SWMS for steel handrail installation

A SWMS is required by law if steel handrail installation includes any high risk construction work, such as working where someone could fall more than 2 metres. Many principal contractors ask for one either way.

It must list the hazards, the controls and how they will be put in place, monitored and reviewed, and the workers must be consulted and sign before starting. The main hazards are falling from height, silica dust from concrete, brick, stone and tiles, welding and cutting fumes and falling through a floor opening or void.

SWMS example: steel handrail installation

This is a complete SWMS for steel handrail installation, with 5 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.

Safe Work Method Statement (SWMS)
Steel handrail and balustrade installation · Welding and fabrication · Example
Document SWMS-001 · Rev 1

High risk construction work covered

None for this task on its own. Tick any that apply on your site.

Job steps, hazards and controls

#Job stepHazardsRisk beforeControlsRisk after
1Install temporary edge protection on open edges
  • Falling from height
  • Falling through a floor opening or void
Extreme
  • Do the work from the ground where you can, for example pre-assemble on the ground or use extension poles. Eliminate
  • Install guardrails or edge protection on all open edges before work starts. Isolate
  • Use a scaffold, mobile work platform or EWP instead of working off a ladder. Engineering
  • Where edge protection is not practical, use a fall restraint or fall arrest system on a rated anchor point. Engineering
  • Everyone working at height holds a White Card and has been briefed on this SWMS before going up. Administrative
  • Have a written emergency and rescue plan, tested before work starts, so a worker hanging in a harness can be brought down within minutes (WHS Regulations r.80). Administrative
  • Wear a full body harness with a shock-absorbing lanyard, clipped on at all times when using fall arrest. PPE
  • Cover every hole and penetration with a fixed, secured cover marked "HOLE" or "DANGER". Isolate
  • Put guardrails with toe boards around stairwells, lift shafts, voids and open edges. Isolate
  • Install stairs early and fit temporary handrails as soon as they go in. Engineering
  • Never remove a cover or guardrail without approval. Put it back straight away. Administrative
  • Inspect covers and barriers daily and after other trades have been through. Administrative
  • Keep lighting good enough to see openings, especially on lower floors and in the evening. Administrative
  • Use a harness clipped to a rated anchor when working right next to an open void. PPE
Medium
2Drill anchors with dust extraction
  • Silica dust from concrete, brick, stone and tiles
  • Loud noise
Extreme
  • If the job involves engineered stone: do not supply, fabricate or install engineered stone benchtops, panels or slabs (banned since 1 July 2024). Removing, repairing or making minor changes to existing engineered stone is only allowed with water suppression or on-tool extraction, a fitted respirator, and written notice to the regulator before the work starts. Eliminate
  • Order materials cut to size, or use low-dust methods such as score and snap or a block splitter. Substitute
  • Cut outdoors or in a separate area, with other people well away and upwind. Isolate
  • Use water on the blade or on-tool dust extraction connected to an H-class vacuum. Engineering
  • Clean up with a vacuum or wet methods. Never dry sweep or use compressed air. Administrative
  • If the cutting, grinding or drilling is high risk, prepare a silica risk control plan (or include the r.529CA assessment in this SWMS), train workers in silica risks and give them the plan before work starts. Administrative
  • Wear a fit-tested P2 (or better) respirator. PPE
  • Use quieter tools and methods, such as cut-to-size materials, low-noise machines and battery tools. Substitute
  • Keep noisy plant away from work areas, and use screens or distance between the noise and people. Isolate
  • Keep tools maintained and use mufflers on compressors and generators. Engineering
  • Limit time on noisy tools and rotate workers. Administrative
  • If you have to shout to be heard 1 metre away, wear hearing protection. Administrative
  • Keep exposure below 85 dB(A) over 8 hours. Give hearing tests to workers who often need hearing protection. Administrative
  • Wear earplugs or earmuffs rated for the noise. PPE
Medium
3Weld on site under a hot work permit
  • Fire from hot works
  • Welding and cutting fumes
  • Eye injuries
Extreme
  • Use cold work methods where you can, such as bolting, press fittings or cutting with a saw instead of a torch. Eliminate
  • Move anything that can burn at least 15 metres away (AS 1674.1), or protect it with fire blankets or screens. Isolate
  • Use fire-resistant screens to stop sparks reaching people or gaps in walls and floors. Engineering
  • Get a hot work permit before starting. Administrative
  • Keep a charged fire extinguisher and fire blanket at the work spot. Administrative
  • Remove paint, galvanising and coatings from the weld area first, or use a process that makes less fume. Substitute
  • Use fume extraction (local exhaust ventilation) close to the weld. Engineering
  • Weld outdoors or in a well-ventilated area, and keep your head out of the fume plume. Engineering
  • Never weld or cut in a confined space without testing the air and using forced ventilation. Administrative
  • Wear a powered air respirator or fitted respirator when extraction is not enough. PPE
  • Use tool guards and screens to stop flying particles. Engineering
  • Use dust extraction and water to keep dust out of the air. Engineering
  • Keep others out of the area when cutting, grinding or chipping. Administrative
  • Keep an eye wash station or eye wash bottles on site. Administrative
  • Wear safety glasses at all times, goggles for dust and chemicals, and a face shield for grinding. PPE
Medium
4Grind welds smooth with guards on
  • Angle grinder injuries
  • Eye injuries
High
  • Use a guarded saw or a different tool where you can. Substitute
  • Keep the guard on and use the side handle. Never remove the guard. Engineering
  • Use the right disc for the job, rated for the grinder's speed. Check it for cracks first. Administrative
  • Only trained people change discs, with the grinder unplugged or the battery out. Administrative
  • Keep both hands on the grinder and let the disc stop before putting it down. Administrative
  • Clamp the work and keep people out of the spark path. Administrative
  • Wear a face shield over safety glasses, hearing protection, gloves and long sleeves. PPE
  • Eye injuries: see step 3 for the full controls Administrative
Medium
5Fire watch and clean up
  • Fire and emergencies
  • Poor housekeeping and waste
High
  • Provide fire extinguishers suited to the site, checked and easy to reach. Engineering
  • Keep exits and escape routes clear and signed. Engineering
  • Have a site emergency plan: alarm, exits, assembly point and emergency contacts. Administrative
  • Keep a stocked first aid kit and at least one trained first aider on site. Administrative
  • Know the site address and how emergency services get in. Call 000. Administrative
  • Go through the emergency plan with every worker and visitor at induction. Administrative
  • Keep flammable materials and rubbish away from exits and escape routes. Administrative
  • Order materials to size and send packaging back where you can. Eliminate
  • Put skip bins and waste chutes close to the work. Engineering
  • Clean as you go, and do a full clean up at the end of each day. Administrative
  • Keep exits, stairs and walkways clear at all times. Administrative
  • Stack materials neatly on level ground, away from edges. Administrative
  • Wear gloves when handling waste. PPE
Medium

PPE

Steel cap bootsWelding helmetWelding glovesSafety glassesHearing protection (earmuffs or plugs)Safety harness and lanyardHalf-face respirator (P2 or P3 filters)Face shieldOverallsSafety gogglesCut-resistant glovesWork gloves

Plant and equipment

WelderAngle grinderRotary hammer drillHand tools

Permits and plans

Hot work permit

Emergency

Call 000. Add the nearest hospital, the assembly point and the first aider for your site.

Sign-off

Supervisor and every worker sign to confirm they have read and understood this SWMS.

Free SWMS template for steel handrail installation

Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.

Make yours in 2 minutes

Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.

Start this SWMS

Pre-start checklist for steel handrail installation

Tick these off before work starts. They come from the hazards, permits and equipment in this job.

The safe sequence of work

  1. Install temporary edge protection on open edges
  2. Drill anchors with dust extraction
  3. Weld on site under a hot work permit
  4. Grind welds smooth with guards on
  5. Fire watch and clean up

Hazards to watch on steel handrail installation

The hazards most specific to this job, and the step where each one comes up.

Step 3Welding and cutting fumesWelding, cutting and brazing give off metal fumes and gases that damage the lungs and can cause cancer.
Step 4Angle grinder injuriesThe disc shatters, binds or kicks back, causing deep cuts to legs and hands or eye injuries.
Step 5Fire and emergenciesA fire, injury or other emergency happens and workers cannot get out, raise the alarm or get first aid in time.
Step 3Fire from hot worksSparks and heat from welding, grinding or flame torches set fire to timber, insulation, rubbish or fuel nearby.
Step 1Falling through a floor opening or voidA worker steps into an open hole, stairwell, lift shaft or penetration and falls to the level below.
Step 3, 4Eye injuriesFlying chips, dust, chemicals or sparks get into the eye and cause damage or blindness.
Almost certainLikelyPossibleUnlikelyRareHow bad it could be: Insignificant to CatastrophicBA
Highest risk on steel handrail installation: Extreme before controls (B), down to Medium after controls (A), on the Australia 5 by 5 risk matrix (likely and catastrophic becomes unlikely and major).

What changes on your site

This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):

  • Will anyone work more than 2 metres off the ground?
  • Will anyone use a ladder or stepladder?
  • Will anyone work on a roof?
  • Is there a skylight, clear sheet, fibro or other fragile roofing?
  • Will you use a scaffold or mobile tower?

Why SWMS get rejected

Principal contractors send documents back for these reasons. This example avoids them, but check yours too.

  • It is generic: another site address, tasks that are not on this job, or no sign it was reviewed for this site. WorkSafe WA says a generic SWMS may not meet the regulations unless it is reviewed and amended for the workplace.
  • The HRCW boxes are not ticked, or the ticks do not match the tasks (for example a roof job with no falls box ticked).
  • Falls are controlled only by "be careful", training or a harness, with no edge protection or scaffold and no reason why higher controls are not reasonably practicable.
  • Workers will clip on to a harness but there is no rescue plan for someone left hanging.
  • The "how controls are implemented, monitored and reviewed" part is missing, or it says the same thing on every row.
  • No worker sign-on, no person responsible for compliance, or a date given to the principal contractor that is before they actually received it.
  • Licence or White Card details are missing for workers operating plant or doing licensed high risk work.

Questions

Do I need a SWMS for steel handrail installation?

A SWMS is required by law if steel handrail installation includes any high risk construction work, such as working where someone could fall more than 2 metres. Many principal contractors ask for one either way.

Who signs the SWMS?

The person conducting the business (PCBU) or their supervisor prepares it with the workers, and every worker doing the high risk work signs to show they were consulted and understand it. Give a copy to the principal contractor before work starts.

How long do I keep it?

Keep this SWMS, and every revised version, until the high risk construction work is finished, where workers and inspectors can see it on site. If a notifiable incident happens during the work, keep it for at least 2 years after the incident.

What PPE is needed for steel handrail installation?

Usually Steel cap boots, Welding helmet, Welding gloves, Safety glasses, Hearing protection (earmuffs or plugs), Safety harness and lanyard, Half-face respirator (P2 or P3 filters), Face shield, Overalls, Safety goggles, Cut-resistant gloves, Work gloves. The site rules may add more, so check with the principal contractor.