Method statement for concrete slab pour
You must assess the risks of concrete slab pour and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are silica dust from concrete, brick, stone and tiles, being hit by mobile plant, road traffic and public entering the work area.
RAMS example: concrete slab pour
This is a complete RAMS for concrete slab pour, with 9 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
Risk assessment
| # | Activity | Hazards | Who might be harmed | Risk before | Controls | Risk after |
|---|---|---|---|---|---|---|
| 1 | Plan truck and pump access, checking for overhead power lines and soft ground |
| Workers, Plant operators, Public, Visitors, Road users | Very high (15) |
| Medium (5) |
| 2 | Set up traffic control at the site entry and a spotter for reversing trucks |
| Workers, Road users, Public, Children | Very high (15) |
| Medium (5) |
| 3 | Check formwork, edge forms, rebar and caps on starter bars before the pour |
| Workers | High (12) |
| Medium (5) |
| 4 | Set up the pump with outriggers on pads and an exclusion zone around the boom and hose. Never open a line or clear a blockage until the pressure is released |
| Workers, Visitors, Public, Plant operators | Very high (15) |
| Medium (5) |
| 5 | Place concrete, keeping clear of the hose end and wearing gloves and boots |
| Workers, Visitors, Public | High (12) |
| Medium (6) |
| 6 | Vibrate and screed, keeping power leads out of wet concrete |
| Workers | High (12) |
| Medium (6) |
| 7 | Finish the surface, taking breaks in heat and sun |
| Workers | High (12) |
| Medium (8) |
| 8 | Wash out the pump and trucks only in the set wash out area, away from drains |
| Workers, Visitors | Medium (9) |
| Low (4) |
| 9 | Cut control joints the next day with water suppression |
| Workers, People nearby | Very high (20) |
| Medium (8) |
Method statement: sequence of work
- Plan truck and pump access, checking for overhead power lines and soft ground
- Set up traffic control at the site entry and a spotter for reversing trucks
- Check formwork, edge forms, rebar and caps on starter bars before the pour
- Set up the pump with outriggers on pads and an exclusion zone around the boom and hose. Never open a line or clear a blockage until the pressure is released
- Place concrete, keeping clear of the hose end and wearing gloves and boots
- Vibrate and screed, keeping power leads out of wet concrete
- Finish the surface, taking breaks in heat and sun
- Wash out the pump and trucks only in the set wash out area, away from drains
- Cut control joints the next day with water suppression
PPE
Plant and equipment
Emergency
Call 999. Add the nearest A&E, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this RAMS.
Free RAMS template for concrete slab pour
Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for concrete slab pour
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- RAMS read, explained and signed by everyone on the job
- Overhead lines identified and safe distances marked
- Water suppression or on-tool extraction fitted; respirators fit tested
- Exclusion zone and spotter set up for plant and traffic
- Exclusion zone below the work and public kept out
- Weather checked: water, shade and rest breaks planned
- First aider, first aid kit and emergency number (999) confirmed
- PPE checked and worn: safety boots, hi-vis vest, chemical-resistant gloves, safety glasses
The safe sequence of work
- Plan truck and pump access, checking for overhead power lines and soft ground
- Set up traffic control at the site entry and a spotter for reversing trucks
- Check formwork, edge forms, rebar and caps on starter bars before the pour
- Set up the pump with outriggers on pads and an exclusion zone around the boom and hose. Never open a line or clear a blockage until the pressure is released
- Place concrete, keeping clear of the hose end and wearing gloves and boots
- Vibrate and screed, keeping power leads out of wet concrete
- Finish the surface, taking breaks in heat and sun
- Wash out the pump and trucks only in the set wash out area, away from drains
- Cut control joints the next day with water suppression
Hazards to watch on concrete slab pour
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone work at height, anywhere a fall could hurt them?
- Will anyone use a ladder or stepladder?
- Will anyone work on a roof?
- Is there a fragile roof, skylight or clear roof sheet?
- Will you use a scaffold or mobile tower?
Why RAMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- The method statement is only a list of headings that repeats the risk table and never says how the work is done.
- The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
- Residual risk is still High after controls with no extra measures or explanation.
- It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
- Work on an older building with no reference to an asbestos survey.
- Plant and access equipment listed with no inspection, thorough examination or competence evidence.
- No briefing record, no revision history, or no named supervisor.
Questions
Do I need RAMS for concrete slab pour?
You must assess the risks of concrete slab pour and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
Who signs the RAMS?
The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.
How long do I keep it?
Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.
What PPE is needed for concrete slab pour?
Usually Safety boots, Hi-vis vest, Chemical-resistant gloves, Safety glasses, Sun protection (sunscreen and neck cover), Safety helmet, Rigger gloves, Safety goggles, Knee pads, Ear defenders, Half-mask respirator (P3 filters), FFP3 dust mask. The site rules may add more, so check with the principal contractor.
More concreting RAMS
Related jobs in other trades
Toolbox talks for this job
Blank RAMS template: free RAMS templates. Also for other countries: Australia (SWMS) · United States (JHA) · Canada (FLHA)