SWMS example: burst pipe repair
This is a complete SWMS for burst pipe repair, with 6 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
High risk construction work covered
Job steps, hazards and controls
| # | Job step | Hazards | Risk before | Controls | Risk after |
|---|---|---|---|---|---|
| 1 | Shut off water at the main and isolate power anywhere water has reached |
| Extreme |
| Medium |
| 2 | Check for mould and sewage contamination in wet areas |
| Medium |
| Low |
| 3 | Open up the wall or floor to reach the pipe, checking for asbestos first |
| Extreme |
| Medium |
| 4 | Cut out the damaged section and fit the repair, with a hot work permit if soldering |
| Extreme |
| Medium |
| 5 | Turn water back on and check for leaks under pressure |
| Medium |
| Low |
| 6 | Dry the area, clean up and advise on make good |
| Medium |
| Low |
PPE
Plant and equipment
Permits and plans
Emergency
Call 000. Add the nearest hospital, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this SWMS.
Free SWMS template for burst pipe repair
Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for burst pipe repair
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- SWMS read, explained and signed by everyone on the job
- Asbestos register or survey checked for the work area
- Hot work permit issued, extinguisher at hand, fire watch arranged
- First aider, first aid kit and emergency number (000) confirmed
- PPE checked and worn: steel cap boots, work gloves, safety glasses, P2 dust mask
The safe sequence of work
- Shut off water at the main and isolate power anywhere water has reached
- Check for mould and sewage contamination in wet areas
- Open up the wall or floor to reach the pipe, checking for asbestos first
- Cut out the damaged section and fit the repair, with a hot work permit if soldering
- Turn water back on and check for leaks under pressure
- Dry the area, clean up and advise on make good
Hazards to watch on burst pipe repair
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone work more than 2 metres off the ground?
- Will anyone use a ladder or stepladder?
- Will anyone work on a roof?
- Is there a skylight, clear sheet, fibro or other fragile roofing?
- Will you use a scaffold or mobile tower?
Why SWMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- It is generic: another site address, tasks that are not on this job, or no sign it was reviewed for this site. WorkSafe WA says a generic SWMS may not meet the regulations unless it is reviewed and amended for the workplace.
- The HRCW boxes are not ticked, or the ticks do not match the tasks (for example a roof job with no falls box ticked).
- Falls are controlled only by "be careful", training or a harness, with no edge protection or scaffold and no reason why higher controls are not reasonably practicable.
- Workers will clip on to a harness but there is no rescue plan for someone left hanging.
- The "how controls are implemented, monitored and reviewed" part is missing, or it says the same thing on every row.
- No worker sign-on, no person responsible for compliance, or a date given to the principal contractor that is before they actually received it.
- Licence or White Card details are missing for workers operating plant or doing licensed high risk work.
Questions
Do I need a SWMS for burst pipe repair?
A SWMS is required by law if burst pipe repair includes any high risk construction work, such as working where someone could fall more than 2 metres. Many principal contractors ask for one either way.
Who signs the SWMS?
The person conducting the business (PCBU) or their supervisor prepares it with the workers, and every worker doing the high risk work signs to show they were consulted and understand it. Give a copy to the principal contractor before work starts.
How long do I keep it?
Keep this SWMS, and every revised version, until the high risk construction work is finished, where workers and inspectors can see it on site. If a notifiable incident happens during the work, keep it for at least 2 years after the incident.
What PPE is needed for burst pipe repair?
Usually Steel cap boots, Work gloves, Safety glasses, P2 dust mask, Half-face respirator (P2 or P3 filters), Safety goggles, Overalls, Chemical-resistant gloves (nitrile), Face shield, Hearing protection (earmuffs or plugs), Welding gloves, Cut-resistant gloves. The site rules may add more, so check with the principal contractor.
More plumbing SWMS
Related jobs in other trades
Toolbox talks for this job
Blank SWMS template: free SWMS templates. Also for other countries: United Kingdom (RAMS) · United States (JHA) · Canada (FLHA)