SWMS for roof tile replacement
Yes. Roof tile replacement usually includes high risk construction work (risk of a person falling more than 2 metres), so a SWMS is required by law before work starts.
It must list the hazards, the controls and how they will be put in place, monitored and reviewed, and the workers must be consulted and sign before starting. The main hazards are falling from a roof edge, falling from height, silica dust from concrete, brick, stone and tiles and scaffold collapse or fall from scaffold.
SWMS example: roof tile replacement
This is a complete SWMS for roof tile replacement, with 9 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
High risk construction work covered
Job steps, hazards and controls
| # | Job step | Hazards | Risk before | Controls | Risk after |
|---|---|---|---|---|---|
| 1 | Check the weather, look for overhead power lines and barricade the area below the work |
| High |
| Medium |
| 2 | Set up scaffold or roof edge protection and a secured ladder for roof access |
| Extreme |
| Medium |
| 3 | Check for brittle or cracked tiles, skylights and roof sheets from the access point, and plan a walking route |
| Extreme |
| Medium |
| 4 | Walk on the tile laps only, clipped to an anchor where there is no edge protection |
| Extreme |
| Medium |
| 5 | Lift out broken tiles and stack them or lower them down; never throw them off the roof |
| High |
| Medium |
| 6 | Cut tiles with a grinder fitted with water or dust extraction, wearing a dust mask and glasses |
| Extreme |
| Medium |
| 7 | Fit new tiles, then re-bed and re-point ridge capping, taking breaks in heat and sun |
| High |
| Medium |
| 8 | Check the roof for tiles cracked during the work, then clear offcuts and loose tiles from the roof and gutters |
| Extreme |
| Medium |
| 9 | Take down access equipment last and leave the area below clean for the client |
| High |
| Medium |
PPE
Plant and equipment
Permits and plans
Emergency
Call 000. Add the nearest hospital, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this SWMS.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for roof tile replacement
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- SWMS read, explained and signed by everyone on the job
- Edge protection installed and checked before anyone works above 2 m
- Fragile roof areas and skylights covered or barricaded
- Ladder inspected, secured and extending 1 m above the landing
- Scaffold tagged, with a handover certificate if over 4 m
- Overhead lines identified and safe distances marked
- Water suppression or on-tool extraction fitted; respirators fit tested
- Exclusion zone below the work and public kept out
- Weather checked: water, shade and rest breaks planned
- Wind and weather checked; stop work limits agreed
- First aider, first aid kit and emergency number (000) confirmed
- PPE checked and worn: steel cap boots, safety harness and lanyard, work gloves, safety glasses
The safe sequence of work
- Check the weather, look for overhead power lines and barricade the area below the work
- Set up scaffold or roof edge protection and a secured ladder for roof access
- Check for brittle or cracked tiles, skylights and roof sheets from the access point, and plan a walking route
- Walk on the tile laps only, clipped to an anchor where there is no edge protection
- Lift out broken tiles and stack them or lower them down; never throw them off the roof
- Cut tiles with a grinder fitted with water or dust extraction, wearing a dust mask and glasses
- Fit new tiles, then re-bed and re-point ridge capping, taking breaks in heat and sun
- Check the roof for tiles cracked during the work, then clear offcuts and loose tiles from the roof and gutters
- Take down access equipment last and leave the area below clean for the client
Hazards to watch on roof tile replacement
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will you use an EWP (scissor lift or boom lift)?
- Was the building built before 2004?
- Will you sand, scrape, cut or heat paint on a building built before 1997?
- Will you use chemicals, solvents, glues, paints or fuels?
- Will people be living or working in the building while you work?
Licences and legal requirements in Australia
This task can involve these high risk construction work categories under the WHS Regulations:
- Risk of a person falling more than 2 metres
Equipment on this job that needs a licence, ticket or training:
- Fixed scaffold: Scaffolding HRWL (SB, SI or SA) to erect, alter or dismantle where a fall of more than 4 m is possible
A SWMS must be prepared before any high risk construction work starts. It must list the high risk work, the hazards and risks, the control measures, and how those controls will be put in place, monitored and reviewed. It must be easy for the workers to read and understand.
Rules that apply: WHS Regulation 2011, Part 3.2 (falling objects); WHS Regulation 2011, Part 4.4 Falls; WHS Regulation 2011, Part 4.4 Falls, Part 5.1 Plant and r.225 (scaffolds); WHS Regulation 2011, Part 4.2 Hazardous manual tasks; WHS Regulations, Chapter 8A (Crystalline silica substances and engineered stone); WHS Regulation 2011, Part 4.1 Noise.
Each state has its own regulator and some extra rules: New South Wales, Victoria, Queensland, Western Australia, South Australia and Australian Capital Territory.
Why SWMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- It is generic: another site address, tasks that are not on this job, or no sign it was reviewed for this site. WorkSafe WA says a generic SWMS may not meet the regulations unless it is reviewed and amended for the workplace.
- The HRCW boxes are not ticked, or the ticks do not match the tasks (for example a roof job with no falls box ticked).
- Falls are controlled only by "be careful", training or a harness, with no edge protection or scaffold and no reason why higher controls are not reasonably practicable.
- Workers will clip on to a harness but there is no rescue plan for someone left hanging.
- The "how controls are implemented, monitored and reviewed" part is missing, or it says the same thing on every row.
- No worker sign-on, no person responsible for compliance, or a date given to the principal contractor that is before they actually received it.
- Licence or White Card details are missing for workers operating plant or doing licensed high risk work.
Questions
Do I need a SWMS for roof tile replacement?
Yes. Roof tile replacement usually includes high risk construction work (risk of a person falling more than 2 metres), so a SWMS is required by law before work starts.
Who signs the SWMS?
The person conducting the business (PCBU) or their supervisor prepares it with the workers, and every worker doing the high risk work signs to show they were consulted and understand it. Give a copy to the principal contractor before work starts.
How long do I keep it?
Keep this SWMS, and every revised version, until the high risk construction work is finished, where workers and inspectors can see it on site. If a notifiable incident happens during the work, keep it for at least 2 years after the incident.
What PPE is needed for roof tile replacement?
Usually Steel cap boots, Safety harness and lanyard, Work gloves, Safety glasses, Sun protection (brim hat, long sleeves, SPF 50+), P2 dust mask, Hard hat, Hi-vis shirt or vest, Cut-resistant gloves, Face shield, Hearing protection (earmuffs or plugs), Half-face respirator (P2 or P3 filters), Safety goggles, Chemical-resistant gloves (nitrile), Knee pads. The site rules may add more, so check with the principal contractor.