SWMS for ducted air conditioning installation
Yes. Ducted air conditioning installation usually includes high risk construction work (work on or near chemical, fuel or refrigerant lines; work on or near energised electrical installations or services), so a SWMS is required by law before work starts.
It must list the hazards, the controls and how they will be put in place, monitored and reviewed, and the workers must be consulted and sign before starting. The main hazards are disturbing asbestos, electric shock from live wiring, falling through a floor opening or void and heat stress.
SWMS example: ducted air conditioning installation
This is a complete SWMS for ducted air conditioning installation, with 6 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
High risk construction work covered
Job steps, hazards and controls
| # | Job step | Hazards | Risk before | Controls | Risk after |
|---|---|---|---|---|---|
| 1 | Check the roof space for asbestos, cables and access |
| Extreme |
| Medium |
| 2 | Work in the roof space early in the day, with breaks and water |
| High |
| Medium |
| 3 | Lift the indoor unit into the roof with a hoist or team |
| High |
| Medium |
| 4 | Walk on joists or crawl boards only |
| Extreme |
| Medium |
| 5 | Install ducts, cutting with care and wearing gloves and a mask for insulation |
| Medium |
| Low |
| 6 | Connect refrigerant and power, test and commission |
| Extreme |
| Medium |
PPE
Plant and equipment
Permits and plans
Emergency
Call 000. Add the nearest hospital, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this SWMS.
Free SWMS template for ducted air conditioning installation
Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for ducted air conditioning installation
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- SWMS read, explained and signed by everyone on the job
- Openings, voids and penetrations covered and marked
- Isolation, lockout and test for dead done before work starts
- Asbestos register or survey checked for the work area
- Confined space permit, atmosphere test and standby person in place
- Exclusion zone below the work and public kept out
- Weather checked: water, shade and rest breaks planned
- First aider, first aid kit and emergency number (000) confirmed
- PPE checked and worn: steel cap boots, safety glasses, cut-resistant gloves, P2 dust mask
The safe sequence of work
- Check the roof space for asbestos, cables and access
- Work in the roof space early in the day, with breaks and water
- Lift the indoor unit into the roof with a hoist or team
- Walk on joists or crawl boards only
- Install ducts, cutting with care and wearing gloves and a mask for insulation
- Connect refrigerant and power, test and commission
Hazards to watch on ducted air conditioning installation
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone work more than 2 metres off the ground?
- Will anyone use a ladder or stepladder?
- Will anyone work on a roof?
- Is there a skylight, clear sheet, fibro or other fragile roofing?
- Will you use a scaffold or mobile tower?
Licences and legal requirements in Australia
This task can involve these high risk construction work categories under the WHS Regulations:
- Work on or near chemical, fuel or refrigerant lines
- Work on or near energised electrical installations or services
Equipment on this job that needs a licence, ticket or training:
- Crane (Franna or mobile): HRWL for the crane class (e.g. C2, CN, C6), plus Dogging licence (DG) where slinging needs judgement or the load is out of the operator's view
A SWMS must be prepared before any high risk construction work starts. It must list the high risk work, the hazards and risks, the control measures, and how those controls will be put in place, monitored and reviewed. It must be easy for the workers to read and understand.
Rules that apply: WHS Regulations, Chapter 8 (Asbestos); WHS Regulation 2011, Part 4.7 General electrical safety; WHS Regulation 2011, Part 4.3 Confined spaces; WHS Regulation 2011, Part 4.2 Hazardous manual tasks; WHS Regulation 2011, Part 3.2 (falling objects); WHS Regulation 2011, Part 4.4 Falls; Ozone Protection and Synthetic Greenhouse Gas Management Act 1989.
Each state has its own regulator and some extra rules: New South Wales, Victoria, Queensland, Western Australia, South Australia and Australian Capital Territory.
Why SWMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- It is generic: another site address, tasks that are not on this job, or no sign it was reviewed for this site. WorkSafe WA says a generic SWMS may not meet the regulations unless it is reviewed and amended for the workplace.
- The HRCW boxes are not ticked, or the ticks do not match the tasks (for example a roof job with no falls box ticked).
- Falls are controlled only by "be careful", training or a harness, with no edge protection or scaffold and no reason why higher controls are not reasonably practicable.
- Workers will clip on to a harness but there is no rescue plan for someone left hanging.
- The "how controls are implemented, monitored and reviewed" part is missing, or it says the same thing on every row.
- No worker sign-on, no person responsible for compliance, or a date given to the principal contractor that is before they actually received it.
- Licence or White Card details are missing for workers operating plant or doing licensed high risk work.
Questions
Do I need a SWMS for ducted air conditioning installation?
Yes. Ducted air conditioning installation usually includes high risk construction work (work on or near chemical, fuel or refrigerant lines; work on or near energised electrical installations or services), so a SWMS is required by law before work starts.
Who signs the SWMS?
The person conducting the business (PCBU) or their supervisor prepares it with the workers, and every worker doing the high risk work signs to show they were consulted and understand it. Give a copy to the principal contractor before work starts.
How long do I keep it?
Keep this SWMS, and every revised version, until the high risk construction work is finished, where workers and inspectors can see it on site. If a notifiable incident happens during the work, keep it for at least 2 years after the incident.
What PPE is needed for ducted air conditioning installation?
Usually Steel cap boots, Safety glasses, Cut-resistant gloves, P2 dust mask, Safety harness and lanyard, Half-face respirator (P2 or P3 filters), Overalls, Work gloves, Insulated electrical gloves, Arc-rated clothing and face shield, Knee pads, Hard hat, Sun protection (brim hat, long sleeves, SPF 50+), Face shield. The site rules may add more, so check with the principal contractor.