Method statement for dry lining

You must assess the risks of dry lining and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.

RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are falling from height, electric shock from live wiring, scaffold collapse or fall from scaffold and lifting and carrying heavy loads.

RAMS example: dry lining

This is a complete RAMS for dry lining, with 9 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.

Risk Assessment and Method Statement (RAMS)
Hang plasterboard · Plastering and dry lining · Example
Document RAMS-001 · Rev 1

Risk assessment

#ActivityHazardsWho might be harmedRisk beforeControlsRisk after
1Check services are installed and isolated where you will fix
  • Electric shock from live wiring
Workers, OccupantsVery high (15)
  • Isolate the power before any work. Do not work live. Eliminate
  • Lock out and tag the isolation point with your own personal lock and danger tag. Isolate
  • Prove dead at the point of work with an approved voltage indicator (GS38), and prove the tester before and after. Control (engineering)
  • Only competent, qualified electricians do electrical work, following a safe isolation procedure. Control (procedures)
  • Check for back feeds from solar, batteries and generators that can keep a circuit live after the main switch is off. Control (procedures)
  • If live work cannot be avoided, use a permit, a safety observer and insulated tools. Control (procedures)
  • Wear insulated gloves, arc-rated clothing and a face shield when testing or working near live parts. PPE
Medium (5)
2Stack sheets flat on a level floor, not leaning against walls, and spread the load
  • Lifting and carrying heavy loads
  • Falling tools and materials
Workers, Public, People belowHigh (12)
  • Plan to avoid carrying: have materials delivered, and old items picked up, as close as possible to where they are used. Eliminate
  • Use lighter or smaller loads: order smaller bags and shorter lengths, and drain or break down old items before moving them. Reduce / substitute
  • Lifting and carrying heavy loads: see step 6 for the full controls Control (procedures)
  • Barricade and sign the drop zone under overhead work so nobody walks beneath. Isolate
  • Fit toe boards, kick plates and mesh screens on scaffolds and edges. Control (engineering)
  • Use catch fans, debris netting or covered walkways where people pass below. Control (engineering)
  • Tether hand tools when working at height. Control (engineering)
  • Keep platforms tidy. Do not stack materials near edges or above toe board height. Control (procedures)
  • Lower materials with a hoist, chute or rope. Never throw or drop anything down. Control (procedures)
  • Wear a hard hat anywhere objects could fall. PPE
Medium (8)
3Carry sheets with two people or a sheet trolley
  • Lifting and carrying heavy loads
WorkersHigh (12)
  • Use trolleys, pallet jacks, hoists, vacuum lifters or plant instead of carrying by hand. Control (engineering)
  • Use a two-person lift for anything heavy, long or awkward. Plan the route first and clear it. Control (procedures)
  • Lifting and carrying heavy loads: see step 6 for the full controls Control (procedures)
Medium (6)
4Set up a platform ladder or mobile scaffold for ceilings and high walls
  • Falling from height
  • Falling from a ladder
  • Scaffold collapse or fall from scaffold
Workers, People below, PublicVery high (20)
  • Do the work from the ground where you can, for example pre-assemble on the ground or use extension poles. Eliminate
  • Install guardrails or edge protection on all open edges before work starts. Isolate
  • Use a scaffold, mobile tower or MEWP instead of working off a ladder. Control (engineering)
  • Where edge protection is not practical, use a fall restraint or fall arrest system on a rated anchor point. Control (engineering)
  • Have a rescue plan so a worker hanging in a harness can be brought down within minutes. Control (procedures)
  • Use a podium step, mobile tower or MEWP for longer jobs instead of a straight ladder. Reduce / substitute
  • Use EN 131 professional ladders in good condition. Remove any damaged ladder from site. Control (engineering)
  • Set extension ladders at a 4 to 1 angle on firm, level ground, tied or footed, and reaching 1 metre above the landing. Control (engineering)
  • Use ladders only for short, light work (about 30 minutes in one spot). Do not carry heavy or awkward loads up a ladder. Control (procedures)
  • Keep three points of contact and your belt buckle between the stiles. Do not overreach. Control (procedures)
  • Scaffold is built, altered and taken down only by CISRS-carded scaffolders, to TG20 or a specific design. Control (engineering)
  • Fit guardrails, mid rails and toe boards on every working platform. Control (engineering)
  • Use mobile scaffolds only on firm, level ground with castors locked and outriggers fitted. Never move one with anyone on it. Control (engineering)
  • Mobile towers are built by PASMA-trained workers. Control (procedures)
  • Inspect the scaffold before first use, after any change or bad weather, and at least every 7 days. Record it on the tag and register. Control (procedures)
  • Do not overload platforms. Know the duty rating and keep material stacks over the standards. Control (procedures)
Medium (8)
5Cut sheets with a sharp knife, cutting away from your body; use extraction if sawing
  • Cuts from sharp edges
  • General dust
Workers, OccupantsMedium (8)
  • Deburr or cover sharp edges, and fit edge protectors on exposed sheet metal. Control (engineering)
  • Use knives with retractable or self-retracting blades. Control (engineering)
  • Cut away from your body and keep your other hand clear. Control (procedures)
  • Put used blades in a blade bin or sharps container. Control (procedures)
  • Use two people to handle large sheets of metal or glass. Control (procedures)
  • Wear cut-resistant gloves and long sleeves. PPE
  • Use low-dust products, such as dust-reduced or pre-mixed compounds. Reduce / substitute
  • Seal off the work area with plastic sheeting in occupied buildings. Isolate
  • Use tools with dust extraction and a vacuum for clean up. Control (engineering)
  • Lightly mist the area with water to keep dust down, away from anything electrical. Control (engineering)
  • Never dry sweep or blow dust off with compressed air. Control (procedures)
  • Wear a dust mask and safety glasses. PPE
Low (4)
6Lift ceiling sheets with a sheet lifter, not your head
  • Lifting and carrying heavy loads
  • Falling tools and materials
  • Repetitive work and awkward postures
Workers, Public, People belowHigh (12)
  • Plan to avoid carrying: have materials delivered, and old items picked up, as close as possible to where they are used. Eliminate
  • Use lighter or smaller loads: order smaller bags and shorter lengths, and drain or break down old items before moving them. Reduce / substitute
  • Use trolleys, pallet jacks, hoists, vacuum lifters or plant instead of carrying by hand. Control (engineering)
  • Use a two-person lift for anything heavy, long or awkward. Plan the route first and clear it. Control (procedures)
  • Keep the load close, back straight and no twisting. Turn with your feet. Control (procedures)
  • Falling tools and materials: see step 2 for the full controls Control (procedures)
  • Use tools that cut the effort: powered screwdrivers, long-handled tools and extension poles for overhead work. Reduce / substitute
  • Set work up at waist height on benches or trestles where you can. Control (engineering)
  • Use light tools with good grips, and keep blades and bits sharp. Control (engineering)
  • Rotate tasks and take short breaks every hour on repetitive work. Control (procedures)
  • Warm up before heavy physical work and report aches and pains early. Control (procedures)
Medium (8)
7Screw sheets off, keeping clear of cables and pipes behind
  • Injury from power tools
  • Electric shock from live wiring
Workers, People nearby, OccupantsVery high (15)
  • Keep all guards fitted and working. Never tie back or remove a guard. Control (engineering)
  • Clamp or secure the work piece. Do not hold it by hand. Control (engineering)
  • Only trained, competent people use power tools, following the maker's instructions. Control (procedures)
  • Check tools before use. Unplug or remove the battery before changing blades or bits. Control (procedures)
  • No loose clothing, jewellery or long hair near spinning parts. Control (procedures)
  • Wear safety glasses and hearing protection. Do not wear loose gloves on drills or other rotating tools. PPE
  • Electric shock from live wiring: see step 1 for the full controls Control (procedures)
Medium (6)
8Use adhesives with ventilation
  • Hazardous chemicals
Workers, OccupantsMedium (9)
  • Choose the least harmful product that does the job, for example water-based instead of solvent-based. Reduce / substitute
  • Use chemicals in well-ventilated areas, or use fans and extraction in closed rooms. Control (engineering)
  • Do a COSHH assessment and read the Safety Data Sheet (SDS) before use. Control (procedures)
  • Keep chemicals in labelled containers. Never decant into drink bottles. Control (procedures)
  • Store chemicals away from heat, food and drink, and keep products that react with each other apart. Control (procedures)
  • Have eye wash and a spill kit nearby, and wash hands before eating. Control (procedures)
  • Wear chemical-resistant gloves and safety glasses or goggles as listed on the SDS. PPE
  • Use a respirator with the right cartridge if the SDS calls for one. PPE
Medium (6)
9Pick up offcuts and screws
  • Poor housekeeping and waste
  • Slips and trips
Workers, Visitors, PublicMedium (8)
  • Order materials to size and send packaging back where you can. Eliminate
  • Put skips and waste chutes close to the work. Control (engineering)
  • Clean as you go, and do a full clean up at the end of each day. Control (procedures)
  • Keep exits, stairs and walkways clear at all times. Control (procedures)
  • Stack materials neatly on level ground, away from edges. Control (procedures)
  • Use a registered waste carrier and keep waste transfer notes for at least 2 years. Keep hazardous waste such as asbestos separate, with consignment notes (special waste in Scotland). Control (procedures)
  • Wear gloves when handling waste. PPE
  • Plan walkways and keep them clear of materials, hoses and leads. Eliminate
  • Run leads and hoses overhead on hooks or stands, or along walls, not across walkways. Control (engineering)
  • Fill or cover holes, and lay boards or mats on muddy access paths. Control (engineering)
  • Clean up offcuts, packaging and spills as you go, not at the end of the day. Control (procedures)
  • Keep work areas, stairs and access paths well lit. Control (procedures)
  • Wear safety boots with good grip, laced up. PPE
Low (4)

Method statement: sequence of work

  1. Check services are installed and isolated where you will fix
  2. Stack sheets flat on a level floor, not leaning against walls, and spread the load
  3. Carry sheets with two people or a sheet trolley
  4. Set up a platform ladder or mobile scaffold for ceilings and high walls
  5. Cut sheets with a sharp knife, cutting away from your body; use extraction if sawing
  6. Lift ceiling sheets with a sheet lifter, not your head
  7. Screw sheets off, keeping clear of cables and pipes behind
  8. Use adhesives with ventilation
  9. Pick up offcuts and screws

PPE

Safety bootsSafety glassesRigger glovesFFP3 dust maskSafety helmetHi-vis vestCut-resistant glovesKnee padsEar defendersChemical-resistant glovesSafety gogglesHalf-mask respirator (P3 filters)Coveralls

Plant and equipment

Power drillPodium stepHand toolsMobile access tower: PASMA certificate

Permits and plans

Work at height permit

Emergency

Call 999. Add the nearest A&E, the assembly point and the first aider for your site.

Sign-off

Supervisor and every worker sign to confirm they have read and understood this RAMS.

Free RAMS template for dry lining

Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.

Make yours in 2 minutes

Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.

Start this RAMS

Pre-start checklist for dry lining

Tick these off before work starts. They come from the hazards, permits and equipment in this job.

The safe sequence of work

  1. Check services are installed and isolated where you will fix
  2. Stack sheets flat on a level floor, not leaning against walls, and spread the load
  3. Carry sheets with two people or a sheet trolley
  4. Set up a platform ladder or mobile scaffold for ceilings and high walls
  5. Cut sheets with a sharp knife, cutting away from your body; use extraction if sawing
  6. Lift ceiling sheets with a sheet lifter, not your head
  7. Screw sheets off, keeping clear of cables and pipes behind
  8. Use adhesives with ventilation
  9. Pick up offcuts and screws

Hazards to watch on dry lining

The hazards most specific to this job, and the step where each one comes up.

Step 4Scaffold collapse or fall from scaffoldA scaffold that is badly built, overloaded or altered collapses or tips, or a worker falls from an unguarded platform.
Step 5General dustDust from plasterboard, filler, cement and clean up irritates eyes and lungs and makes it hard to see.
Step 7Injury from power toolsDrills, saws, routers and sanders kick back, catch clothing or throw debris, causing cuts, broken bones and eye injuries.
Step 6Repetitive work and awkward posturesDoing the same movement for hours, kneeling or working overhead causes long-term damage to joints, muscles and tendons.
Step 8Hazardous chemicalsGlues, sealants, solvents, acids, cleaners and cement burn skin and eyes or cause breathing problems and poisoning.
Step 4Falling from a ladderThe ladder slips or tips, or the worker overreaches, and they fall onto a hard surface.
Very likelyLikelyPossibleUnlikelyVery unlikelyHow bad it could be: Negligible to FatalBA
Highest risk on dry lining: Very high before controls (B), down to Medium after controls (A), on the United Kingdom 5 by 5 risk matrix (likely and fatal becomes unlikely and major injury).

What changes on your site

This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):

  • Will anyone work on a roof?
  • Is there a fragile roof, skylight or clear roof sheet?
  • Will you use a MEWP (scissor lift or cherry picker)?
  • Was the building built before 2000?
  • Will you sand, scrape, burn off or cut old paint in a building from before 1992?

Licences and legal requirements in United Kingdom

Equipment on this job that needs a licence, ticket or training:

  • Mobile access tower: PASMA certificate

Employers must assess the risks of their work and record the significant findings (required where you employ 5 or more people). On CDM projects, contractors give their RAMS to the principal contractor before starting, and brief the workers on it.

Rules that apply: Electricity at Work Regulations 1989; Manual Handling Operations Regulations 1992; Work at Height Regulations 2005, regulation 10 (falling objects); Work at Height Regulations 2005; Provision and Use of Work Equipment Regulations 1998 (PUWER); COSHH Regulations 2002.

Why RAMS get rejected

Principal contractors send documents back for these reasons. This example avoids them, but check yours too.

  • The method statement is only a list of headings that repeats the risk table and never says how the work is done.
  • The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
  • Residual risk is still High after controls with no extra measures or explanation.
  • It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
  • Work on an older building with no reference to an asbestos survey.
  • Plant and access equipment listed with no inspection, thorough examination or competence evidence.
  • No briefing record, no revision history, or no named supervisor.

Questions

Do I need RAMS for dry lining?

You must assess the risks of dry lining and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.

Who signs the RAMS?

The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.

How long do I keep it?

Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.

What PPE is needed for dry lining?

Usually Safety boots, Safety glasses, Rigger gloves, FFP3 dust mask, Safety helmet, Hi-vis vest, Cut-resistant gloves, Knee pads, Ear defenders, Chemical-resistant gloves, Safety goggles, Half-mask respirator (P3 filters), Coveralls. The site rules may add more, so check with the principal contractor.