JHA for central air installation
OSHA expects employers to find and control hazards on every job, and many general contractors require a written JHA for central air installation before you start.
A JHA breaks the job into steps, lists the hazards in each step and the controls that protect the crew, and the crew signs it. The main hazards are disturbing asbestos, electric shock from live wiring, falling through a floor opening or void and heat stress.
JHA example: central air installation
This is a complete JHA for central air installation, with 6 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
Job steps, hazards and controls
| # | Job step | Hazards | Risk before | Controls | Risk after |
|---|---|---|---|---|---|
| 1 | Check the roof space for asbestos, cables and access |
| Critical |
| Medium |
| 2 | Work in the roof space early in the day, with breaks and water |
| High |
| Medium |
| 3 | Lift the indoor unit into the roof with a hoist or team |
| High |
| Medium |
| 4 | Walk on joists or crawl boards only |
| Critical |
| Medium |
| 5 | Install ducts, cutting with care and wearing gloves and a mask for insulation |
| Medium |
| Low |
| 6 | Connect refrigerant and power, test and commission |
| Critical |
| Medium |
PPE
Plant and equipment
Permits and plans
Emergency
Call 911. Add the nearest hospital, the assembly point and the first aid / cpr person for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this JHA.
Free JHA template for central air installation
Word (.docx) and PDF, Letter landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for central air installation
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- JHA read, explained and signed by everyone on the job
- Openings, voids and penetrations covered and marked
- Lockout, tagout and test before touch done before work starts
- Asbestos register or survey checked for the work area
- Confined space permit, atmosphere test and standby person in place
- Exclusion zone below the work and public kept out
- Weather checked: water, shade and rest breaks planned
- First aid / CPR person, first aid kit and emergency number (911) confirmed
- PPE checked and worn: safety-toe boots (ASTM F2413), safety glasses (ANSI Z87.1), cut-resistant gloves, N95 respirator
The safe sequence of work
- Check the roof space for asbestos, cables and access
- Work in the roof space early in the day, with breaks and water
- Lift the indoor unit into the roof with a hoist or team
- Walk on joists or crawl boards only
- Install ducts, cutting with care and wearing gloves and a mask for insulation
- Connect refrigerant and power, test and commission
Hazards to watch on central air installation
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone work 6 feet or more above a lower level?
- Will anyone use a ladder or stepladder?
- Will anyone work on a roof?
- Is there a skylight, fiberglass panel or other fragile roofing?
- Will you use a scaffold or rolling tower?
Licences and legal requirements in United States
Equipment on this job that needs a licence, ticket or training:
- Mobile crane: Operator certified by an accredited body or audited employer program (29 CFR 1926.1427) and evaluated by the employer, with a signed evaluation on site (1926.1427(f)); qualified rigger (1926.1425) and qualified signal person (1926.1428)
OSHA requires employers to find and fix hazards and to train workers on them. A JHA breaks the job into steps, lists the hazards in each step and the controls that protect the crew. General contractors often require one before you start.
Rules that apply: 29 CFR 1926.1101 and 40 CFR 61 Subpart M (NESHAP); 29 CFR 1926 Subpart K; OSH Act Section 5(a)(1) General Duty Clause; state heat rules where they apply (Cal/OSHA T8 3395, WA WAC 296-62-095, OR OAR 437-002-0156, MD COMAR 09.12.32); 29 CFR 1926 Subpart AA; 29 CFR 1926.501(c); 29 CFR 1926 Subpart M; 40 CFR Part 82 Subpart F (Section 608).
Why JHAs get rejected
General contractors send documents back for these reasons. This example avoids them, but check yours too.
- Generic steps such as "work safely" or "use PPE" with no task-specific hazards or controls.
- No OSHA standards referenced for the hazards that have them, such as fall protection, ladders, scaffolds or silica.
- No competent person named for fall protection, excavation, scaffolds or silica where those hazards exist.
- Equipment listed without inspection requirements, and no training listed for the people using it.
- Respirators listed with no respiratory protection program, medical clearance or fit test.
- Controls rely only on PPE when engineering controls such as guardrails, wet cutting or extraction are feasible.
- No crew sign-off, or no date and revision when the job has changed.
Questions
Do I need a JHA for central air installation?
OSHA expects employers to find and control hazards on every job, and many general contractors require a written JHA for central air installation before you start.
Who signs the JHA?
The supervisor or competent person who prepared it signs, and every crew member signs to show they were trained on the hazards and controls before the job starts. Many general contractors also sign to accept it.
How long do I keep it?
Keep this JHA on site during the job, and keep it with the training and inspection records for at least 1 year after the job (longer if your state plan or general contractor requires it). OSHA does not set a retention period for JHAs themselves.
What PPE is needed for central air installation?
Usually Safety-toe boots (ASTM F2413), Safety glasses (ANSI Z87.1), Cut-resistant gloves, N95 respirator, Personal fall arrest system (harness), Half-face respirator (P100 cartridges), Coveralls, Work gloves, Rubber insulating gloves, Arc flash PPE (NFPA 70E), Knee pads, Hard hat (ANSI Z89.1), Sun protection (sunscreen, hat, long sleeves), Face shield (ANSI Z87.1). The site rules may add more, so check with the general contractor.
More hvac JHAs
Related jobs in other trades
Toolbox talks for this job
Blank JHA template: free JHA templates. Also for other countries: Australia (SWMS) · United Kingdom (RAMS) · Canada (FLHA)