SiteSorted
Glazing · United States

JHA for storefront glazing

OSHA expects employers to find and control hazards on every job, and many general contractors require a written JHA for storefront glazing before you start.

A JHA breaks the job into steps, lists the hazards in each step and the controls that protect the crew, and the crew signs it. The main hazards are falling from height, road traffic, aerial lift tip-over or crush and public entering the work area.

JHA example: storefront glazing

This is a complete JHA for storefront glazing, with 5 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.

Job Hazard Analysis (JHA)
Shopfront and commercial glazing · Glazing · Example
Document JHA-001 · Rev 1

Job steps, hazards and controls

#Job stepHazardsRisk beforeControlsRisk after
1Set up pedestrian control on the sidewalk
  • Public entering the work area
  • Road traffic
Critical
  • Fence off the site with secure temporary fencing and lock the gates when you leave. Engineering (guarding)
  • Give pedestrians a safe, marked path around the work, with ramps for strollers and wheelchairs. Engineering (guarding)
  • Use hoarding, covered walkways or catch fans where work is above public areas. Engineering
  • Put signs at each entry: site name, contact number and "No unauthorized entry". Administrative
  • Make the site safe at the end of each day: cover holes, lower plant, remove ladders and lock tools away. Administrative
  • Use a spotter when moving plant or materials across public paths. Administrative
  • Do the work at low-traffic times, or close the road or lane with approval. Elimination
  • Put solid barriers between the work and traffic where speeds are high, not just cones. Engineering (guarding)
  • Use a truck-mounted attenuator or buffer vehicle on high speed roads. Engineering
  • Set up work zone signs and cones to MUTCD Part 6, with trained flaggers. Administrative
  • Get any permit needed from the city, county or state DOT before you start. Administrative
  • Park work vehicles to shield the work zone, with beacons on. Administrative
  • Wear ANSI/ISEA 107 Class 2 or 3 high-visibility clothing. PPE
Medium
2Plan large lifts with vacuum lifters or crane
  • Crane and lifting failure
  • Glass handling and breakage
High
  • Barricade the lift zone and keep everyone out from under the load. Engineering (guarding)
  • Use a crane rated for the load at the radius, set up on firm ground with outrigger pads. Engineering
  • Check slings, chains, shackles and hooks before use. Remove anything damaged or not tagged. Engineering
  • Plan the lift: weight, radius, ground, path and landing area. Use a written lift plan for complex lifts. Administrative
  • Use a certified crane operator who has also been evaluated by the employer, with the evaluation documented on site (29 CFR 1926.1427), plus a qualified rigger (1926.1425) and a qualified signal person (1926.1428). Administrative
  • Use tag lines to control loads and agree on clear radio or hand signals. Administrative
  • Stop lifting in high wind or when the operator cannot see the signal person. Administrative
  • Never ride on a load or hook. Administrative
  • Wear a hard hat, hi-vis, gloves and safety boots. PPE
  • Use suction lifters, glass trolleys or a glazing robot for large panes. Engineering
  • Store glass upright on racks and secure it. Never lay it flat or lean it loosely. Engineering
  • Use two or more people for large panes, and clear the carry route first. Administrative
  • Mark new glass with tape or stickers so nobody walks into it. Administrative
  • Clean up broken glass straight away into a marked container. Administrative
  • Wear cut-resistant gloves, arm guards, safety glasses and safety boots. PPE
Medium
3Work from a aerial lift for high panes
  • Aerial lift tip-over or crush
  • Falling from height
Critical
  • Check the ground before setting up. Use outriggers and spreader pads, and keep clear of trenches, pits and slopes. Engineering
  • Use a platform with tilt alarm and secondary guarding (anti-entrapment) where there is an overhead crush risk. Engineering
  • Only trained and authorized operators use aerial lifts and scissor lifts (29 CFR 1926.453 for boom lifts, 1926.452(w) and 1926.454 for scissor lifts). Administrative
  • Do a pre-start check each day. Keep a trained person on the ground who can lower the platform in an emergency. Administrative
  • Never exceed the safe working load, climb on the rails or use a ladder in the basket. Administrative
  • In boom-type platforms, wear a harness clipped to the basket anchor point. PPE
  • Do the work from the ground where you can, for example pre-assemble on the ground or use extension poles. Elimination
  • Install guardrails or edge protection on all open edges before work starts. Engineering (guarding)
  • Use a scaffold, mobile work platform or aerial lift instead of working off a ladder. Engineering
  • Where edge protection is not practical, use a fall restraint or fall arrest system on a rated anchor point. Engineering
  • Provide fall protection at 6 feet or more and train workers to recognize fall hazards (29 CFR 1926.503). Administrative
  • Have a rescue plan so a worker hanging in a harness can be brought down within minutes. Administrative
  • Wear a full body harness with a shock-absorbing lanyard, clipped on at all times when using fall arrest. PPE
Medium
4Install frames and glass, keeping everyone out from under the load
  • Falling tools and materials
  • Lifting and carrying heavy loads
High
  • Barricade and sign the drop zone under overhead work so nobody walks beneath. Engineering (guarding)
  • Fit toe boards, kick plates and mesh screens on scaffolds and edges. Engineering
  • Use catch fans, debris netting or covered walkways where people pass below. Engineering
  • Tether hand tools when working at height. Engineering
  • Keep platforms tidy. Do not stack materials near edges or above toe board height. Administrative
  • Lower materials with a hoist, chute or rope. Never throw or drop anything down. Administrative
  • Wear a hard hat anywhere objects could fall. PPE
  • Plan to avoid carrying: have materials delivered, and old items picked up, as close as possible to where they are used. Elimination
  • Use lighter or smaller loads: order smaller bags and shorter lengths, and drain or break down old items before moving them. Substitution
  • Use trolleys, pallet jacks, hoists, vacuum lifters or plant instead of carrying by hand. Engineering
  • Use a two-person lift for anything heavy, long or awkward. Plan the route first and clear it. Administrative
  • Keep the load close, back straight and no twisting. Turn with your feet. Administrative
  • Rotate tasks and take breaks on long lifting jobs. Administrative
  • Wear gloves for grip and safety boots to protect your feet. PPE
Medium
5Seal, clean up and reopen the sidewalk
  • Hazardous chemicals
  • Poor housekeeping and waste
Medium
  • Choose the least harmful product that does the job, for example water-based instead of solvent-based. Substitution
  • Use chemicals in well-ventilated areas, or use fans and extraction in closed rooms. Engineering
  • Read the Safety Data Sheet (SDS) and labels before use, following OSHA Hazard Communication. Administrative
  • Keep chemicals in labeled containers. Never pour them into drink bottles. Administrative
  • Store chemicals away from heat, food and drink, and keep products that react with each other apart. Administrative
  • Have eye wash and a spill kit nearby, and wash hands before eating. Administrative
  • Wear chemical-resistant gloves and safety glasses or goggles as listed on the SDS. PPE
  • Use a respirator with the right cartridge if the SDS calls for one. PPE
  • Order materials to size and send packaging back where you can. Elimination
  • Put dumpsters and waste chutes close to the work. Engineering
  • Clean as you go, and do a full clean up at the end of each day. Administrative
  • Keep exits, stairs and walkways clear at all times. Administrative
  • Stack materials neatly on level ground, away from edges. Administrative
  • Wear gloves when handling waste. PPE
Medium

PPE

Safety-toe boots (ASTM F2413)Hard hat (ANSI Z89.1)High-visibility safety apparel, ANSI/ISEA 107 Class 2 or 3 (Type R near roadways)Cut-resistant glovesSafety glasses (ANSI Z87.1)Personal fall arrest system (harness)Work glovesChemical-resistant glovesSafety goggles (ANSI Z87.1)Half-face respirator (P100 cartridges)Coveralls

Plant and equipment

Mobile crane: Operator certified by an accredited body or audited employer program (29 CFR 1926.1427) and evaluated by the employer, with a signed evaluation on site (1926.1427(f)); qualified rigger (1926.1425) and qualified signal person (1926.1428)Boom lift (aerial lift): Trained and authorized operator (29 CFR 1926.453, ANSI A92.24 training and familiarization)Telehandler: Trained and evaluated operator, certified by the employer with name, training date, evaluation date and evaluator; re-evaluated every 3 years (29 CFR 1910.178(l), via 1926.602(d)). If used to hoist a suspended load with a winch or jib, crane rules apply (29 CFR 1926 Subpart CC)Power drillHand tools

Permits and plans

Critical lift planWritten fall protection plan (only where guardrails, nets or personal fall arrest are not feasible, 1926.502(k))

Emergency

Call 911. Add the nearest hospital, the assembly point and the first aid / cpr person for your site.

Sign-off

Supervisor and every worker sign to confirm they have read and understood this JHA.

Free JHA template for storefront glazing

Word (.docx) and PDF, Letter landscape, no email needed. Fill in your site details, then print or send it.

Make yours in 2 minutes

Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.

Start this JHA

Pre-start checklist for storefront glazing

Tick these off before work starts. They come from the hazards, permits and equipment in this job.

The safe sequence of work

  1. Set up pedestrian control on the sidewalk
  2. Plan large lifts with vacuum lifters or crane
  3. Work from a aerial lift for high panes
  4. Install frames and glass, keeping everyone out from under the load
  5. Seal, clean up and reopen the sidewalk

Hazards to watch on storefront glazing

The hazards most specific to this job, and the step where each one comes up.

Step 3Aerial lift tip-over or crushThe platform tips on soft or sloping ground, the worker is crushed against a beam or ceiling, or is thrown out of the basket.
Step 1Road trafficPassing cars and trucks hit workers or plant working on or next to a road.
Step 2Crane and lifting failureA load falls or swings, or the crane tips, crushing workers under or near the lift.
Step 2Glass handling and breakageGlass panes break while being moved or fitted, causing deep cuts, or heavy panels fall and crush.
Step 5Hazardous chemicalsGlues, sealants, solvents, acids, cleaners and cement burn skin and eyes or cause breathing problems and poisoning.
Step 3Falling from heightA worker falls 6 feet or more from an edge, platform or opening to a lower level and is badly hurt or killed.
Almost certainLikelyPossibleUnlikelyRareHow bad it could be: First aid only to FatalityBA
Highest risk on storefront glazing: Critical before controls (B), down to Medium after controls (A), on the United States 5 by 5 risk matrix (likely and fatality becomes unlikely and serious injury).

What changes on your site

This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):

  • Will anyone use a ladder or stepladder?
  • Will anyone work on a roof?
  • Is there a skylight, fiberglass panel or other fragile roofing?
  • Will you use a scaffold or rolling tower?
  • Was the building built before 1981?

Licences and legal requirements in United States

Equipment on this job that needs a licence, ticket or training:

  • Mobile crane: Operator certified by an accredited body or audited employer program (29 CFR 1926.1427) and evaluated by the employer, with a signed evaluation on site (1926.1427(f)); qualified rigger (1926.1425) and qualified signal person (1926.1428)
  • Boom lift (aerial lift): Trained and authorized operator (29 CFR 1926.453, ANSI A92.24 training and familiarization)
  • Telehandler: Trained and evaluated operator, certified by the employer with name, training date, evaluation date and evaluator; re-evaluated every 3 years (29 CFR 1910.178(l), via 1926.602(d)). If used to hoist a suspended load with a winch or jib, crane rules apply (29 CFR 1926 Subpart CC)

OSHA requires employers to find and fix hazards and to train workers on them. A JHA breaks the job into steps, lists the hazards in each step and the controls that protect the crew. General contractors often require one before you start.

Rules that apply: MUTCD Part 6 and 29 CFR 1926 Subpart G; 29 CFR 1926 Subpart CC; 29 CFR 1926.453 (boom lifts); 1926.452(w) and 1926.454 (scissor lifts); 29 CFR 1926 Subpart M; 29 CFR 1926.501(c); 29 CFR 1926.59 Hazard Communication.

Why JHAs get rejected

General contractors send documents back for these reasons. This example avoids them, but check yours too.

  • Generic steps such as "work safely" or "use PPE" with no task-specific hazards or controls.
  • No OSHA standards referenced for the hazards that have them, such as fall protection, ladders, scaffolds or silica.
  • No competent person named for fall protection, excavation, scaffolds or silica where those hazards exist.
  • Equipment listed without inspection requirements, and no training listed for the people using it.
  • Respirators listed with no respiratory protection program, medical clearance or fit test.
  • Controls rely only on PPE when engineering controls such as guardrails, wet cutting or extraction are feasible.
  • No crew sign-off, or no date and revision when the job has changed.

Questions

Do I need a JHA for storefront glazing?

OSHA expects employers to find and control hazards on every job, and many general contractors require a written JHA for storefront glazing before you start.

Who signs the JHA?

The supervisor or competent person who prepared it signs, and every crew member signs to show they were trained on the hazards and controls before the job starts. Many general contractors also sign to accept it.

How long do I keep it?

Keep this JHA on site during the job, and keep it with the training and inspection records for at least 1 year after the job (longer if your state plan or general contractor requires it). OSHA does not set a retention period for JHAs themselves.

What PPE is needed for storefront glazing?

Usually Safety-toe boots (ASTM F2413), Hard hat (ANSI Z89.1), High-visibility safety apparel, ANSI/ISEA 107 Class 2 or 3 (Type R near roadways), Cut-resistant gloves, Safety glasses (ANSI Z87.1), Personal fall arrest system (harness), Work gloves, Chemical-resistant gloves, Safety goggles (ANSI Z87.1), Half-face respirator (P100 cartridges), Coveralls. The site rules may add more, so check with the general contractor.

More glazing JHAs

Related jobs in other trades

Toolbox talks for this job

Blank JHA template: free JHA templates. Also for other countries: Australia (SWMS) · United Kingdom (RAMS) · Canada (FLHA)

Sources