Demolition · Australia

SWMS for load bearing wall removal

Yes. Load bearing wall removal usually includes high risk construction work (work in an area with movement of powered mobile plant), so a SWMS is required by law before work starts.

It must list the hazards, the controls and how they will be put in place, monitored and reviewed, and the workers must be consulted and sign before starting. The main hazards are silica dust from concrete, brick, stone and tiles, disturbing asbestos, electric shock from live wiring and demolition and falling debris.

SWMS example: load bearing wall removal

This is a complete SWMS for load bearing wall removal, with 6 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.

Safe Work Method Statement (SWMS)
Load-bearing wall removal · Demolition · Example
Document SWMS-001 · Rev 1

High risk construction work covered

Work in an area with movement of powered mobile plant

Job steps, hazards and controls

#Job stepHazardsRisk beforeControlsRisk after
1Get the engineer design for the new beam and temporary propping
  • Structural collapse during alterations
High
  • Get an engineer to check before removing any wall, beam, post or bracing that may be load-bearing. Eliminate
  • Keep everyone clear of the area under and next to the work. Isolate
  • Install temporary props, needles or shoring as designed before removing any support. Engineering
  • Follow the engineer's sequence. Do not change it without approval. Administrative
  • Check props daily. Do not remove them until the permanent support is in and approved. Administrative
  • Install temporary support to the engineer's or temporary works design before any load bearing element is altered. Administrative
  • Wear a hard hat and safety boots. PPE
Medium
2Check for asbestos and isolate any services in the wall
  • Disturbing asbestos
  • Electric shock from live wiring
  • Gas and fuel lines
Extreme
  • Before work, check the asbestos register (workplaces built before 2004). For homes, or if there is no register, have a competent person identify asbestos or assume it is present. Eliminate
  • Seal off the work area and keep everyone else out. Isolate
  • If asbestos must be disturbed, keep it wet, use hand tools not power tools, and clean up with an H-class vacuum. Engineering
  • Friable asbestos (Class A) and more than 10 square metres of non-friable asbestos (Class B) must be removed by a licensed removalist. Administrative
  • Stop work straight away if you find suspect asbestos. Do not touch it and tell your supervisor. Administrative
  • Wear a fitted P2 (or better) respirator and disposable coveralls. PPE
  • Isolate the power before any work. Do not do live work except in the limited cases the WHS Regulations allow (r.157; in Qld, the Electrical Safety Regulation 2013). Eliminate
  • Lock out and tag the isolation point with your own personal lock and danger tag. Isolate
  • Test before you touch: prove dead at the point of work with a voltage tester, proving the tester on a known live source before and after (AS/NZS 4836). Engineering
  • Only licensed electricians do electrical work. Administrative
  • Check for back feeds from solar, batteries and generators that can keep a circuit live after the main switch is off. Administrative
  • Isolate and purge the line before work, with the owner's approval. Eliminate
  • Lock off and tag the isolation valve. Isolate
  • Check for leaks with a gas detector before and during work, and ventilate the area. Engineering
  • Only licensed gasfitters work on gas lines. Administrative
  • Remove ignition sources: no smoking, no hot work and no sparking tools near the line. Administrative
Medium
3Install props and needles before taking anything out
  • Structural collapse during alterations
  • Lifting and carrying heavy loads
High
  • Structural collapse during alterations: see step 1 for the full controls Administrative
  • Plan to avoid carrying: have materials delivered, and old items picked up, as close as possible to where they are used. Eliminate
  • Use lighter or smaller loads: order smaller bags and shorter lengths, and drain or break down old items before moving them. Substitute
  • Lifting and carrying heavy loads: see step 5 for the full controls Administrative
Medium
4Remove the wall in small sections, from the top down
  • Demolition and falling debris
  • Falling tools and materials
  • Silica dust from concrete, brick, stone and tiles
  • Loud noise
Extreme
  • Check for asbestos, lead, live services and structural risks before demolition starts. Eliminate
  • Disconnect and cap power, gas and water before demolition. Isolate
  • Set an exclusion zone bigger than the distance the structure could fall. Isolate
  • Use a machine with a guarded cab instead of hand demolition where practical. Engineering
  • Notify your state WHS regulator before demolition work where required. Administrative
  • Barricade and sign the drop zone under overhead work so nobody walks beneath. Isolate
  • Fit toe boards, kick plates and mesh screens on scaffolds and edges. Engineering
  • Use catch fans, debris netting or covered walkways where people pass below. Engineering
  • Tether hand tools when working at height. Engineering
  • If the job involves engineered stone: do not supply, fabricate or install engineered stone benchtops, panels or slabs (banned since 1 July 2024). Removing, repairing or making minor changes to existing engineered stone is only allowed with water suppression or on-tool extraction, a fitted respirator, and written notice to the regulator before the work starts. Eliminate
  • Order materials cut to size, or use low-dust methods such as score and snap or a block splitter. Substitute
  • Cut outdoors or in a separate area, with other people well away and upwind. Isolate
  • Use water on the blade or on-tool dust extraction connected to an H-class vacuum. Engineering
  • Clean up with a vacuum or wet methods. Never dry sweep or use compressed air. Administrative
  • If the cutting, grinding or drilling is high risk, prepare a silica risk control plan (or include the r.529CA assessment in this SWMS), train workers in silica risks and give them the plan before work starts. Administrative
  • Use quieter tools and methods, such as cut-to-size materials, low-noise machines and battery tools. Substitute
  • Keep noisy plant away from work areas, and use screens or distance between the noise and people. Isolate
  • Keep tools maintained and use mufflers on compressors and generators. Engineering
  • Limit time on noisy tools and rotate workers. Administrative
  • Keep exposure below 85 dB(A) over 8 hours. Give hearing tests to workers who often need hearing protection. Administrative
Medium
5Lift in and fix the new beam with enough people or a lifting aid
  • Lifting and carrying heavy loads
  • Crane and lifting failure
  • Falling from a ladder
High
  • Plan to avoid carrying: have materials delivered, and old items picked up, as close as possible to where they are used. Eliminate
  • Use lighter or smaller loads: order smaller bags and shorter lengths, and drain or break down old items before moving them. Substitute
  • Use trolleys, pallet jacks, hoists, vacuum lifters or plant instead of carrying by hand. Engineering
  • Use a two-person lift for anything heavy, long or awkward. Plan the route first and clear it. Administrative
  • Keep the load close, back straight and no twisting. Turn with your feet. Administrative
  • Barricade the lift zone and keep everyone out from under the load. Isolate
  • Use a crane rated for the load at the radius, set up on firm ground with outrigger pads. Engineering
  • Check slings, chains, shackles and hooks before use. Remove anything damaged or not tagged. Engineering
  • Plan the lift: weight, radius, ground, path and landing area. Use a written lift plan for complex lifts. Administrative
  • Crane operators and doggers or riggers hold the right High Risk Work Licence. Administrative
  • Use a platform ladder, mobile scaffold or EWP for longer jobs instead of a straight ladder. Substitute
  • Use industrial-rated ladders (AS/NZS 1892, 120 kg or more) in good condition. Remove any damaged ladder from site. Engineering
  • Set extension ladders at a 4 to 1 angle on firm, level ground, tied or footed, and reaching 1 metre above the landing. Engineering
  • Use ladders only for short, light work. Do not carry heavy or awkward loads up a ladder. Administrative
  • Keep three points of contact and your belt buckle between the stiles. Do not overreach. Administrative
Medium
6Remove props only after the engineer signs off
  • Structural collapse during alterations
  • Poor housekeeping and waste
High
  • Structural collapse during alterations: see step 1 for the full controls Administrative
  • Order materials to size and send packaging back where you can. Eliminate
  • Put skip bins and waste chutes close to the work. Engineering
  • Clean as you go, and do a full clean up at the end of each day. Administrative
  • Keep exits, stairs and walkways clear at all times. Administrative
  • Stack materials neatly on level ground, away from edges. Administrative
  • Wear gloves when handling waste. PPE
Medium

PPE

Steel cap bootsHard hatSafety glassesP2 dust maskHearing protection (earmuffs or plugs)Work glovesHalf-face respirator (P2 or P3 filters)OverallsHi-vis shirt or vest

Plant and equipment

Hand toolsCircular sawJackhammerPlatform ladder

Permits and plans

Lift plan

Emergency

Call 000. Add the nearest hospital, the assembly point and the first aider for your site.

Sign-off

Supervisor and every worker sign to confirm they have read and understood this SWMS.

Free SWMS template for load bearing wall removal

Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.

Make yours in 2 minutes

Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.

Start this SWMS

Pre-start checklist for load bearing wall removal

Tick these off before work starts. They come from the hazards, permits and equipment in this job.

The safe sequence of work

  1. Get the engineer design for the new beam and temporary propping
  2. Check for asbestos and isolate any services in the wall
  3. Install props and needles before taking anything out
  4. Remove the wall in small sections, from the top down
  5. Lift in and fix the new beam with enough people or a lifting aid
  6. Remove props only after the engineer signs off

Hazards to watch on load bearing wall removal

The hazards most specific to this job, and the step where each one comes up.

Step 4Demolition and falling debrisPart of a structure collapses early, or debris falls and hits workers or the public during demolition or strip out.
Step 5Crane and lifting failureA load falls or swings, or the crane tips, crushing workers under or near the lift.
Step 2Gas and fuel linesDamaging or opening a gas or fuel line causes a leak, fire or explosion.
Step 1, 3, 6Structural collapse during alterationsRemoving a wall, beam, post or bracing makes part of the building fall on workers.
Step 2Disturbing asbestosBuildings built before 1990 are likely to contain asbestos, and any built before 2004 may. Drilling, cutting or breaking it releases fibres that cause cancer years later.
Step 5Falling from a ladderThe ladder slips or tips, or the worker overreaches, and they fall onto a hard surface.
Almost certainLikelyPossibleUnlikelyRareHow bad it could be: Insignificant to CatastrophicBA
Highest risk on load bearing wall removal: Extreme before controls (B), down to Medium after controls (A), on the Australia 5 by 5 risk matrix (likely and catastrophic becomes unlikely and major).

What changes on your site

This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):

  • Will anyone work more than 2 metres off the ground?
  • Will anyone work on a roof?
  • Is there a skylight, clear sheet, fibro or other fragile roofing?
  • Will you use a scaffold or mobile tower?
  • Will you use an EWP (scissor lift or boom lift)?

Licences and legal requirements in Australia

This task can involve these high risk construction work categories under the WHS Regulations:

  • Work in an area with movement of powered mobile plant

A SWMS must be prepared before any high risk construction work starts. It must list the high risk work, the hazards and risks, the control measures, and how those controls will be put in place, monitored and reviewed. It must be easy for the workers to read and understand.

Rules that apply: WHS Regulations, Chapter 8 (Asbestos); WHS Regulation 2011, Part 4.7 General electrical safety; WHS Regulation 2011, Part 4.2 Hazardous manual tasks; WHS Regulation 2011, Part 3.2 (falling objects); WHS Regulations, Chapter 8A (Crystalline silica substances and engineered stone); WHS Regulation 2011, Part 4.1 Noise; WHS Regulation 2011, Part 4.5 High risk work and Part 5.1 Plant; WHS Regulation 2011, Part 4.4 Falls.

Each state has its own regulator and some extra rules: New South Wales, Victoria, Queensland, Western Australia, South Australia and Australian Capital Territory.

Why SWMS get rejected

Principal contractors send documents back for these reasons. This example avoids them, but check yours too.

  • It is generic: another site address, tasks that are not on this job, or no sign it was reviewed for this site. WorkSafe WA says a generic SWMS may not meet the regulations unless it is reviewed and amended for the workplace.
  • The HRCW boxes are not ticked, or the ticks do not match the tasks (for example a roof job with no falls box ticked).
  • Falls are controlled only by "be careful", training or a harness, with no edge protection or scaffold and no reason why higher controls are not reasonably practicable.
  • Workers will clip on to a harness but there is no rescue plan for someone left hanging.
  • The "how controls are implemented, monitored and reviewed" part is missing, or it says the same thing on every row.
  • No worker sign-on, no person responsible for compliance, or a date given to the principal contractor that is before they actually received it.
  • Licence or White Card details are missing for workers operating plant or doing licensed high risk work.

Questions

Do I need a SWMS for load bearing wall removal?

Yes. Load bearing wall removal usually includes high risk construction work (work in an area with movement of powered mobile plant), so a SWMS is required by law before work starts.

Who signs the SWMS?

The person conducting the business (PCBU) or their supervisor prepares it with the workers, and every worker doing the high risk work signs to show they were consulted and understand it. Give a copy to the principal contractor before work starts.

How long do I keep it?

Keep this SWMS, and every revised version, until the high risk construction work is finished, where workers and inspectors can see it on site. If a notifiable incident happens during the work, keep it for at least 2 years after the incident.

What PPE is needed for load bearing wall removal?

Usually Steel cap boots, Hard hat, Safety glasses, P2 dust mask, Hearing protection (earmuffs or plugs), Work gloves, Half-face respirator (P2 or P3 filters), Overalls, Hi-vis shirt or vest. The site rules may add more, so check with the principal contractor.