SWMS for solar panel installation
Yes. Solar panel installation usually includes high risk construction work (risk of a person falling more than 2 metres; work on or near energised electrical installations or services), so a SWMS is required by law before work starts.
It must list the hazards, the controls and how they will be put in place, monitored and reviewed, and the workers must be consulted and sign before starting. The main hazards are falling from a roof edge, silica dust from concrete, brick, stone and tiles, disturbing asbestos and falling through a fragile roof or skylight.
SWMS example: solar panel installation
This is a complete SWMS for solar panel installation, with 6 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
High risk construction work covered
Job steps, hazards and controls
| # | Job step | Hazards | Risk before | Controls | Risk after |
|---|---|---|---|---|---|
| 1 | Check the roof for asbestos, brittle tiles and power lines |
| Extreme |
| Medium |
| 2 | Set up edge protection or harness anchors and a secured ladder |
| Extreme |
| Medium |
| 3 | Lift panels with a hoist, not up a ladder |
| High |
| Medium |
| 4 | Fit rails and brackets, cutting tiles with dust control |
| Extreme |
| Medium |
| 5 | Mount panels, remembering they make power in daylight |
| Extreme |
| Medium |
| 6 | Run DC cabling and test, then clean up the roof |
| Extreme |
| Medium |
PPE
Plant and equipment
Permits and plans
Emergency
Call 000. Add the nearest hospital, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this SWMS.
Free SWMS template for solar panel installation
Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for solar panel installation
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- SWMS read, explained and signed by everyone on the job
- Edge protection installed and checked before anyone works above 2 m
- Fragile roof areas and skylights covered or barricaded
- Ladder inspected, secured and extending 1 m above the landing
- Isolation, lockout and test for dead done before work starts
- Overhead lines identified and safe distances marked
- Asbestos register or survey checked for the work area
- Water suppression or on-tool extraction fitted; respirators fit tested
- Exclusion zone below the work and public kept out
- Weather checked: water, shade and rest breaks planned
- Wind and weather checked; stop work limits agreed
- First aider, first aid kit and emergency number (000) confirmed
The safe sequence of work
- Check the roof for asbestos, brittle tiles and power lines
- Set up edge protection or harness anchors and a secured ladder
- Lift panels with a hoist, not up a ladder
- Fit rails and brackets, cutting tiles with dust control
- Mount panels, remembering they make power in daylight
- Run DC cabling and test, then clean up the roof
Hazards to watch on solar panel installation
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone work more than 2 metres off the ground?
- Will anyone work on a roof?
- Will you use a scaffold or mobile tower?
- Will you use an EWP (scissor lift or boom lift)?
- Will you sand, scrape, cut or heat paint on a building built before 1997?
Licences and legal requirements in Australia
This task can involve these high risk construction work categories under the WHS Regulations:
- Risk of a person falling more than 2 metres
- Work on or near energised electrical installations or services
Equipment on this job that needs a licence, ticket or training:
- Fixed scaffold: Scaffolding HRWL (SB, SI or SA) to erect, alter or dismantle where a fall of more than 4 m is possible
- Materials hoist: High Risk Work Licence HM for a materials hoist
A SWMS must be prepared before any high risk construction work starts. It must list the high risk work, the hazards and risks, the control measures, and how those controls will be put in place, monitored and reviewed. It must be easy for the workers to read and understand.
Rules that apply: WHS Regulations, Chapter 8 (Asbestos); WHS Regulation 2011, Part 4.4 Falls; WHS Regulation 2011, Part 4.2 Hazardous manual tasks; WHS Regulation 2011, Part 3.2 (falling objects); WHS Regulations, Chapter 8A (Crystalline silica substances and engineered stone); WHS Regulation 2011, Part 4.7 General electrical safety.
Each state has its own regulator and some extra rules: New South Wales, Victoria, Queensland, Western Australia, South Australia and Australian Capital Territory.
Why SWMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- It is generic: another site address, tasks that are not on this job, or no sign it was reviewed for this site. WorkSafe WA says a generic SWMS may not meet the regulations unless it is reviewed and amended for the workplace.
- The HRCW boxes are not ticked, or the ticks do not match the tasks (for example a roof job with no falls box ticked).
- Falls are controlled only by "be careful", training or a harness, with no edge protection or scaffold and no reason why higher controls are not reasonably practicable.
- Workers will clip on to a harness but there is no rescue plan for someone left hanging.
- The "how controls are implemented, monitored and reviewed" part is missing, or it says the same thing on every row.
- No worker sign-on, no person responsible for compliance, or a date given to the principal contractor that is before they actually received it.
- Licence or White Card details are missing for workers operating plant or doing licensed high risk work.
Questions
Do I need a SWMS for solar panel installation?
Yes. Solar panel installation usually includes high risk construction work (risk of a person falling more than 2 metres; work on or near energised electrical installations or services), so a SWMS is required by law before work starts.
Who signs the SWMS?
The person conducting the business (PCBU) or their supervisor prepares it with the workers, and every worker doing the high risk work signs to show they were consulted and understand it. Give a copy to the principal contractor before work starts.
How long do I keep it?
Keep this SWMS, and every revised version, until the high risk construction work is finished, where workers and inspectors can see it on site. If a notifiable incident happens during the work, keep it for at least 2 years after the incident.
What PPE is needed for solar panel installation?
Usually Steel cap boots, Safety harness and lanyard, Cut-resistant gloves, Safety glasses, Sun protection (brim hat, long sleeves, SPF 50+), Hard hat, Half-face respirator (P2 or P3 filters), Overalls, Work gloves, Hearing protection (earmuffs or plugs), Face shield, Insulated electrical gloves, Arc-rated clothing and face shield. The site rules may add more, so check with the principal contractor.
More solar SWMS
Related jobs in other trades
Toolbox talks for this job
Blank SWMS template: free SWMS templates. Also for other countries: United Kingdom (RAMS) · United States (JHA) · Canada (FLHA)