SafetyPaperwork
Painting · United States

JHA for pressure washing

OSHA expects employers to find and control hazards on every job, and many general contractors require a written JHA for pressure washing before you start.

A JHA breaks the job into steps, lists the hazards in each step and the controls that protect the crew, and the crew signs it. The main hazards are electric shock from live wiring, disturbing asbestos, electric shock from cords and power tools and lead paint dust and fumes.

JHA example: pressure washing

This is a complete JHA for pressure washing, with 6 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.

Job Hazard Analysis (JHA)
Pressure washing and surface prep · Painting · Example
Document JHA-001 · Rev 1

Job steps, hazards and controls

#Job stepHazardsRisk beforeControlsRisk after
1Cover power points and outside lights, and keep leads off wet ground
  • Electric shock from cords and power tools
  • Electric shock from live wiring
Critical
  • Use battery-powered tools where you can. Substitution
  • Use GFCIs on all 120-volt, 15, 20 and 30 amp temporary receptacles, or a written assured equipment grounding conductor program run by a competent person with recorded tests (29 CFR 1926.404(b)(1)). Engineering
  • Keep cords off the ground and out of water, using stands or hooks. Engineering
  • Check cords, plugs and tools before every use. Tag out and remove anything damaged. Administrative
  • Do not use tools in rain or wet areas unless they are rated for it. Administrative
  • Wear safety boots and dry gloves. PPE
  • Isolate the power before any work. Do not work live. Elimination
  • Lock out and tag the disconnecting means with your own personal lock and tag so the circuit cannot be energized (29 CFR 1926.417). Engineering (guarding)
  • Test before you touch: prove dead at the point of work with a tested voltage tester. Engineering
  • Only qualified persons work on or near exposed energized parts. Administrative
  • Check for back feeds from solar, batteries and generators that can keep a circuit live after the main switch is off. Administrative
  • If energized work cannot be avoided, use an energized work permit, a safety observer and insulated tools, following NFPA 70E. Administrative
  • Wear insulated gloves, arc-rated clothing and a face shield when testing or working near live parts. PPE
Medium
2Check surfaces for asbestos and lead paint first
  • Disturbing asbestos
  • Lead paint dust and fumes
Critical
  • Treat insulation, surfacing and resilient flooring in buildings built before 1981 as asbestos unless testing shows otherwise, and get the owner's asbestos survey before you start. Elimination
  • Seal off the work area and keep everyone else out. Engineering (guarding)
  • If asbestos must be disturbed, keep it wet, use hand tools not power tools, and clean up with a HEPA vacuum. Engineering
  • Follow 29 CFR 1926.1101: competent person, work class, regulated area and exposure monitoring. Administrative
  • Commercial renovation and any demolition need a NESHAP asbestos inspection first, and demolition needs written notice to the state or EPA 10 working days before work starts (40 CFR 61 Subpart M). Administrative
  • Roofing felts, cement shingles and siding, roof coatings and old panel backboards can also contain asbestos. Test them or treat them as asbestos; asbestos roofing is removed intact with hand tools by trained workers (29 CFR 1926.1101(g)(8)). Administrative
  • Stop work straight away if you find suspect asbestos. Do not touch it and tell your supervisor. Administrative
  • Wear a fit-tested NIOSH-approved respirator suited to the work class, and disposable coveralls. PPE
  • Test old paint for lead before you sand, scrape, cut or heat it. Elimination
  • Use wet scraping, chemical strippers or shrouded tools with extraction instead of dry sanding. Never burn off lead paint with an open flame. Substitution
  • Seal off the work area with plastic sheeting and keep residents, children and pets out. Engineering (guarding)
  • Clean up with a HEPA vacuum and wet wipes. Never dry sweep. Engineering
  • In homes and child-occupied facilities built before 1978 (such as child care centers, preschools and kindergarten classrooms), work that disturbs more than 6 sq ft inside or 20 sq ft outside is done by an EPA Lead-Safe Certified firm with a certified renovator (RRP rule). Administrative
  • Do an initial lead exposure assessment and protect workers as if over the limit until results are in. Over 50 micrograms per cubic meter, follow a written lead compliance program (29 CFR 1926.62(d), (e)). Administrative
  • Never torch painted surfaces, keep heat guns below 1,100 degrees F, and use sanders, grinders or planers only with a shroud and HEPA vacuum attachment (40 CFR 745.85(a)(3)). Administrative
  • Provide a clean change area and handwashing, and keep food, drink and tobacco out of the work area (29 CFR 1926.62(i)). Administrative
  • Wash hands and face before eating, drinking or smoking. Change out of dusty clothes before going home. Administrative
  • Wear a NIOSH-approved respirator with N100 or P100 filters, disposable coveralls and gloves. PPE
Medium
3Never use the pressure washer from a ladder
  • Falling from a ladder
  • High pressure water jetting
High
  • Use a platform ladder, mobile scaffold or aerial lift for longer jobs instead of a straight ladder. Substitution
  • Use Type I, IA or IAA ladders in good condition. Tag and remove any damaged ladder. Engineering
  • Set extension ladders at a 4 to 1 angle on firm, level ground, secured, and reaching 3 feet above the landing. Engineering
  • Use ladders only for short, light work. Do not carry heavy or awkward loads up a ladder. Administrative
  • Keep three points of contact and your belt buckle between the stiles. Do not overreach. Administrative
  • Do not stand on the top three rungs of an extension ladder or the top step of a stepladder. Administrative
  • Check the ladder before each use: feet, rungs, side rails and locks. Administrative
  • Wear non-slip safety boots with clean soles. PPE
  • Set an exclusion zone around the jetting area. Engineering (guarding)
  • Use a dead man's trigger that stops the jet when released, and check hoses and fittings before use. Engineering
  • Only trained operators use high pressure jetting gear. Administrative
  • Never point the lance at anyone or put a hand in front of it. Administrative
  • Treat any jetting injury as serious and go to hospital, even if it looks small. Administrative
  • Wear a face shield, waterproof clothing, gloves, hearing protection and safety boots. PPE
Medium
4Mix and apply cleaning chemicals as the label says
  • Hazardous chemicals
Medium
  • Choose the least harmful product that does the job, for example water-based instead of solvent-based. Substitution
  • Use chemicals in well-ventilated areas, or use fans and extraction in closed rooms. Engineering
  • Read the Safety Data Sheet (SDS) and labels before use, following OSHA Hazard Communication. Administrative
  • Keep chemicals in labeled containers. Never pour them into drink bottles. Administrative
  • Store chemicals away from heat, food and drink, and keep products that react with each other apart. Administrative
  • Have eye wash and a spill kit nearby, and wash hands before eating. Administrative
  • Wear chemical-resistant gloves and safety glasses or goggles as listed on the SDS. PPE
  • Use a respirator with the right cartridge if the SDS calls for one. PPE
Medium
5Wash down, keeping the lance away from people
  • High pressure water jetting
  • Loud noise
  • Slips and trips
High
  • High pressure water jetting: see step 3 for the full controls Administrative
  • Use quieter tools and methods, such as cut-to-size materials, low-noise machines and battery tools. Substitution
  • Keep noisy plant away from work areas, and use screens or distance between the noise and people. Engineering (guarding)
  • Keep tools maintained and use mufflers on compressors and generators. Engineering
  • Limit time on noisy tools and rotate workers. Administrative
  • If you have to shout to be heard at arm's length, wear hearing protection. Administrative
  • Plan walkways and keep them clear of materials, hoses and leads. Elimination
  • Run cords and hoses overhead on hooks or stands, or along walls, not across walkways. Engineering
  • Fill or cover holes, and lay boards or mats on muddy access paths. Engineering
  • Clean up offcuts, packaging and spills as you go, not at the end of the day. Administrative
  • Keep work areas, stairs and access paths well lit. Administrative
Medium
6Stop runoff entering storm drain drains and clean up
  • Poor housekeeping and waste
Medium
  • Order materials to size and send packaging back where you can. Elimination
  • Put dumpsters and waste chutes close to the work. Engineering
  • Clean as you go, and do a full clean up at the end of each day. Administrative
  • Keep exits, stairs and walkways clear at all times. Administrative
  • Stack materials neatly on level ground, away from edges. Administrative
  • Wear gloves when handling waste. PPE
Low

PPE

Safety-toe boots (ASTM F2413)Safety goggles (ANSI Z87.1)Chemical-resistant glovesHearing protection (earmuffs or plugs)Work glovesHalf-face respirator (P100 cartridges)CoverallsHard hat (ANSI Z89.1)Face shield (ANSI Z87.1)

Plant and equipment

Pressure washerExtension ladderPortable generator

Emergency

Call 911. Add the nearest hospital, the assembly point and the first aid / cpr person for your site.

Sign-off

Supervisor and every worker sign to confirm they have read and understood this JHA.

Free JHA template for pressure washing

Word (.docx) and PDF, Letter landscape, no email needed. Fill in your site details, then print or send it.

Make yours in 2 minutes

Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.

Start this JHA

Pre-start checklist for pressure washing

Tick these off before work starts. They come from the hazards, permits and equipment in this job.

The safe sequence of work

  1. Cover power points and outside lights, and keep leads off wet ground
  2. Check surfaces for asbestos and lead paint first
  3. Never use the pressure washer from a ladder
  4. Mix and apply cleaning chemicals as the label says
  5. Wash down, keeping the lance away from people
  6. Stop runoff entering storm drain drains and clean up

Hazards to watch on pressure washing

The hazards most specific to this job, and the step where each one comes up.

Step 3, 5High pressure water jettingHigh pressure water cuts through skin and injects water and dirt into the body, or the hose whips.
Step 2Lead paint dust and fumesHomes and child-occupied facilities built before 1978 may have lead paint. Sanding, scraping or heating it releases dust that poisons workers and children.
Step 1Electric shock from cords and power toolsDamaged cords, plugs or tools, or water near power, give the user an electric shock.
Step 2Disturbing asbestosIn buildings built before 1981, OSHA presumes pipe and boiler insulation, sprayed or troweled coatings, and asphalt and vinyl flooring contain asbestos, and many other older materials can too. Drilling, cutting or breaking it releases fibers that cause cancer years later.
Step 4Hazardous chemicalsGlues, sealants, solvents, acids, cleaners and cement burn skin and eyes or cause breathing problems and poisoning.
Step 3Falling from a ladderThe ladder slips or tips, or the worker overreaches, and they fall onto a hard surface.
Almost certainLikelyPossibleUnlikelyRareHow bad it could be: First aid only to FatalityBA
Highest risk on pressure washing: Critical before controls (B), down to Medium after controls (A), on the United States 5 by 5 risk matrix (possible and fatality becomes unlikely and serious injury).

What changes on your site

This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):

  • Will anyone work 6 feet or more above a lower level?
  • Will anyone work on a roof?
  • Is there a skylight, fiberglass panel or other fragile roofing?
  • Will you use a scaffold or rolling tower?
  • Will you use an aerial lift (scissor lift or boom lift)?

Why JHAs get rejected

General contractors send documents back for these reasons. This example avoids them, but check yours too.

  • Generic steps such as "work safely" or "use PPE" with no task-specific hazards or controls.
  • No OSHA standards referenced for the hazards that have them, such as fall protection, ladders, scaffolds or silica.
  • No competent person named for fall protection, excavation, scaffolds or silica where those hazards exist.
  • Equipment listed without inspection requirements, and no training listed for the people using it.
  • Respirators listed with no respiratory protection program, medical clearance or fit test.
  • Controls rely only on PPE when engineering controls such as guardrails, wet cutting or extraction are feasible.
  • No crew sign-off, or no date and revision when the job has changed.

Questions

Do I need a JHA for pressure washing?

OSHA expects employers to find and control hazards on every job, and many general contractors require a written JHA for pressure washing before you start.

Who signs the JHA?

The supervisor or competent person who prepared it signs, and every crew member signs to show they were trained on the hazards and controls before the job starts. Many general contractors also sign to accept it.

How long do I keep it?

Keep this JHA on site during the job, and keep it with the training and inspection records for at least 1 year after the job (longer if your state plan or general contractor requires it). OSHA does not set a retention period for JHAs themselves.

What PPE is needed for pressure washing?

Usually Safety-toe boots (ASTM F2413), Safety goggles (ANSI Z87.1), Chemical-resistant gloves, Hearing protection (earmuffs or plugs), Work gloves, Half-face respirator (P100 cartridges), Coveralls, Hard hat (ANSI Z89.1), Face shield (ANSI Z87.1). The site rules may add more, so check with the general contractor.

More painting JHAs

Related jobs in other trades

Toolbox talks for this job

Blank JHA template: free JHA templates. Also for other countries: Australia (SWMS) · United Kingdom (RAMS) · Canada (FLHA)

Sources