Method statement for bathroom first fix plumbing

You must assess the risks of bathroom first fix plumbing and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.

RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are silica dust from concrete, brick, stone and tiles, electric shock from live wiring, disturbing asbestos and saw cuts and kickback.

RAMS example: bathroom first fix plumbing

This is a complete RAMS for bathroom first fix plumbing, with 6 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.

Risk Assessment and Method Statement (RAMS)
Bathroom rough-in plumbing · Plumbing · Example
Document RAMS-001 · Rev 1

Risk assessment

#ActivityHazardsWho might be harmedRisk beforeControlsRisk after
1Isolate water to the area and confirm power is off to any circuits in the walls
  • Electric shock from live wiring
  • Stored energy
Workers, OccupantsVery high (15)
  • Isolate the power before any work. Do not work live. Eliminate
  • Lock out and tag the isolation point with your own personal lock and danger tag. Isolate
  • Prove dead at the point of work with an approved voltage indicator (GS38), and prove the tester before and after. Control (engineering)
  • Only competent, qualified electricians do electrical work, following a safe isolation procedure. Control (procedures)
  • Check for back feeds from solar, batteries and generators that can keep a circuit live after the main switch is off. Control (procedures)
  • If live work cannot be avoided, use a permit, a safety observer and insulated tools. Control (procedures)
  • Wear insulated gloves, arc-rated clothing and a face shield when testing or working near live parts. PPE
  • Release or block all stored energy before work: release the pressure in pipes, tanks and hoses, bleed hydraulics, release springs, lower loads. Eliminate
  • Lock out and tag all energy sources with personal locks. Isolate
  • Put mechanical blocks or props under raised parts like buckets, tipper bodies and doors. Control (engineering)
  • Test that the system is dead and nothing can move before you start. Control (procedures)
  • Follow the maker's procedure, for example for garage door and roller door springs. Control (procedures)
  • Wear safety glasses and gloves. PPE
Medium (5)
2Check walls and floors for asbestos before cutting
  • Disturbing asbestos
Workers, Occupants, PublicVery high (15)
  • Before work on any building built before 2000, check the refurbishment and demolition asbestos survey for the work area (HSE HSG264). If there is none, presume asbestos is present or have it sampled before you start. Eliminate
  • Seal off the work area and keep everyone else out. Isolate
  • If asbestos must be disturbed, keep it wet, use hand tools not power tools, and clean up with an H-class vacuum. Control (engineering)
  • Most asbestos insulation, coatings and insulating board need a licensed contractor. Notifiable non-licensed work is notified to HSE before it starts. Other work needs trained workers and controls. Control (procedures)
  • Stop work straight away if you find suspect asbestos. Do not touch it and tell your supervisor. Control (procedures)
  • Wear a fit-tested FFP3 mask (or better) and disposable type 5 coveralls. PPE
Medium (5)
3Cut slab or wall chases with water suppression or dust extraction
  • Silica dust from concrete, brick, stone and tiles
  • Saw cuts and kickback
  • Loud noise
  • Hand-arm and whole-body vibration
Workers, People nearbyVery high (20)
  • Order materials cut to size, or use low-dust methods such as score and snap or a block splitter. Reduce / substitute
  • Cut outdoors or in a separate area, with other people well away and upwind. Isolate
  • Use water on the blade or on-tool dust extraction connected to an H-class vacuum. Control (engineering)
  • Clean up with a vacuum or wet methods. Never dry sweep or use compressed air. Control (procedures)
  • Do a COSHH assessment and keep exposure below the workplace exposure limit (0.1 mg/m3 respirable crystalline silica, 8 hours). Control (procedures)
  • Workers regularly exposed to silica dust get health surveillance (COSHH reg 11, HSE G404). Control (procedures)
  • Wear a fit-tested FFP3 mask. PPE
  • Keep blade guards fitted and working, and use the riving knife on table saws. Control (engineering)
  • Use push sticks and clamps, and support long pieces so they do not pinch the blade. Control (engineering)
  • Use a sharp, undamaged blade made for the material. Control (procedures)
  • Stand to one side of the blade line, out of the kickback path. Control (procedures)
  • Use quieter tools and methods, such as cut-to-size materials, low-noise machines and battery tools. Reduce / substitute
  • Keep noisy plant away from work areas, and use screens or distance between the noise and people. Isolate
  • Keep tools maintained and use mufflers on compressors and generators. Control (engineering)
  • Limit time on noisy tools and rotate workers. Control (procedures)
  • Assess noise. At 85 dB(A) or more, hearing protection is required and the zone must be marked. Control (procedures)
  • Use low-vibration tools and methods, such as a breaker on an excavator instead of a hand jackhammer. Reduce / substitute
  • Keep tools sharp and well maintained, and use anti-vibration handles and seats. Control (engineering)
  • Limit trigger time using the HSE vibration calculator to stay below the exposure action value, and rotate workers. Control (procedures)
  • Keep hands warm and dry, and take regular breaks. Control (procedures)
Medium (8)
4Run waste and water pipes, working at floor level with knee pads
  • Lifting and carrying heavy loads
  • Repetitive work and awkward postures
  • Cuts from sharp edges
WorkersHigh (12)
  • Plan to avoid carrying: have materials delivered, and old items picked up, as close as possible to where they are used. Eliminate
  • Use lighter or smaller loads: order smaller bags and shorter lengths, and drain or break down old items before moving them. Reduce / substitute
  • Use trolleys, pallet jacks, hoists, vacuum lifters or plant instead of carrying by hand. Control (engineering)
  • Use a two-person lift for anything heavy, long or awkward. Plan the route first and clear it. Control (procedures)
  • Keep the load close, back straight and no twisting. Turn with your feet. Control (procedures)
  • Use tools that cut the effort: powered screwdrivers, long-handled tools and extension poles for overhead work. Reduce / substitute
  • Set work up at waist height on benches or trestles where you can. Control (engineering)
  • Use light tools with good grips, and keep blades and bits sharp. Control (engineering)
  • Rotate tasks and take short breaks every hour on repetitive work. Control (procedures)
  • Warm up before heavy physical work and report aches and pains early. Control (procedures)
  • Deburr or cover sharp edges, and fit edge protectors on exposed sheet metal. Control (engineering)
  • Use knives with retractable or self-retracting blades. Control (engineering)
  • Cut away from your body and keep your other hand clear. Control (procedures)
  • Put used blades in a blade bin or sharps container. Control (procedures)
  • Use two people to handle large sheets of metal or glass. Control (procedures)
Medium (6)
5Glue solvent joints with ventilation and no flames nearby
  • Hazardous chemicals
  • Flammable liquids and gases
Workers, Occupants, PublicHigh (10)
  • Choose the least harmful product that does the job, for example water-based instead of solvent-based. Reduce / substitute
  • Use chemicals in well-ventilated areas, or use fans and extraction in closed rooms. Control (engineering)
  • Do a COSHH assessment and read the Safety Data Sheet (SDS) before use. Control (procedures)
  • Keep chemicals in labelled containers. Never decant into drink bottles. Control (procedures)
  • Store chemicals away from heat, food and drink, and keep products that react with each other apart. Control (procedures)
  • Have eye wash and a spill kit nearby, and wash hands before eating. Control (procedures)
  • Wear chemical-resistant gloves and safety glasses or goggles as listed on the SDS. PPE
  • Use a respirator with the right cartridge if the SDS calls for one. PPE
  • Use non-flammable or water-based products where you can. Reduce / substitute
  • Keep ignition sources away: no smoking, no hot work and no running engines near flammables. Isolate
  • Store fuels and solvents in approved, closed containers in a ventilated area away from the work. Control (engineering)
  • Refuel equipment outdoors with the engine off and cool. Control (procedures)
  • Keep only what you need for the day on site. Control (procedures)
  • Store gas cylinders upright, secured and outdoors. Control (procedures)
  • Keep a suitable fire extinguisher where flammables are used or stored. Control (procedures)
  • Wear chemical gloves and safety glasses when pouring or mixing. PPE
Medium (6)
6Pressure test the pipework and clean up
  • Pressure testing
  • Poor housekeeping and waste
Workers, Occupants, VisitorsMedium (8)
  • Test with water instead of air or gas where the system allows it. Never put water in refrigerant pipework, which is tested with dry nitrogen. Reduce / substitute
  • Keep people out of the test area with signs and barriers. Isolate
  • Use a calibrated gauge and a relief valve set to protect the system. Control (engineering)
  • Test to the pressure the system calls for and hold it for the set time. Never go over. Control (procedures)
  • Release the pressure fully before tightening anything or fixing leaks. Control (procedures)
  • Wear safety glasses or a face shield. PPE
  • Order materials to size and send packaging back where you can. Eliminate
  • Put skips and waste chutes close to the work. Control (engineering)
  • Clean as you go, and do a full clean up at the end of each day. Control (procedures)
  • Keep exits, stairs and walkways clear at all times. Control (procedures)
  • Stack materials neatly on level ground, away from edges. Control (procedures)
  • Use a registered waste carrier and keep waste transfer notes for at least 2 years. Keep hazardous waste such as asbestos separate, with consignment notes (special waste in Scotland). Control (procedures)
  • Wear gloves when handling waste. PPE
Low (4)

Method statement: sequence of work

  1. Isolate water to the area and confirm power is off to any circuits in the walls
  2. Check walls and floors for asbestos before cutting
  3. Cut slab or wall chases with water suppression or dust extraction
  4. Run waste and water pipes, working at floor level with knee pads
  5. Glue solvent joints with ventilation and no flames nearby
  6. Pressure test the pipework and clean up

PPE

Safety bootsSafety glassesFFP3 dust maskEar defendersKnee padsRigger glovesHalf-mask respirator (P3 filters)CoverallsCut-resistant glovesChemical-resistant glovesSafety gogglesFace shield

Plant and equipment

Power drillSDS drillPress fitting toolHand toolsCut-off saw (Stihl saw)

Permits and plans

Permit to work (electrical isolation)

Emergency

Call 999. Add the nearest A&E, the assembly point and the first aider for your site.

Sign-off

Supervisor and every worker sign to confirm they have read and understood this RAMS.

Free RAMS template for bathroom first fix plumbing

Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.

Make yours in 2 minutes

Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.

Start this RAMS

Pre-start checklist for bathroom first fix plumbing

Tick these off before work starts. They come from the hazards, permits and equipment in this job.

The safe sequence of work

  1. Isolate water to the area and confirm power is off to any circuits in the walls
  2. Check walls and floors for asbestos before cutting
  3. Cut slab or wall chases with water suppression or dust extraction
  4. Run waste and water pipes, working at floor level with knee pads
  5. Glue solvent joints with ventilation and no flames nearby
  6. Pressure test the pipework and clean up

Hazards to watch on bathroom first fix plumbing

The hazards most specific to this job, and the step where each one comes up.

Step 5Flammable liquids and gasesPetrol, solvents, thinners and LPG catch fire or explode when vapour reaches a spark, flame or hot surface.
Step 6Pressure testingA pipe, fitting or cap fails under test pressure and blows apart, hitting people nearby.
Step 1Stored energyEnergy left in springs, hydraulics, compressed gas, raised loads or capacitors releases suddenly and crushes or injures workers.
Step 3Hand-arm and whole-body vibrationLong periods on jackhammers, grinders, compactors or riding plant cause white finger, numbness and back damage.
Step 2Disturbing asbestosBuildings built before 2000 may contain asbestos. Drilling, cutting or breaking it releases fibres that cause cancer years later.
Step 3Saw cuts and kickbackCircular saws, drop saws and table saws cut fingers and hands or throw material back at the user.
Very likelyLikelyPossibleUnlikelyVery unlikelyHow bad it could be: Negligible to FatalBA
Highest risk on bathroom first fix plumbing: Very high before controls (B), down to Medium after controls (A), on the United Kingdom 5 by 5 risk matrix (likely and fatal becomes unlikely and major injury).

What changes on your site

This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):

  • Will anyone work at height, anywhere a fall could hurt them?
  • Will anyone use a ladder or stepladder?
  • Will anyone work on a roof?
  • Is there a fragile roof, skylight or clear roof sheet?
  • Will you use a scaffold or mobile tower?

Why RAMS get rejected

Principal contractors send documents back for these reasons. This example avoids them, but check yours too.

  • The method statement is only a list of headings that repeats the risk table and never says how the work is done.
  • The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
  • Residual risk is still High after controls with no extra measures or explanation.
  • It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
  • Work on an older building with no reference to an asbestos survey.
  • Plant and access equipment listed with no inspection, thorough examination or competence evidence.
  • No briefing record, no revision history, or no named supervisor.

Questions

Do I need RAMS for bathroom first fix plumbing?

You must assess the risks of bathroom first fix plumbing and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.

Who signs the RAMS?

The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.

How long do I keep it?

Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.

What PPE is needed for bathroom first fix plumbing?

Usually Safety boots, Safety glasses, FFP3 dust mask, Ear defenders, Knee pads, Rigger gloves, Half-mask respirator (P3 filters), Coveralls, Cut-resistant gloves, Chemical-resistant gloves, Safety goggles, Face shield. The site rules may add more, so check with the principal contractor.