SWMS for switchboard upgrade
Yes. Switchboard upgrade usually includes high risk construction work (work on or near energised electrical installations or services), so a SWMS is required by law before work starts.
It must list the hazards, the controls and how they will be put in place, monitored and reviewed, and the workers must be consulted and sign before starting. The main hazards are disturbing asbestos, electric shock from live wiring, lifting and carrying heavy loads and falling from a ladder.
SWMS example: switchboard upgrade
This is a complete SWMS for switchboard upgrade, with 10 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
High risk construction work covered
Job steps, hazards and controls
| # | Job step | Hazards | Risk before | Controls | Risk after |
|---|---|---|---|---|---|
| 1 | Tell the occupants when the power will be off and arrange a supply for medical or other critical equipment |
| Medium |
| Low |
| 2 | Set up barriers and good lighting at the switchboard so no one else can reach the open board |
| Medium |
| Low |
| 3 | Check the old switchboard backing board and surrounds for asbestos |
| Extreme |
| Medium |
| 4 | Arrange for the network operator (or a Level 2 accredited service provider in NSW) to disconnect the supply, then isolate, lock out and danger tag, and test to prove dead. Treat the consumer mains as live until the supply is disconnected |
| Extreme |
| Medium |
| 5 | Check the tester on a known live source before and after proving dead |
| Extreme |
| Medium |
| 6 | Remove the old switchboard, labelling every circuit as it comes off |
| Extreme |
| Medium |
| 7 | Mount the new enclosure, drilling with dust control and working from a stable step |
| High |
| Medium |
| 8 | Terminate circuits with RCD protection and tighten connections to the right torque |
| High |
| Medium |
| 9 | With your lock still on, do the dead tests: earth continuity, insulation resistance, polarity and correct circuit connections |
| Extreme |
| Medium |
| 10 | Remove your lock only when the dead tests pass and everyone is clear, re-energise, then test RCD trip times and polarity live; label the switchboard, clean up and issue the state certificate (for example a CCEW in NSW or a Certificate of Electrical Safety in Vic) |
| Extreme |
| Medium |
PPE
Plant and equipment
Permits and plans
Emergency
Call 000. Add the nearest hospital, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this SWMS.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for switchboard upgrade
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- SWMS read, explained and signed by everyone on the job
- Ladder inspected, secured and extending 1 m above the landing
- Isolation, lockout and test for dead done before work starts
- Asbestos register or survey checked for the work area
- First aider, first aid kit and emergency number (000) confirmed
- PPE checked and worn: steel cap boots, safety glasses, insulated electrical gloves, arc-rated clothing and face shield
The safe sequence of work
- Tell the occupants when the power will be off and arrange a supply for medical or other critical equipment
- Set up barriers and good lighting at the switchboard so no one else can reach the open board
- Check the old switchboard backing board and surrounds for asbestos
- Arrange for the network operator (or a Level 2 accredited service provider in NSW) to disconnect the supply, then isolate, lock out and danger tag, and test to prove dead. Treat the consumer mains as live until the supply is disconnected
- Check the tester on a known live source before and after proving dead
- Remove the old switchboard, labelling every circuit as it comes off
- Mount the new enclosure, drilling with dust control and working from a stable step
- Terminate circuits with RCD protection and tighten connections to the right torque
- With your lock still on, do the dead tests: earth continuity, insulation resistance, polarity and correct circuit connections
- Remove your lock only when the dead tests pass and everyone is clear, re-energise, then test RCD trip times and polarity live; label the switchboard, clean up and issue the state certificate (for example a CCEW in NSW or a Certificate of Electrical Safety in Vic)
Hazards to watch on switchboard upgrade
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone work more than 2 metres off the ground?
- Will anyone work on a roof?
- Is there a skylight, clear sheet, fibro or other fragile roofing?
- Will you use a scaffold or mobile tower?
- Will you use an EWP (scissor lift or boom lift)?
Licences and legal requirements in Australia
This task can involve these high risk construction work categories under the WHS Regulations:
- Work on or near energised electrical installations or services
A SWMS must be prepared before any high risk construction work starts. It must list the high risk work, the hazards and risks, the control measures, and how those controls will be put in place, monitored and reviewed. It must be easy for the workers to read and understand.
Rules that apply: WHS Regulations, Chapter 8 (Asbestos); WHS Regulation 2011, Part 4.7 General electrical safety; WHS Regulation 2011, Part 4.2 Hazardous manual tasks; WHS Regulation 2011, Part 4.4 Falls; WHS Regulation 2011, Part 4.7 and AS/NZS 3012.
Each state has its own regulator and some extra rules: New South Wales, Victoria, Queensland, Western Australia, South Australia and Australian Capital Territory.
Why SWMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- It is generic: another site address, tasks that are not on this job, or no sign it was reviewed for this site. WorkSafe WA says a generic SWMS may not meet the regulations unless it is reviewed and amended for the workplace.
- The HRCW boxes are not ticked, or the ticks do not match the tasks (for example a roof job with no falls box ticked).
- Falls are controlled only by "be careful", training or a harness, with no edge protection or scaffold and no reason why higher controls are not reasonably practicable.
- Workers will clip on to a harness but there is no rescue plan for someone left hanging.
- The "how controls are implemented, monitored and reviewed" part is missing, or it says the same thing on every row.
- No worker sign-on, no person responsible for compliance, or a date given to the principal contractor that is before they actually received it.
- Licence or White Card details are missing for workers operating plant or doing licensed high risk work.
Questions
Do I need a SWMS for switchboard upgrade?
Yes. Switchboard upgrade usually includes high risk construction work (work on or near energised electrical installations or services), so a SWMS is required by law before work starts.
Who signs the SWMS?
The person conducting the business (PCBU) or their supervisor prepares it with the workers, and every worker doing the high risk work signs to show they were consulted and understand it. Give a copy to the principal contractor before work starts.
How long do I keep it?
Keep this SWMS, and every revised version, until the high risk construction work is finished, where workers and inspectors can see it on site. If a notifiable incident happens during the work, keep it for at least 2 years after the incident.
What PPE is needed for switchboard upgrade?
Usually Steel cap boots, Safety glasses, Insulated electrical gloves, Arc-rated clothing and face shield, P2 dust mask, Hi-vis shirt or vest, Half-face respirator (P2 or P3 filters), Overalls, Work gloves, Cut-resistant gloves, Hearing protection (earmuffs or plugs), Hard hat, Knee pads. The site rules may add more, so check with the principal contractor.