Method statement for toilet and tap installation

You must assess the risks of toilet and tap installation and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.

RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are lifting and carrying heavy loads, glass handling and breakage, sewage and wastewater and injury from power tools.

RAMS example: toilet and tap installation

This is a complete RAMS for toilet and tap installation, with 5 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.

Risk Assessment and Method Statement (RAMS)
Install a toilet, taps or basin · Plumbing · Example
Document RAMS-001 · Rev 1

Risk assessment

#ActivityHazardsWho might be harmedRisk beforeControlsRisk after
1Isolate water to the fixture and drain the lines
  • Stored energy
  • Slips and trips
Workers, Visitors, PublicMedium (8)
  • Release or block all stored energy before work: release the pressure in pipes, tanks and hoses, bleed hydraulics, release springs, lower loads. Eliminate
  • Lock out and tag all energy sources with personal locks. Isolate
  • Put mechanical blocks or props under raised parts like buckets, tipper bodies and doors. Control (engineering)
  • Test that the system is dead and nothing can move before you start. Control (procedures)
  • Follow the maker's procedure, for example for garage door and roller door springs. Control (procedures)
  • Wear safety glasses and gloves. PPE
  • Plan walkways and keep them clear of materials, hoses and leads. Eliminate
  • Run leads and hoses overhead on hooks or stands, or along walls, not across walkways. Control (engineering)
  • Slips and trips: see step 5 for the full controls Control (procedures)
Low (4)
2Remove the old fixture, wearing gloves for waste contamination
  • Sewage and wastewater
  • Lifting and carrying heavy loads
  • Cuts from sharp edges
WorkersHigh (12)
  • Flush and drain the line before opening it, and plan the job to avoid contact. Eliminate
  • Use drain cameras, jetters and long-handled tools to keep hands out. Control (engineering)
  • Cover cuts with waterproof dressings. Never eat, drink or smoke before washing. Control (procedures)
  • Wash hands well and clean tools and boots after the job. Control (procedures)
  • Keep vaccinations such as tetanus and hepatitis A up to date, on medical advice. Control (procedures)
  • Plan to avoid carrying: have materials delivered, and old items picked up, as close as possible to where they are used. Eliminate
  • Use lighter or smaller loads: order smaller bags and shorter lengths, and drain or break down old items before moving them. Reduce / substitute
  • Use trolleys, pallet jacks, hoists, vacuum lifters or plant instead of carrying by hand. Control (engineering)
  • Use a two-person lift for anything heavy, long or awkward. Plan the route first and clear it. Control (procedures)
  • Keep the load close, back straight and no twisting. Turn with your feet. Control (procedures)
  • Deburr or cover sharp edges, and fit edge protectors on exposed sheet metal. Control (engineering)
  • Use knives with retractable or self-retracting blades. Control (engineering)
  • Cut away from your body and keep your other hand clear. Control (procedures)
  • Put used blades in a blade bin or sharps container. Control (procedures)
  • Use two people to handle large sheets of metal or glass. Control (procedures)
Medium (6)
3Drill fixings into tiles with the right bit and glasses on
  • Injury from power tools
  • Eye injuries
  • Glass handling and breakage
Workers, People nearby, OccupantsHigh (12)
  • Keep all guards fitted and working. Never tie back or remove a guard. Control (engineering)
  • Clamp or secure the work piece. Do not hold it by hand. Control (engineering)
  • Only trained, competent people use power tools, following the maker's instructions. Control (procedures)
  • Check tools before use. Unplug or remove the battery before changing blades or bits. Control (procedures)
  • No loose clothing, jewellery or long hair near spinning parts. Control (procedures)
  • Use tool guards and screens to stop flying particles. Control (engineering)
  • Use dust extraction and water to keep dust out of the air. Control (engineering)
  • Keep others out of the area when cutting, grinding or chipping. Control (procedures)
  • Keep an eye wash station or eye wash bottles on site. Control (procedures)
  • Wear safety glasses at all times, goggles for dust and chemicals, and a face shield for grinding. PPE
  • Use suction lifters, glass trolleys or a glazing robot for large panes. Control (engineering)
  • Store glass upright on racks and secure it. Never lay it flat or lean it loosely. Control (engineering)
  • Use two or more people for large panes, and clear the carry route first. Control (procedures)
  • Mark new glass with tape or stickers so nobody walks into it. Control (procedures)
  • Clean up broken glass straight away into a marked container. Control (procedures)
Medium (8)
4Fit and connect the new fixture, kneeling on pads
  • Lifting and carrying heavy loads
  • Repetitive work and awkward postures
WorkersHigh (12)
  • Rotate tasks and take breaks on long lifting jobs. Control (procedures)
  • Wear gloves for grip and safety boots to protect your feet. PPE
  • Lifting and carrying heavy loads: see step 2 for the full controls Control (procedures)
  • Use tools that cut the effort: powered screwdrivers, long-handled tools and extension poles for overhead work. Reduce / substitute
  • Set work up at waist height on benches or trestles where you can. Control (engineering)
  • Use light tools with good grips, and keep blades and bits sharp. Control (engineering)
  • Rotate tasks and take short breaks every hour on repetitive work. Control (procedures)
  • Warm up before heavy physical work and report aches and pains early. Control (procedures)
  • Wear knee pads for kneeling work and gloves for grip. PPE
Medium (6)
5Turn water on, check for leaks and clean up
  • Slips and trips
  • Poor housekeeping and waste
Workers, Visitors, PublicMedium (8)
  • Plan walkways and keep them clear of materials, hoses and leads. Eliminate
  • Run leads and hoses overhead on hooks or stands, or along walls, not across walkways. Control (engineering)
  • Fill or cover holes, and lay boards or mats on muddy access paths. Control (engineering)
  • Clean up offcuts, packaging and spills as you go, not at the end of the day. Control (procedures)
  • Keep work areas, stairs and access paths well lit. Control (procedures)
  • Wear safety boots with good grip, laced up. PPE
  • Order materials to size and send packaging back where you can. Eliminate
  • Put skips and waste chutes close to the work. Control (engineering)
  • Clean as you go, and do a full clean up at the end of each day. Control (procedures)
  • Keep exits, stairs and walkways clear at all times. Control (procedures)
  • Stack materials neatly on level ground, away from edges. Control (procedures)
  • Use a registered waste carrier and keep waste transfer notes for at least 2 years. Keep hazardous waste such as asbestos separate, with consignment notes (special waste in Scotland). Control (procedures)
  • Wear gloves when handling waste. PPE
Low (4)

Method statement: sequence of work

  1. Isolate water to the fixture and drain the lines
  2. Remove the old fixture, wearing gloves for waste contamination
  3. Drill fixings into tiles with the right bit and glasses on
  4. Fit and connect the new fixture, kneeling on pads
  5. Turn water on, check for leaks and clean up

PPE

Safety bootsRigger glovesSafety glassesKnee padsChemical-resistant glovesSafety gogglesFace shieldCoverallsCut-resistant glovesEar defenders

Plant and equipment

Hand toolsPower drill

Permits and plans

Permit to work (electrical isolation)

Emergency

Call 999. Add the nearest A&E, the assembly point and the first aider for your site.

Sign-off

Supervisor and every worker sign to confirm they have read and understood this RAMS.

Free RAMS template for toilet and tap installation

Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.

Make yours in 2 minutes

Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.

Start this RAMS

Pre-start checklist for toilet and tap installation

Tick these off before work starts. They come from the hazards, permits and equipment in this job.

The safe sequence of work

  1. Isolate water to the fixture and drain the lines
  2. Remove the old fixture, wearing gloves for waste contamination
  3. Drill fixings into tiles with the right bit and glasses on
  4. Fit and connect the new fixture, kneeling on pads
  5. Turn water on, check for leaks and clean up

Hazards to watch on toilet and tap installation

The hazards most specific to this job, and the step where each one comes up.

Step 2Sewage and wastewaterContact with sewage spreads germs that cause stomach illness, hepatitis and skin infections.
Step 3Glass handling and breakageGlass panes break while being moved or fitted, causing deep cuts, or heavy panels fall and crush.
Step 1Stored energyEnergy left in springs, hydraulics, compressed gas, raised loads or capacitors releases suddenly and crushes or injures workers.
Step 3Eye injuriesFlying chips, dust, chemicals or sparks get into the eye and cause damage or blindness.
Step 3Injury from power toolsDrills, saws, routers and sanders kick back, catch clothing or throw debris, causing cuts, broken bones and eye injuries.
Step 4Repetitive work and awkward posturesDoing the same movement for hours, kneeling or working overhead causes long-term damage to joints, muscles and tendons.
Very likelyLikelyPossibleUnlikelyVery unlikelyHow bad it could be: Negligible to FatalBA
Highest risk on toilet and tap installation: High before controls (B), down to Medium after controls (A), on the United Kingdom 5 by 5 risk matrix (likely and lost time injury becomes unlikely and major injury).

What changes on your site

This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):

  • Will anyone work at height, anywhere a fall could hurt them?
  • Will anyone use a ladder or stepladder?
  • Will anyone work on a roof?
  • Is there a fragile roof, skylight or clear roof sheet?
  • Will you use a scaffold or mobile tower?

Why RAMS get rejected

Principal contractors send documents back for these reasons. This example avoids them, but check yours too.

  • The method statement is only a list of headings that repeats the risk table and never says how the work is done.
  • The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
  • Residual risk is still High after controls with no extra measures or explanation.
  • It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
  • Work on an older building with no reference to an asbestos survey.
  • Plant and access equipment listed with no inspection, thorough examination or competence evidence.
  • No briefing record, no revision history, or no named supervisor.

Questions

Do I need RAMS for toilet and tap installation?

You must assess the risks of toilet and tap installation and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.

Who signs the RAMS?

The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.

How long do I keep it?

Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.

What PPE is needed for toilet and tap installation?

Usually Safety boots, Rigger gloves, Safety glasses, Knee pads, Chemical-resistant gloves, Safety goggles, Face shield, Coveralls, Cut-resistant gloves, Ear defenders. The site rules may add more, so check with the principal contractor.