Method statement for dry lining
You must assess the risks of dry lining and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are falling from height, electric shock from live wiring, scaffold collapse or fall from scaffold and lifting and carrying heavy loads.
RAMS example: dry lining
This is a complete RAMS for dry lining, with 9 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
Risk assessment
| # | Activity | Hazards | Who might be harmed | Risk before | Controls | Risk after |
|---|---|---|---|---|---|---|
| 1 | Check services are installed and isolated where you will fix |
| Workers, Occupants | Very high (15) |
| Medium (5) |
| 2 | Stack sheets flat on a level floor, not leaning against walls, and spread the load |
| Workers, Public, People below | High (12) |
| Medium (8) |
| 3 | Carry sheets with two people or a sheet trolley |
| Workers | High (12) |
| Medium (6) |
| 4 | Set up a platform ladder or mobile scaffold for ceilings and high walls |
| Workers, People below, Public | Very high (20) |
| Medium (8) |
| 5 | Cut sheets with a sharp knife, cutting away from your body; use extraction if sawing |
| Workers, Occupants | Medium (8) |
| Low (4) |
| 6 | Lift ceiling sheets with a sheet lifter, not your head |
| Workers, Public, People below | High (12) |
| Medium (8) |
| 7 | Screw sheets off, keeping clear of cables and pipes behind |
| Workers, People nearby, Occupants | Very high (15) |
| Medium (6) |
| 8 | Use adhesives with ventilation |
| Workers, Occupants | Medium (9) |
| Medium (6) |
| 9 | Pick up offcuts and screws |
| Workers, Visitors, Public | Medium (8) |
| Low (4) |
Method statement: sequence of work
- Check services are installed and isolated where you will fix
- Stack sheets flat on a level floor, not leaning against walls, and spread the load
- Carry sheets with two people or a sheet trolley
- Set up a platform ladder or mobile scaffold for ceilings and high walls
- Cut sheets with a sharp knife, cutting away from your body; use extraction if sawing
- Lift ceiling sheets with a sheet lifter, not your head
- Screw sheets off, keeping clear of cables and pipes behind
- Use adhesives with ventilation
- Pick up offcuts and screws
PPE
Plant and equipment
Permits and plans
Emergency
Call 999. Add the nearest A&E, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this RAMS.
Free RAMS template for dry lining
Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for dry lining
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- RAMS read, explained and signed by everyone on the job
- Edge protection or fall protection in place before work at height starts
- Ladder inspected, secured and extending 1 m above the landing
- Scaffold inspected in the last 7 days, tag in date
- Exclusion zone below the work and public kept out
- First aider, first aid kit and emergency number (999) confirmed
- PPE checked and worn: safety boots, safety glasses, rigger gloves, FFP3 dust mask
The safe sequence of work
- Check services are installed and isolated where you will fix
- Stack sheets flat on a level floor, not leaning against walls, and spread the load
- Carry sheets with two people or a sheet trolley
- Set up a platform ladder or mobile scaffold for ceilings and high walls
- Cut sheets with a sharp knife, cutting away from your body; use extraction if sawing
- Lift ceiling sheets with a sheet lifter, not your head
- Screw sheets off, keeping clear of cables and pipes behind
- Use adhesives with ventilation
- Pick up offcuts and screws
Hazards to watch on dry lining
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone work on a roof?
- Is there a fragile roof, skylight or clear roof sheet?
- Will you use a MEWP (scissor lift or cherry picker)?
- Was the building built before 2000?
- Will you sand, scrape, burn off or cut old paint in a building from before 1992?
Licences and legal requirements in United Kingdom
Equipment on this job that needs a licence, ticket or training:
- Mobile access tower: PASMA certificate
Employers must assess the risks of their work and record the significant findings (required where you employ 5 or more people). On CDM projects, contractors give their RAMS to the principal contractor before starting, and brief the workers on it.
Rules that apply: Electricity at Work Regulations 1989; Manual Handling Operations Regulations 1992; Work at Height Regulations 2005, regulation 10 (falling objects); Work at Height Regulations 2005; Provision and Use of Work Equipment Regulations 1998 (PUWER); COSHH Regulations 2002.
Why RAMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- The method statement is only a list of headings that repeats the risk table and never says how the work is done.
- The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
- Residual risk is still High after controls with no extra measures or explanation.
- It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
- Work on an older building with no reference to an asbestos survey.
- Plant and access equipment listed with no inspection, thorough examination or competence evidence.
- No briefing record, no revision history, or no named supervisor.
Questions
Do I need RAMS for dry lining?
You must assess the risks of dry lining and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
Who signs the RAMS?
The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.
How long do I keep it?
Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.
What PPE is needed for dry lining?
Usually Safety boots, Safety glasses, Rigger gloves, FFP3 dust mask, Safety helmet, Hi-vis vest, Cut-resistant gloves, Knee pads, Ear defenders, Chemical-resistant gloves, Safety goggles, Half-mask respirator (P3 filters), Coveralls. The site rules may add more, so check with the principal contractor.