Method statement for formwork
You must assess the risks of formwork and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are falling from height, being hit by mobile plant, falling through a floor opening or void and falling tools and materials.
RAMS example: formwork
This is a complete RAMS for formwork, with 9 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
Risk assessment
| # | Activity | Hazards | Who might be harmed | Risk before | Controls | Risk after |
|---|---|---|---|---|---|---|
| 1 | Check the formwork design and that props sit on sole plates on firm ground |
| Workers | High (10) |
| Medium (5) |
| 2 | Plan deliveries and crane lifts of form materials, with an exclusion zone under the load |
| Workers, Public, People below, Visitors | Very high (15) |
| Medium (8) |
| 3 | Install edge protection before anyone works near an edge |
| Workers, People below, Visitors | Very high (20) |
| Medium (5) |
| 4 | Cut and fix form ply and timber with saw guards working |
| Workers, People nearby | High (12) |
| Medium (8) |
| 5 | Erect props, bearers and joists in the designed order, bracing as you go. Work from a platform or from below, never walking on unfixed joists |
| Workers, People below | Very high (20) |
| Medium (6) |
| 6 | Lay the deck, cover penetrations and cap rebar bars that stick up |
| Workers, Visitors, People below, Public | Very high (20) |
| Medium (5) |
| 7 | Inspect forms and props and get sign off before the pour, then watch them during it |
| Workers | High (10) |
| Medium (5) |
| 8 | Strip forms only when the engineer says so, from a safe position, back propping as designed |
| Workers, Public, People below, Occupants | High (12) |
| Medium (8) |
| 9 | Denail, stack timber and clean up |
| Workers, Visitors | Medium (8) |
| Low (4) |
Method statement: sequence of work
- Check the formwork design and that props sit on sole plates on firm ground
- Plan deliveries and crane lifts of form materials, with an exclusion zone under the load
- Install edge protection before anyone works near an edge
- Cut and fix form ply and timber with saw guards working
- Erect props, bearers and joists in the designed order, bracing as you go. Work from a platform or from below, never walking on unfixed joists
- Lay the deck, cover penetrations and cap rebar bars that stick up
- Inspect forms and props and get sign off before the pour, then watch them during it
- Strip forms only when the engineer says so, from a safe position, back propping as designed
- Denail, stack timber and clean up
PPE
Plant and equipment
Permits and plans
Emergency
Call 999. Add the nearest A&E, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this RAMS.
Free RAMS template for formwork
Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for formwork
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- RAMS read, explained and signed by everyone on the job
- Edge protection or fall protection in place before work at height starts
- Openings, voids and penetrations covered and marked
- Exclusion zone and spotter set up for plant and traffic
- Exclusion zone below the work and public kept out
- Wind and weather checked; stop work limits agreed
- First aider, first aid kit and emergency number (999) confirmed
- PPE checked and worn: safety boots, safety helmet, safety glasses, rigger gloves
The safe sequence of work
- Check the formwork design and that props sit on sole plates on firm ground
- Plan deliveries and crane lifts of form materials, with an exclusion zone under the load
- Install edge protection before anyone works near an edge
- Cut and fix form ply and timber with saw guards working
- Erect props, bearers and joists in the designed order, bracing as you go. Work from a platform or from below, never walking on unfixed joists
- Lay the deck, cover penetrations and cap rebar bars that stick up
- Inspect forms and props and get sign off before the pour, then watch them during it
- Strip forms only when the engineer says so, from a safe position, back propping as designed
- Denail, stack timber and clean up
Hazards to watch on formwork
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone use a ladder or stepladder?
- Will anyone work on a roof?
- Is there a fragile roof, skylight or clear roof sheet?
- Will you use a scaffold or mobile tower?
- Will you use a MEWP (scissor lift or cherry picker)?
Licences and legal requirements in United Kingdom
Equipment on this job that needs a licence, ticket or training:
- Mobile crane: CPCS or NPORS crane operator card, plus slinger signaller card; lift plan by an Appointed Person
Employers must assess the risks of their work and record the significant findings (required where you employ 5 or more people). On CDM projects, contractors give their RAMS to the principal contractor before starting, and brief the workers on it.
Rules that apply: Lifting Operations and Lifting Equipment Regulations 1998 (LOLER); Work at Height Regulations 2005, regulation 10 (falling objects); CDM Regulations 2015 and PUWER 1998; Work at Height Regulations 2005; Provision and Use of Work Equipment Regulations 1998 (PUWER); COSHH Regulations 2002; Control of Noise at Work Regulations 2005; Manual Handling Operations Regulations 1992; CDM Regulations 2015, regulation 19 (stability of structures).
Why RAMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- The method statement is only a list of headings that repeats the risk table and never says how the work is done.
- The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
- Residual risk is still High after controls with no extra measures or explanation.
- It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
- Work on an older building with no reference to an asbestos survey.
- Plant and access equipment listed with no inspection, thorough examination or competence evidence.
- No briefing record, no revision history, or no named supervisor.
Questions
Do I need RAMS for formwork?
You must assess the risks of formwork and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
Who signs the RAMS?
The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.
How long do I keep it?
Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.
What PPE is needed for formwork?
Usually Safety boots, Safety helmet, Safety glasses, Rigger gloves, Ear defenders, Full body harness and lanyard, Hi-vis vest, FFP3 dust mask, Chemical-resistant gloves, Safety goggles, Knee pads, Cut-resistant gloves. The site rules may add more, so check with the principal contractor.
More concreting RAMS
Related jobs in other trades
Toolbox talks for this job
Blank RAMS template: free RAMS templates. Also for other countries: Australia (SWMS) · United States (JHA) · Canada (FLHA)