
  • The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
  • Residual risk is still High after controls with no extra measures or explanation.
  • It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
  • Work on an older building with no reference to an asbestos survey.
  • Plant and access equipment listed with no inspection, thorough examination or competence evidence.
  • No briefing record, no revision history, or no named supervisor.

Questions

Do I need RAMS for plasterboard repair?

You must assess the risks of plasterboard repair and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.

Who signs the RAMS?

The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.

How long do I keep it?

Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.

What PPE is needed for plasterboard repair?

Usually FFP3 dust mask, Safety glasses, Safety boots, Half-mask respirator (P3 filters), Coveralls, Rigger gloves, Cut-resistant gloves, Safety helmet. The site rules may add more, so check with the principal contractor.