SWMS for rooftop package unit replacement

Yes. Rooftop package unit replacement usually includes high risk construction work (risk of a person falling more than 2 metres; work on or near chemical, fuel or refrigerant lines), so a SWMS is required by law before work starts.

It must list the hazards, the controls and how they will be put in place, monitored and reviewed, and the workers must be consulted and sign before starting. The main hazards are falling from a roof edge, falling through a fragile roof or skylight, electric shock from live wiring and public entering the work area.

SWMS example: rooftop package unit replacement

This is a complete SWMS for rooftop package unit replacement, with 6 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.

Safe Work Method Statement (SWMS)
Rooftop unit replacement · Air conditioning and refrigeration · Example
Document SWMS-001 · Rev 1

High risk construction work covered

Risk of a person falling more than 2 metresWork on or near chemical, fuel or refrigerant linesWork on or near energised electrical installations or servicesWork in an area with movement of powered mobile plant

Job steps, hazards and controls

#Job stepHazardsRisk beforeControlsRisk after
1Plan the crane lift and close the area below
  • Crane and lifting failure
  • Public entering the work area
  • Contact with overhead power lines
High
  • Barricade the lift zone and keep everyone out from under the load. Isolate
  • Use a crane rated for the load at the radius, set up on firm ground with outrigger pads. Engineering
  • Check slings, chains, shackles and hooks before use. Remove anything damaged or not tagged. Engineering
  • Plan the lift: weight, radius, ground, path and landing area. Use a written lift plan for complex lifts. Administrative
  • Crane operators and doggers or riggers hold the right High Risk Work Licence. Administrative
  • Fence off the site with secure temporary fencing and lock the gates when you leave. Isolate
  • Give pedestrians a safe, marked path around the work, with ramps for prams and wheelchairs. Isolate
  • Use hoarding, covered walkways or catch fans where work is above public areas. Engineering
  • Put signs at each entry: site name, contact number and "No unauthorised entry". Administrative
  • Make the site safe at the end of each day: cover holes, lower plant, remove ladders and lock tools away. Administrative
  • Ask the network operator to turn off, move or insulate the lines before work starts. Eliminate
  • Use non-conductive (fibreglass) ladders near any power lines. Substitute
  • Mark the safe distance with flags, tape or goal posts and keep all plant and people outside it. Isolate
  • Keep out of the No Go Zone set by your state and the network operator, or get written approval and a safety observer. In NSW and Qld, untrained people and plant stay at least 3 m from lines on poles up to 132 kV, 6 m up to 330 kV and 8 m above 330 kV. In Victoria the limits differ, and work within 8 m of tower lines needs a spotter and the network operator's permission. Administrative
  • Use a dedicated spotter whenever plant moves or raises anything near lines. Administrative
  • Treat all lines as live. If plant touches a line, stay in the cab and keep everyone well away. Administrative
Medium
2Set up roof edge protection or harness anchors
  • Falling from a roof edge
  • Falling through a fragile roof or skylight
Extreme
  • Do what you can from the ground or from a scaffold at the gutter line, for example pre-assemble parts on the ground. Eliminate
  • Install edge protection or guardrails on all open roof edges before work starts. Isolate
  • Use a perimeter scaffold with handrails and toe boards along the eaves where practical. Engineering
  • Where guardrails cannot be fitted, use fall restraint on certified roof anchors so workers cannot reach the edge. Engineering
  • Only workers briefed on this SWMS go on the roof. Stop and review the SWMS if the roof, weather or method changes. Administrative
  • Use one safe, controlled access point and keep others off the roof. Administrative
  • Stop roof work in strong wind or rain, and when the roof is wet, icy or covered in dust or frost. Administrative
  • Have a written emergency and rescue plan, tested before work starts, for any worker using a harness (WHS Regulations r.80). Administrative
  • Wear a harness clipped to a rated anchor when using restraint or fall arrest, and soft-soled non-slip boots. PPE
  • Work from underneath or from an EWP so nobody stands on the fragile roof. Eliminate
  • Cover or guard every skylight and fragile sheet with a fixed, marked cover or mesh before work starts. Isolate
  • Install safety mesh under new roof sheeting, and use crawl boards or staging to spread the load on fragile surfaces. Engineering
  • Use fall arrest on rated anchors when working near fragile areas. Engineering
  • Treat all roof sheets as fragile until a competent person confirms they are not. Old fibre cement and plastic sheets are fragile. Administrative
  • Put "Fragile roof" signs at every roof access point. Administrative
  • Never walk on sheets between purlins or along skylights. Stay on boards or staging. Administrative
  • Wear a full body harness clipped to a rated anchor. PPE
Medium
3Isolate power and gas, lock out and danger tag
  • Electric shock from live wiring
  • Gas and fuel lines
Extreme
  • Isolate the power before any work. Do not do live work except in the limited cases the WHS Regulations allow (r.157; in Qld, the Electrical Safety Regulation 2013). Eliminate
  • Lock out and tag the isolation point with your own personal lock and danger tag. Isolate
  • Test before you touch: prove dead at the point of work with a voltage tester, proving the tester on a known live source before and after (AS/NZS 4836). Engineering
  • Only licensed electricians do electrical work. Administrative
  • Check for back feeds from solar, batteries and generators that can keep a circuit live after the main switch is off. Administrative
  • If live work cannot be avoided, use a permit, a safety observer and insulated tools. Administrative
  • Wear insulated gloves, arc-rated clothing and a face shield when testing or working near live parts. PPE
  • Isolate and purge the line before work, with the owner's approval. Eliminate
  • Lock off and tag the isolation valve. Isolate
  • Check for leaks with a gas detector before and during work, and ventilate the area. Engineering
  • Only licensed gasfitters work on gas lines. Administrative
  • Remove ignition sources: no smoking, no hot work and no sparking tools near the line. Administrative
  • Know where the shut-off valve is and what to do if a leak happens. Administrative
  • Wear safety glasses and gloves, and keep a fire extinguisher close by. PPE
Medium
4Recover refrigerant before disconnecting
  • Refrigerant leaks
Medium
  • Recover refrigerant into an approved cylinder before opening the system. Never vent it. Isolate
  • Ventilate closed spaces and use a leak detector during the work. Engineering
  • Only holders of a refrigerant handling licence (ARCtick) work on refrigerant systems. Administrative
  • Check the licence covers the job: the restricted split licence only covers single-head splits under 18 kW, and adding refrigerant needs an ARC Refrigerant Trading Authorisation (RTA) for the business. Administrative
  • With flammable refrigerants (such as R32 or R290), remove ignition sources and use spark-free tools. Administrative
  • Wear cold-rated gloves and safety glasses or a face shield. PPE
Low
5Lift out the old unit and set the new one, keeping clear of the load
  • Crane and lifting failure
  • Falling tools and materials
  • Strong wind and storms
High
  • Use tag lines to control loads and agree on clear radio or hand signals. Administrative
  • Stop lifting in high wind or when the operator cannot see the signaller. Administrative
  • Never ride on a load or hook. Administrative
  • Crane and lifting failure: see step 1 for the full controls Administrative
  • Barricade and sign the drop zone under overhead work so nobody walks beneath. Isolate
  • Fit toe boards, kick plates and mesh screens on scaffolds and edges. Engineering
  • Use catch fans, debris netting or covered walkways where people pass below. Engineering
  • Tether hand tools when working at height. Engineering
  • Keep platforms tidy. Do not stack materials near edges or above toe board height. Administrative
  • Check the forecast each morning and plan work at height and lifting around the weather. Eliminate
  • Tie down or weigh down loose sheets, panels, boards and rubbish at the end of each shift. Engineering
  • Set wind limits for roof work, platforms and cranes, using the manufacturer's limits, and stop when they are reached. Administrative
  • Stop work and get down in lightning. Wait 30 minutes after the last thunder before going back up. Administrative
  • Check scaffold, fencing and edge protection after strong wind before anyone uses them. Administrative
Medium
6Connect, commission and clean the roof
  • Electric shock from live wiring
  • Poor housekeeping and waste
Extreme
  • Electric shock from live wiring: see step 3 for the full controls Administrative
  • Order materials to size and send packaging back where you can. Eliminate
  • Put skip bins and waste chutes close to the work. Engineering
  • Clean as you go, and do a full clean up at the end of each day. Administrative
  • Keep exits, stairs and walkways clear at all times. Administrative
  • Stack materials neatly on level ground, away from edges. Administrative
  • Wear gloves when handling waste. PPE
Medium

PPE

Steel cap bootsHard hatSafety harness and lanyardHi-vis shirt or vestWork glovesSafety glassesSun protection (brim hat, long sleeves, SPF 50+)Insulated electrical glovesArc-rated clothing and face shieldFace shield

Plant and equipment

Crane (Franna or mobile): HRWL for the crane class (e.g. C2, CN, C6), plus Dogging licence (DG) where slinging needs judgement or the load is out of the operator's viewHand toolsElectrical test equipmentExtension ladder

Permits and plans

Lift planRoof access permitWorking at heights permitElectrical isolation permit

Emergency

Call 000. Add the nearest hospital, the assembly point and the first aider for your site.

Sign-off

Supervisor and every worker sign to confirm they have read and understood this SWMS.

Free SWMS template for rooftop package unit replacement

Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.

Make yours in 2 minutes

Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.

Start this SWMS

Pre-start checklist for rooftop package unit replacement

Tick these off before work starts. They come from the hazards, permits and equipment in this job.

The safe sequence of work

  1. Plan the crane lift and close the area below
  2. Set up roof edge protection or harness anchors
  3. Isolate power and gas, lock out and danger tag
  4. Recover refrigerant before disconnecting
  5. Lift out the old unit and set the new one, keeping clear of the load
  6. Connect, commission and clean the roof

Hazards to watch on rooftop package unit replacement

The hazards most specific to this job, and the step where each one comes up.

Step 4Refrigerant leaksRefrigerant gas causes frostbite, pushes oxygen out of small rooms, and some types catch fire.
Step 2Falling through a fragile roof or skylightA worker steps on a skylight, clear sheet or old fibre cement roof and falls through to the floor below.
Step 1, 5Crane and lifting failureA load falls or swings, or the crane tips, crushing workers under or near the lift.
Step 1Contact with overhead power linesA ladder, EWP, crane, tipper or long length of material touches or gets close to an overhead line and electrocutes people.
Step 3Gas and fuel linesDamaging or opening a gas or fuel line causes a leak, fire or explosion.
Step 5Strong wind and stormsWind blows sheets, panels and people off roofs and scaffolds, and storms and lightning make work at height and lifting unsafe.
Almost certainLikelyPossibleUnlikelyRareHow bad it could be: Insignificant to CatastrophicBA
Highest risk on rooftop package unit replacement: Extreme before controls (B), down to Medium after controls (A), on the Australia 5 by 5 risk matrix (likely and catastrophic becomes unlikely and major).

What changes on your site

This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):

  • Will anyone work more than 2 metres off the ground?
  • Will anyone use a ladder or stepladder?
  • Will anyone work on a roof?
  • Will you use a scaffold or mobile tower?
  • Will you use an EWP (scissor lift or boom lift)?

Licences and legal requirements in Australia

This task can involve these high risk construction work categories under the WHS Regulations:

  • Risk of a person falling more than 2 metres
  • Work on or near chemical, fuel or refrigerant lines
  • Work on or near energised electrical installations or services
  • Work in an area with movement of powered mobile plant

Equipment on this job that needs a licence, ticket or training:

  • Crane (Franna or mobile): HRWL for the crane class (e.g. C2, CN, C6), plus Dogging licence (DG) where slinging needs judgement or the load is out of the operator's view

A SWMS must be prepared before any high risk construction work starts. It must list the high risk work, the hazards and risks, the control measures, and how those controls will be put in place, monitored and reviewed. It must be easy for the workers to read and understand.

Rules that apply: WHS Regulation 2011, Part 4.5 High risk work and Part 5.1 Plant; WHS Regulation 2011, Part 4.4 Falls; WHS Regulation 2011, Part 4.7 General electrical safety; Ozone Protection and Synthetic Greenhouse Gas Management Act 1989; WHS Regulation 2011, Part 3.2 (falling objects).

Each state has its own regulator and some extra rules: New South Wales, Victoria, Queensland, Western Australia, South Australia and Australian Capital Territory.

Why SWMS get rejected

Principal contractors send documents back for these reasons. This example avoids them, but check yours too.

  • It is generic: another site address, tasks that are not on this job, or no sign it was reviewed for this site. WorkSafe WA says a generic SWMS may not meet the regulations unless it is reviewed and amended for the workplace.
  • The HRCW boxes are not ticked, or the ticks do not match the tasks (for example a roof job with no falls box ticked).
  • Falls are controlled only by "be careful", training or a harness, with no edge protection or scaffold and no reason why higher controls are not reasonably practicable.
  • Workers will clip on to a harness but there is no rescue plan for someone left hanging.
  • The "how controls are implemented, monitored and reviewed" part is missing, or it says the same thing on every row.
  • No worker sign-on, no person responsible for compliance, or a date given to the principal contractor that is before they actually received it.
  • Licence or White Card details are missing for workers operating plant or doing licensed high risk work.

Questions

Do I need a SWMS for rooftop package unit replacement?

Yes. Rooftop package unit replacement usually includes high risk construction work (risk of a person falling more than 2 metres; work on or near chemical, fuel or refrigerant lines), so a SWMS is required by law before work starts.

Who signs the SWMS?

The person conducting the business (PCBU) or their supervisor prepares it with the workers, and every worker doing the high risk work signs to show they were consulted and understand it. Give a copy to the principal contractor before work starts.

How long do I keep it?

Keep this SWMS, and every revised version, until the high risk construction work is finished, where workers and inspectors can see it on site. If a notifiable incident happens during the work, keep it for at least 2 years after the incident.

What PPE is needed for rooftop package unit replacement?

Usually Steel cap boots, Hard hat, Safety harness and lanyard, Hi-vis shirt or vest, Work gloves, Safety glasses, Sun protection (brim hat, long sleeves, SPF 50+), Insulated electrical gloves, Arc-rated clothing and face shield, Face shield. The site rules may add more, so check with the principal contractor.

More air conditioning and refrigeration SWMS

Related jobs in other trades

Toolbox talks for this job

Blank SWMS template: free SWMS templates. Also for other countries: United Kingdom (RAMS) · United States (JHA) · Canada (FLHA)

Sources