Method statement for concrete cutting
You must assess the risks of concrete cutting and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are silica dust from concrete, brick, stone and tiles, electric shock from live wiring, hitting underground services and falling through a floor opening or void.
RAMS example: concrete cutting
This is a complete RAMS for concrete cutting, with 8 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
Risk assessment
| # | Activity | Hazards | Who might be harmed | Risk before | Controls | Risk after |
|---|---|---|---|---|---|---|
| 1 | Get the engineer's approval for every cut, then scan the slab and mark cables, conduits, reo and post-tension tendons. Never cut or core through a tendon |
| Workers, Occupants, Public | Very high (15) |
| Medium (5) |
| 2 | Set an exclusion zone, including the floor below for coring, and keep occupants out |
| Workers, Public, People below, Children, Residents, Staff | High (12) |
| Medium (8) |
| 3 | Plan where the water and slurry will go and keep leads off wet ground, using RCD protection |
| Workers, Visitors, Public | High (12) |
| Low (4) |
| 4 | Check the blade or bit, guard and water feed before starting |
| Workers, People nearby | High (12) |
| Medium (8) |
| 5 | Fix the core drill rig with an anchor or vacuum base so it cannot spin |
| Workers, People nearby | High (12) |
| Medium (6) |
| 6 | Cut with water suppression or extraction, never dry cut. Indoors, use electric or hydraulic saws; never run petrol saws or generators inside (carbon monoxide) |
| Workers, People nearby | Very high (20) |
| Medium (8) |
| 7 | Support cut pieces and cores so they do not drop or pinch the blade |
| Workers, Public, People below, Occupants | High (12) |
| Medium (8) |
| 8 | Cover or guard new holes, vacuum slurry and clean up |
| Workers, Visitors, Public | Very high (15) |
| Medium (5) |
Method statement: sequence of work
- Get the engineer's approval for every cut, then scan the slab and mark cables, conduits, reo and post-tension tendons. Never cut or core through a tendon
- Set an exclusion zone, including the floor below for coring, and keep occupants out
- Plan where the water and slurry will go and keep leads off wet ground, using RCD protection
- Check the blade or bit, guard and water feed before starting
- Fix the core drill rig with an anchor or vacuum base so it cannot spin
- Cut with water suppression or extraction, never dry cut. Indoors, use electric or hydraulic saws; never run petrol saws or generators inside (carbon monoxide)
- Support cut pieces and cores so they do not drop or pinch the blade
- Cover or guard new holes, vacuum slurry and clean up
PPE
Plant and equipment
Permits and plans
Emergency
Call 999. Add the nearest A&E, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this RAMS.
Free RAMS template for concrete cutting
Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for concrete cutting
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- RAMS read, explained and signed by everyone on the job
- Openings, voids and penetrations covered and marked
- Isolation, lockout and test for dead done before work starts
- Utility plans checked and area scanned with CAT and Genny
- Water suppression or on-tool extraction fitted; respirators fit tested
- Exclusion zone below the work and public kept out
- First aider, first aid kit and emergency number (999) confirmed
- PPE checked and worn: safety boots, safety glasses, ear defenders, FFP3 dust mask
The safe sequence of work
- Get the engineer's approval for every cut, then scan the slab and mark cables, conduits, reo and post-tension tendons. Never cut or core through a tendon
- Set an exclusion zone, including the floor below for coring, and keep occupants out
- Plan where the water and slurry will go and keep leads off wet ground, using RCD protection
- Check the blade or bit, guard and water feed before starting
- Fix the core drill rig with an anchor or vacuum base so it cannot spin
- Cut with water suppression or extraction, never dry cut. Indoors, use electric or hydraulic saws; never run petrol saws or generators inside (carbon monoxide)
- Support cut pieces and cores so they do not drop or pinch the blade
- Cover or guard new holes, vacuum slurry and clean up
Hazards to watch on concrete cutting
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone work at height, anywhere a fall could hurt them?
- Will anyone use a ladder or stepladder?
- Will anyone work on a roof?
- Is there a fragile roof, skylight or clear roof sheet?
- Will you use a scaffold or mobile tower?
Why RAMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- The method statement is only a list of headings that repeats the risk table and never says how the work is done.
- The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
- Residual risk is still High after controls with no extra measures or explanation.
- It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
- Work on an older building with no reference to an asbestos survey.
- Plant and access equipment listed with no inspection, thorough examination or competence evidence.
- No briefing record, no revision history, or no named supervisor.
Questions
Do I need RAMS for concrete cutting?
You must assess the risks of concrete cutting and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
Who signs the RAMS?
The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.
How long do I keep it?
Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.
What PPE is needed for concrete cutting?
Usually Safety boots, Safety glasses, Ear defenders, FFP3 dust mask, Rigger gloves, Safety helmet, Hi-vis vest, Half-mask respirator (P3 filters). The site rules may add more, so check with the principal contractor.